HomeMy WebLinkAboutC2013-012 - 1/29/2013 - ApprovedCITY OF CORPUS CHRISTI
CONTRACT FOR PROFESSIONAL SERVICES
The City of Corpus Christi, a Texas home rule municipal corporation, P.O. Box 9277,
Corpus Christi, Nueces County, Texas 78469 -9277 (City) acting through its duly authorized
City Manager or Designee (Director of Engineering Services) and Govind Development,
LLC a Texas corporation, 9359 IH 37, Suite A, Corpus Christi, Nueces County, Texas
78409, (Architect/Engineer -- A/E), hereby agree as follows:
1. SCOPE OF PROJECT
Greenwood_ Drive from Gollihar Road to Horne Road ( Proiect No. E12092) BOND
ISSUE 2012 -- The scope of this project includes full -depth repair and widening the existing
five lane roadway (four travel lanes and continuous center left turn lane). The existing
travel lanes will be widened and reconstructed to meet the requirements of the UTMP A -1
Arterial designation. Other street improvements include curb and gutter, wide sidewalks,
ADA curb ramps, lane striping and pavement markings, and bus stop rehabilitation.
2. SCOPE OF SERVICES
The A/E hereby agrees, at its own expense, to perform design services necessary to
review and prepare plans, specifications, and bid and contract documents. In addition, A/E
will provide monthly status updates (project progress or delays, gantt charts presented with
monthly invoices) and provide contract administration services, as described in Exhibit "A"
and "A -1 ", to complete the Project. Work will not begin on Additional Services until
requested by the A/E (provide breakdown of costs, schedules), and written authorization is
provided by the Director of Engineering Services.
A/E services will be "Services for Construction Projects " - (Basic Services for Construction
Projects ") which are shown and are in accordance with "Professional Engineering Services -
A Guide to the Selection and Negotiation Process, 1993" a joint publication of the
Consulting Engineer's Council of Texas and Texas Society of Professional Engineers. For
purposes of this contract certain services listed in this publication as Additional Services
will be considered as Basic Services.
3. ORDER OF SERVICES
The A/E agrees to begin work on those authorized Basic Services for this contract upon
receipt of the Notice to Proceed from the Director of Engineering Services. Work will not
begin on any phase or any Additional Services until requested in writing by the A/E and
written authorization is provided by the Director of Engineering Services. The anticipated
schedule of the preliminary phase, design phase, bid phase, and construction phase is
shown on Exhibit "A ". This schedule is not to be inclusive of all additional time that may
be required for review by the City staff and may be amended by or with the concurrence of
the Director of Engineering Services.
2013 -012 Contract for Engineering (A/E) Services
1129113 Page 1 of 3
y 15TREET4E42092 GREENWOOD FROM GOLLIHAR TO HORNE BOND ISSUE 20125CONSULTANT CONTRACT GOVIND
M2013 -014AL sERVICES.DOC
Govind Development LLC
, 4 I I I , . I , C I F
The Director of Engineering Services may direct the A/E to undertake additional services or
tasks provided that no increase in fee is required. Services or tasks requiring an increase
of fee will be mutually agreed and evidenced in writing as an amendment to this contract.
A/E shall notify the City of Corpus Christi within three (3) days of notice if tasks requested
requires an additional fee.
4. INDEMNITY AND INSURANCE
A/E agrees to the mandatory contract indemnification and insurance requirements as set
forth in Exhibit "B ".
5. FEE
The City will pay the A/E a fee, as described in Exhibit "A ", for providing services
authorized, a total fee not to exceed $390,773.00, (Three Hundred Ninety Thousand
Seven Hundred Seventy_ Three Dollars and Zero Cents) Monthly invoices will be
submitted in accordance with Exhibit "C ".
6. TERMINATION OF CONTRACT
The City may, at any time, with or without cause, terminate this contract upon seven days
written notice to the A/E at the address of record. In this event, the A/E will be
compensated for its services on all stages authorized based upon A/E and City's estimate
of the proportion of the total services actually completed at the time of termination.
7. LOCAL PARTICIPATION
The City Council's stated policy is that City expenditures on contracts for professional
services be of maximum benefit to the local economy. The A/E agrees that at least 75% of
the work described herein will be performed by a labor force residing within the Corpus
Christi Metropolitan Statistical Area (MSA). Additionally, no more than 25% of the work
described herein will be performed by a labor force residing outside the Corpus Christi
Metropolitan Statistical Area (MSA.)
8. ASSIGNABILITY
The A/E will not assign, transfer or delegate any of its obligations or duties in this contract
to any other person without the prior written consent of the City, except for routine duties
delegated to personnel of the A/E staff. If the A/E is a partnership, then in the event of the
termination of the partnership, this contract will inure to the individual benefit of such
partner or partners as the City may designate. No part of the A/E fee may be assigned in
advance of receipt by the A/E without written consent of the City.
The City will not pay the fees of expert or technical assistance and consultants unless such
employment, including the rate of compensation, has been approved in writing by the City.
Contract for Engineering (AIE) Services
Page 2 of 3
KAENGINEERING DATAEXCHANGOVELMAPLSTREE RE12092 GREENWOOD FROM GOLLIHAR TO HORNE BOND ISSUE 20121CONSULTANT CONTRACT GOVIND
DEVELOPMENT51 CONTRACT PROFESSIONAL SERVICES, DOC
.
9. OWNERSHIP OF DOCUMENTS
P
All documents including contract documents (plans and specifications), record drawings,
contractor's field data, and submittal data will be the sole property of the City, may not be
used again by the AIE without the express written consent of the Director of Engineering
Services. However, the AIE may use standard details that are not specific to this project.
The City agrees that any modification of the plans will be evidenced on the plans, and be
signed and sealed by a professional engineer prior to re -use of modified plans.
10. DISCLOSURE OF INTEREST
AIE further agrees, in compliance with City of Corpus Christi Ordinance No. 17112, to
complete, as part of this contract, the Disclosure of Interests form.
CITY OF CORPUS CHRISTI
Oscar R. Martinez, Date
Assistant City Manager
RECOMMENDED
Daniel Biles, P. E., Date
Director of Engineering Services
G VIN EVELOPMENT, LLC
��.13.�.Q!48'u I nu Li.-
I �
APPRO ED AS TO FORM
Office of Management ate
and Budget
Street Fund 3549 Bond 12 GO
WasteWater 4251 2012A CIP Fund
StorrnWater 3496 2012B CIP Fund
Water 4092 2012B CIP Fund
ATTEST
Armando Chapa, Cit Secretary
��`,°
%amWw VW%o L.PiJVW nai111 %J011inar Rugg io norne Koaa
' e Ct N o. hlZ09Z
Department
Fund Source No.
Amount
Street
550950 - 3549 - 00000 -E 12092
$182, 545.00
Wastewater
550950.4251- 00000 -E 12092
53,877.00
Storm Water
550950- 3496- 00000- E12092
108,949.00
Water
550950 -4092- 00000- E12092
45,402.00
Total
$390,773.00
Encumbrance No.
l�-
Ramiro u II, P. E., ate
Vice Presid nt
9359 1H 37, Suite A
Corpus Christi, TX 78409
(361) 241 -2777 Office
(361) 241 -2200 Fax
SEG`ilETAitr
Contract for Engineering (AIE) Services
KIENGINEERING DATAEXCHANGEIVELMAPISTREETIE12092 GREENWOOD FROM GOLLIHAR TO HORNE BOND ISSUE 20125CONSULTANTCONT Page 3 of 3
RACT GOVIND
DEVELOPMENT11 CONTRACT PROFESSIONAL SERVICES.DOC
EXHIBIT "A"
CITY OF CORPUS CHRISTI, TEXAS
GREENWOOD DRIVE FROM GOLLIHAR ROAD TO HORNE ROAD
PROJECT NUMBER NO. E12092
BOND ISSUE 2012
SCOPE OF SERVICES
A. BASIC SERVICES
For the purpose of this contract, Preliminary Phase may include Schematic Design and Design
Phase services may include Design Development as applicable to Architectural services.
1.
Preliminary Phase. The Arch itect/Engineer -AIE (also referred to as Consultant) will:
a)
Prepare Powerpoint presentation in City format for City Council Meeting.
b)
Hold Project Kick -off Meeting. Prepare meeting agenda and distribute meeting
meetings to attendees within seven working days of the meeting.
c)
Provide scope of geotechnical testing requirements to the City's Geotechnical
Consultant.
d)
Review available reports, record drawings, utility maps and other information
provided by the City pertaining to the project area.
e)
Develop preliminary requirements for utility relocations replacements or upgrades.
Coordinate with the City's Project Manager and identify operating departments
potential project needs.
f)
Develop preliminary street cross section to incorporate the Geotechnical
Consultant's recommendations. Prepare conceptual life -cycle cost estimate with
recommended pavement sections.
g)
Identify right -of -way acquisition requirements and illustrate on a schematic strip map.
h)
Prepare preliminary opinions of probable construction costs for the recommended
improvements.
i)
Develop drainage area boundary map for existing and proposed drainage areas
served.
j)
Conduct the hydraulic analysis to quantify the storm sewer design of existing and
proposed systems. Include the analysis of inlet capacity.
k)
Identify electric and communication utility companies and private pipeline companies
that may have existing facilities and must relocated to accommodate the proposed
improvements.
1)
Coordinate with AEP and City Traffic Engineering to identify location of electrical
power conduit for street lighting and traffic signalization.
m)
Identify and analyze requirements of governmental authorities having jurisdiction to
approve design of the Project including permitting, environmental, historical,
construction, and geotechnical issues; upon request or concurrence of the Project
Manager, meet and coordinate with agencies such as RTA, USPS, CCISD TDLR.
n)
Identify and recommend public outreach and community stakeholder requirements.
o)
Prepare an Engineering Letter Report (20 — 25 page main -body text document with
supporting appendices) that documents the analyses, approach, opinions of
probable construction costs, and document the work with text, tables, schematic -
level exhibits and computer models or other applicable supporting documents
required per City Plan Preparation Standards Contract Format
(CPPSCF).Engineering Letter Report to include:
1. Provide a concise presentation of pertinent factors, sketches, designs, cross -
sections, and parameters which will or may impact the design, including
EXHIBIT " A "
Page 1 of 9
Revised December 13, 2012
K3Engineering DataExchangelVELMAPISTREET1E12092 GREENWOOD FROM GOLLIHAR TO HORNE BOND ISSUE 20121CONSULTANT CONTRACT govind developmenA2 EXHIBIT A LARGE AE
REVISED Nov13 2012.doc
engineering design basis, preliminary layout sketches, construction
sequencing, alignment, cross section, geotechnical testing report, right -of-
way requirements, conformance to master plans, identification of needed
additional services, identification of needed permits and environmental
consideration, existing and proposed utilities, identification of quality and
quantity of materials of construction, and other factors required for a
professional design.
2. Include existing site photos.
3. Provide opinion of probable construction costs.
4. Identify and analyze requirements of governmental authorities having
jurisdiction to approve design of the Project including permitting,
environmental, historical, construction, and geotechnical issues; meet and
coordinate with agencies such as RTA, USPS, CC1SD, TDLR.
5. Provide an analysis on project impacts towards "re- engineering" and effects
on cost savings toward City operations, which this project will affect.
6. Provide anticipated index of drawings and specifications.
P) Submit one (1) copy in an approved electronic format, and one (1) paper copy of the
Draft Engineering Letter Report (30% Submittal).
q) Hold Project review meeting with City staff to review and receive City comments on
the Draft Engineering Letter Report.
r) Assimilate all review comments of the Draft Engineering Letter Report and provide
one (1) set of the Final Engineering Letter Report (ELR) (electronic and hard
copies using City Standards as applicable) suitable for reproduction.
S) Assist City in presenting summary of ELR findings to City - appointed capital project
oversight committee having responsible charge of vetting preliminary project design
components prior to proceeding to project design phase. Prepare Powerpoint
presentation, handouts and exhibits for meeting. Provide follow -up and response to
comments.
City staff will provide one set only of the following information (as applicable):
a) Record drawings, record information of existing facilities, and utilities (as available
from City Engineering files).
b) The preliminary budget, specifying the funds available for construction.
C) A copy of existing studies and plans. (as available from City Engineering files).
d) Field location of existing city utilities. (A/E to coordinate with City Operating
Department.
e) Applicable Master Plans and GIS mapping are available on the City's website.
f) Provide bench marks and coordinates.
g) Aerial Photography for the Project Area
h) Provide all required data for input into life -cycle cost analysis.
The records provided for A/E's use under this contract are proprietary, copyrighted, and
authorized for use only by A /E, and only far the intended purpose of this project. Any
unauthorized use or distribution of the records provided under this contract is strictly prohibited.
2. Design Phase Upon approval of the preliminary phase, designated by receiving
authorization to proceed, the A/E will:
a) Provide coordination with electric and communication utility companies and private
pipeline companies that may have existing facilities and must relocated to
accommodate the proposed improvements.
:EXHIBIT "A"
age 2 of 9
Revd Deoember 13, 2012
K4Engineering DataExcharnge \VELMARSTREET1E12092 GREENWOOD FROM GOLLIHAR TO HORNE BOND ISSUE 201MCONSULTANT CONTRACT govind developmentl2 EXHIBIT A LARGE AE
REVISED Nov13 2012.doc
b) Provide assistance to identify testing, handling and disposal of any hazardous
materials and /or contaminated soils that may be discovered during construction (to
be included under additional services).
C) Prepare construction documents in City standard format for the work identified in the
approved ELR. Construction plans to include improvements or modifications to the
storm water, water and wastewater systems within the project limits. Include
standard City of Corpus Christi detail sheets as appropriate.
d) Prepare construction plans in compliance with CPPSCF using English units on 24 "x
36" plan sheets that can be reduced to 11 "x 17 ".
1. Prepare Traffic Control and Construction Sequencing Plans. The TCP will
include construction sequencing, typical cross section and construction
phasing plan sheets, warning and barricades, as well as standards sheets for
barricades, traffic control plan, work zone pavement markings and signage.
2. Provide Storm Water Pollution Prevention Plan, including construction
drawings.
e) Furnish one (1) set of the interim plans (60% submittal - electronic and full -size
hard copies using City Standards as applicable) to the City staff for review and
approval purposes with estimates of probable construction costs. Identify distribution
list for plans and bid documents to all affected franchise utilities.
1. Required with the interim plans is a " Plan Executive Summary which will
identify and summarize the project by distinguishing key elements and
opinion of probable project costs.
f) Hold Project 60% review meeting. Prepare meeting agenda and distribute meeting
meetings to attendees within seven working days of the meeting. Assimilate all
review comments, as appropriate and, upon Notice to Proceed.
g) Provide one (1) set of the final (100 %) plans (unsealed and unstamped - electronic
and full -size hard copies using City Standards as applicable) for City's final review.
h) Assimilate all final review comments Upon approval by the Director of Engineering
Services, provide one (1) set of the final plans and contract documents
(electronic and full -size hard copies using City Standards as applicable) suitable for
reproduction. Said bid documents henceforth become the shared intellectual
p ro p erty of the City of Car us Christi and the Consultant. The City agrees that any
modifications of the submitted final plans (for other uses by the City) will be
evidenced on the plans and be signed and sealed by a professional engineer prior to
re -use of modified plans.
i) Provide Quality Assurance /Quality Control (QA/QC) measures to ensure that
submittal of the interim, pre -final (if required), and final complete plans and complete
bid documents with specifications accurately reflect the percent completion
designated and do not necessitate an excessive amount of revision and correction
by City. Additional revisions or design submittals are required (and within the scope
of Consultant's duties under this contract if, in the opinion of the City Engineer or
designee, Consultant has not adequately addressed City- provided review comments
or provided submittals in accordance with City standards.
D Prepare and submit monthly status reports to the Project Manager no later than the
last Wednesday of each month with action items developed from monthly progress
and review meetings.
k) Provide copy of contract documents along with appropriate fee to Texas Department
of Licensing and Regulation (TDLR) for review and approval of accessibility
requirements for pedestrian improvements (as authorized by Additional Services).
:EXHIBIT "A"
age 3 of 9
Revd December 13, 2012
KlEngineering DataExchangelVELMAPISTREET1E12092 GREENWOOD FROM GOLLIHAR TO HORNE BOND ISSUE 20121CONSULTANT CONTRACT govind developmentt2 EXHIBIT A LARGE AE
REVISED Nov13 2012.doe
The City staff will:
a) Designate an individual to have responsibility, authority, and control for coordinating
activities for the construction contract awarded.
b) Provide the budget forthe Project specifying the funds available for the construction
contract.
c) Provide the City's standard specifications, standard detail sheets, standard and
special provisions, and forms for required bid documents.
3. Bid Phase The A/E will:
a) Participate in the pre -bid conference and provide a meeting agenda for critical
construction activities and elements impacted the project.
b) Assist the City in solicitation of bids by identification of prospective bidders, and
review of bids by solicited interests.
c) Review all pre -bid questions and submissions concerning the bid documents and
prepare, in the City's format, for the Engineering Services' approval, any addenda or
other revisions necessary to inform contractors of approved changes prior to bidding.
d) Attend bid opening, analyze bids, evaluate, prepare bid tabulation, and make
recommendation concerning award of the contract.
e) In the event the lowest responsible bidder's bid exceeds the project budget as
revised by the Engineering Services in accordance with the A/E's design phase
estimate required above, the Engineer will, at its expense, confer with City staff and
make such revisions to the bid documents as the City staff deems necessary to re-
advertise that particular portion of the Project for bids.
f} Prepare Powerpoint presentation in City format for City Council Meeting.
The City staff will:
a) Arrange and pay for printing of all documents and addenda to be distributed to
prospective bidders.
b) Advertise the Project for bidding, maintain the list of prospective bidders, receive and
process deposits for all bid documents, issue (with the assistance of the A/E) any
addenda, prepare and supply bid tabulation forms, and conduct bid opening.
C) Receive the Engineer's recommendation concerning bid evaluation and
recommendation and prepare agenda materials for the City Council concerning bid
awards.
d) Prepare, review and provide copies of the contract for execution between the City
and the contractor.
4. Construction Administration Phase The AIE will perform contract administration to
include the following:
a) Participate in pre - construction meeting conference and provide a recommended
agenda for critical construction activities and elements impacted the project.
b) Review, Contractor submittals and operating and maintenance manuals for
conformance to contract documents.
c) Review and interpret field and laboratory tests.
d) Provide interpretations and clarifications of the contract documents for the contractor
and authorize required changes, which do not affect the contractor's price and are
not contrary to the general interest of the City under the contract.
e) Make regular visits to the site of the Project to confer with the City project inspector
and contractor to observe the general progress and quality of work, and to
determine, in general, if the work is being done in accordance with the contract
EXHIBIT "A"
Page 4 of 9
Revised December 13, 2p12
K:1Engineering DalaExchange %VELMAPISTREET4E12092 GREENWOOD FROM GOLLIHAR TO HORNE BOND ISSUE 20121CONSULTANT CONTRACT govind developmenA2 EXHIBIT A LARGE AE
REVISED Nov13 2012.doc
documents. This will not be confused with the project representative observation or
continuous monitoring of the progress of construction.
f) Prepare change orders as authorized by the City; provide interpretations and
clarifications of the plans and specifications for the contractor and authorize minor
changes which do not affect the contractor's price and are not contraryto the general
interest of the City under the contract.
g) Attend final inspection with City staff and provide the City with a Certificate of
Completion for the project upon successful completion of the project.
h) Review Contractor - provided construction "red -line" drawings. Prepare Project record
drawings and provide a reproducible set and electronic file (AutoCAD r.14 or later)
within two (2) months of final acceptance of the project. All drawings shall be CADD
drawn using dwg format in AutoCAD, and graphics data will be in dxf format with
each layer being provided in a separate file. Attribute data will be provided in ASCII
format in tabular form. All electronic data will be compatible with the City GIS
system.
The City staff will:
a) Prepare applications /estimates for payments to contractor.
b) Conduct the final acceptance inspection with the Engineer.
B. ADDITIONAL SERVICES
This section defines the scope of additional services that may only be included as park of this
contract if authorized by the Director of Engineering Services. A/E may not begin work on any
services under this section without specific written authorization by the Director of Engineering
Services. Fees for Additional Services are an allowance for potential services to be provided and
will be negotiated by the Director of Engineering Services as required. The A/E shall, with written
authorization by the Director of Engineering Services, perform the following::
Permit Preparation. Furnish the City all engineering data and documentation necessary for
all required permits. The A/E will prepare this documentation for all required signatures.
The A/E will prepare and submit identified permits as applicable to the appropriate local,
state, and federal authorities, including:
a. Texas Commission of Environmental Quality (TCEQ) Permits /Amendments
b. Texas Department of Licensing and Regulation (TDLR)
2. Right-of-Way ROW Acquisition Surve To Be Determined). All work must comply
with Category 1 -A, Condition I specifications of the Texas Society of Professional
Surveyors' Manual of Practice for Land Surveying in the State of Texas, Ninth Edition.
All work must be tied to and in conformance with the City's Global Positioning System
(GPS) control network. All work must comply with all TxDOT requirements as applicable.
a) Perform surveys to determine apparent right -of -way widths.
b) Research plats, ROW maps, deed, easements, and survey for fence corners,
monuments, and iron pins within the existing ROW and analyze to establish
existing apparent ROW. A/E must obtain Preliminary Title Reports from a local
title company and provide copies of the title reports to the City. Preliminary Title
Report shall identify title ownership and any title encumbrances to all right -of -way
to be acquired.
C) Provide a preliminary base map containing apparent ROW, which will be used by
the A/E to develop the proposed alignment and its position relative to the existing
EXHIBIT " A "
Page 5 of 9
Revised December 13, 2012
K%Engineering DataExchange4VELMARSTREEnE12092 GREENWOOD FROM GOLLIHAR TO HORNE BOND ISSUE 201MCONSULTANT CONTRACT govind developmentQ EXHIBIT A LARGE AE
REVISED Nov13 2012,doc
and proposed ROW. This preliminary base map must show lot or property lines,
land ownership and addresses as per appraisal district records.
3. Topographic Survey and Parcel Descriptions All work must be tied to and conform with
the City's Global Positioning System (GPS) control network and comply with Category 6,
Condition I specifications of the Texas Society of Professional Surveyors' Manual of Practice
for Land Surveying in the State of Texas, Ninth Edition. Include reference to a minimum of
two (2) found boundary monuments from the project area.
a) Establish Horizontal and Vertical Control.
b) Establish both primary and secondary horizontal /vertical control.
C) Set project control points for Horizontal and Vertical Control outside the limits of
project construction disturbance.
d) Horizontal control will be based on NAD 83 State plane coordinates (South Zone),
and the. data will have no adjustment factor applied — i.e. - -the coordinate data
will remain in grid.
e) Vertical control will be based on NAVD 88.
f} All control work will be established using conventional (non -GPS) methods.
Perform topographic surveys to gather existing condition information.
g) Locate proposed soil /pavement core holes as drilled by the City's Geotechnical
Engineering Consultant.
h) Obtain x, y, and z coordinates of all accessible existing sanitary sewer, storm
sewer, water and gas lines as well as any other lines owned by third - parties and
locate all visible utilities, wells and signs within the apparent ROW width along
project limits. No utility connections will be shown. Surveying services, related to
subsurface utility utility engineering (SUE) shall be provided as part of the scope
of work for SUE.
i) Locate improvements within the apparent ROW.
j) Locate and identify trees, at least five inches in diameter within the apparent
ROW.
k) Generate electronic planimetric base map for use in project design.
4. Environmental Issues (To Be Determined). Identify and develop a scope of work for any
testing, handling and disposal of hazardous materials and /or contaminated soils that may be
discovered during construction.
5. Public Involvement. Participate in two public meetings. One public meeting shall be held
after submittal of the Final Engineering Letter Report and one public meeting shall be held
prior to start of project construction. Prepare notices, powerpoint presentations, handouts
and exhibits for meetings. Provide follow -up and response to citizen comments. Revise
contract drawings to address citizen comments, as directed by the City. Prepare notices,
handouts and exhibits for public information meetings.
6. Subsurface Utility Investi ation
a) Provide subsurface utility engineering in accordance with ASCE Standard "ASCE C-
1, 38 -02, Standard Guideline for the Collection and Depiction of Existing Subsurface
Utility Data" including, but not limited to, hydro - excavation. The proposed subsurface
utility investigation will be as follows:
i) Excavation — The survey scope includes working with a subsurface utility
excavator to perform Quality Level A investigation of underground utilities in
specified areas through the project limit. (Quality Level A involves the use of
nondestructive digging equipment at critical points to determine the
EXHIBIT " A "
Page 6 of 9
Revised December 13, 2012
K3Engineering DataExchangekVELMAPXSTREEnEl2092 GREENWOOD FROM GOLLIHAR TO HORNE BOND ISSUE 20121CONSULTANT CONTRACT govind developmentU EXHIBIT A LARGE AE
REVISED Nov13 2012.doc
horizontal and vertical position of underground utilities, as well as the type,
size, condition, material, and other characteristics.) Utilities located at this
quality level will be physically located and tied to the topographic survey
control. The utility will be identified and an elevation will be obtained to the
top of the utility.
ii) Utility Location — The survey scope includes locating certain utilities to
Quality Level B (Quality Level B involves surveying visible above ground
utility facilities, such as manholes, valve boxes, posts, etc., and correlating
this information with existing utility records.) These utilities will be located by
obtaining a One -Call Notice and measuring the marked locations.
iii) Storm Water— Storm waterfacilities within the project limits will be located to
Quality Level C. Locations will be based on the surveyed locations of
accessible storm water manholes and drainage inlets.
iv) Wastewater— Wastewater facilities within the project limits will be located to
Quality Level C. Locations will be based on the surveyed locations of
accessible wastewater manholes. Wastewater lines that are not to be
replaced as part of this project and that fall within the footprint of
construction- related excavation shall be located at Quality Level A.
V) Water — Water facilities within the project limits will be located to Quality
Level C.
vi) Gas — Gas facilities within the project limits will be located to Quality Level C
by the AIE. The City of Corpus Christi Gas Department will provide Quality
Level A. The AIE will coordinate this activity.
b) Inform local franchises whose utilities fall within the footprint of construction - related
excavation of the potential for encountering their utility lines during construction.
7. Construction Observation Services. To Be Determined
8. Start -up Services. Provide on -site services and verification for all start -up procedures
during actual start-up of major Project components, systems, and related appurtenances if
needed and required.
9. Warranty Phase. Provide a maintenance guaranty inspection toward the end of the one -
year period after acceptance of the Project. Note defects requiring contractor action to
maintain, repair, fix, restore, patch, or replace improvement underthe maintenance guaranty
terms of the contract. Document the condition and prepare a report for the City staff of the
locations and conditions requiring action, with its recommendation for the method or action
to best correct defective conditions and submit to City Staff. Complete the inspection and
prepare the report no later than sixty (60) days prior to the end of the maintenance guaranty
period.
10. Franchise Utility Coordination. AIE to meet, coordinate, and resolve all requires!
Franchise Utilities that are in conflict with the construction of this project. (AEP, AT &T,
private gas lines, etc.)
Provide the services above authorized in addition to those items shown on Exhibit "A -1" Task List,
which provides supplemental description to Exhibit "A ". Note: The Exhibit "A -1" Task List does not
supersede Exhibit "A ".
EXHIBIT "A"
Page 7 of 9
Revised December 13, 2012
KlEngineering DataExchangelVELMAP ISTREET1E12092 GREENWOOD FROM GOLLIHAR TO HORNE BOND ISSUE 20121CONSULTANT CONTRACT govind deveiopmenW EXHIBIT A LARGE AE
REVISED Nov13 2012.doc
II. SCHEDULE
Date
Activit
January 21,2013
NTP
March 26,2013
30% Draft ELR submittal
April 2,2013
Ci Review
April 23,2013
Final ELR submittal
June 18,2013
60% Design Submittal
July 9,2013
City Review
October 8, 2013
100% Final Submittal
October 22, 2013
Advertise for Bids
October 23, 2013
Pre -Bid Conference
November 5,2013
Receive Bids
December 10,2012
Contract Award
March 7, 2014
Begin Construction
March 6, 2015
Complete Construction
III. FEES
A. Fee for Basic Services. The City will pay the A/E a fixed fee for providing for all "Basic Services"
authorized as per the table below. The fees for Basic Services will not exceed those identified and
will be full and total compensation for all services outlined in Section I.A.1 -4 above, and for all
expenses incurred in performing these services. The fee for this project is subject to the
availability of funds. The Engineer may be directed to suspend work pending receipt and
appropriation of funds. For services provided in Section I.A.1 -4, A/E will submit monthly
statements far basic services rendered. In Section I.A.1 -4, the statement will be based upon AIE's
estimate (and with City's concurrence) of the proportion of the total services actually completed at
the time of billing. City will make prompt monthly payments in response to AIE's monthly
statements.
B. Fee for Additional Services. For services authorized by the Director of Engineering Services
under Section I.B. "Additional Services," the City will pay the AIE a not -to- exceed fee as perthe table
below:
:EXHIBIT "A"
age 8 of 9
Revid December 13, 2012
KlEngineering DataExchangelVELMAPNSTREE nEl2092 GREENWOOD FROM GOLLIHAR TO HORNE BOND ISSUE 2012=NSULTANT CONTRACT govind developme02 EXHIBIT A LARGE AE
REVISED Nov13 2012.doc
Summary of Fees
Basic Services Fees
1. Preliminary Phase
$74,438.00
2. Design Phase
138,361.00
3. Bid Phase
7,292.00
4. Construction Administration Phase
23,807.00
Subtotal Basic Services Fees
243,898.00
Additional Services Fees (Allowance)
1. Permit Preparation (NTP)
7,000.00
2. ROW Acquisition Survey (NTP)
To Be Determined
3. Topographic Survey and Parcel Descriptions (Authorized)
23,250.00
4. Environmental Issues (NTP)
To Be Determined
5. Public Involvement (Authorized)
15,000.00
6. Subsurface Utility Investigation (Authorized)
76,125.00
7. Construction Observation Services (NTP)
To Be Determined
8. Start -up Services (NTP)
To Be Determined
9. Warranty Phase (Authorized)
5,500.00
10. f=ranchise Utility Coordination (NTP)
20,000.00
Sub -Total Additional Services Fees Authorized
146,875.00
Total Authorized Fee
$390,773.00
EXHIBIT "A"
Page 9 of 9
Revised December 13, 2012
K1Engineering DataExchangelVELMAP ISTREET1E12D92 GREENWOOD FROM GOLLIHAR TO HORNE BOND ISSUE 2012\CONSULTANT CONTRACT govind developmentl2 EXHIBIT A LARGE AE
REVISED Nov13 2012.doc
EXHIBIT "A -1" TASK LIST
CITY OF CORPUS CHRISTI, TEXAS
GREENWOOD DRIVE FROM GOLLIHAR ROAD TO HORNE ROAD
PROJECT NUMBER NO. E12092
BOND ISSUE 2012
I. SCOPE OF SERVICES
A. BASIC SERVICES
For the purpose of this contract, Preliminary Phase may include Schematic Design and Design
Phase services may include Design Development as applicable to Architectural services.
1. Preliminary Phase
a) NIA
b) NIA
c) At this time no allowance has been provided to perform the Geotechnical Investigation; only
to develop the scope of work.
d) NIA
e) NIA
f) NIA
g) NIA
h) Life cycle cost analysis to be determined using FHWA software.
i) Drainage area boundary will be based on existing limits that are to be provided by the City.
j) At this time the drainage study is limited to the designated project limits and no offsite
drainage studylanalysis has been included or identified.
k) NIA
1) NIA
m) NIA
n) NIA
o) Engineering Letter Report
1. NIA
2. NIA
3. NIA
4. NIA
5. NIA
6. Provide anticipated index of drawings and specifications.
1
Cover Sheet
2
Index of Sheets
3
Project Location Map
4 -7
General Notes and Testing Schedule
8
Existing Typical Sections
9
Proposed Typical Sections
10
Alignment Data
11
Control Layout
12 -13
Basis of Estimate and Specification Data
15
Legend - Estimated Quantities
16
Removal Summary
17
Construction and Traffic Control Notes
18 -22
Traffic Control Legend
23 -25
Proposed Construction Sequence
26 -28
Construction Sequence Layout
29 -35
Traffic Control Plan
36 -42
Utility Plan & Profiles
EXHIBIT "A -1"
Page 1 of 4
Revised December 13, 2012
43 -44
Waterline Tie -in Details
45 -46
Drainage Area Maps
47 -53
Storm Water Plan & Profiles
53 -59
Street Plan & Profiles
60 -62
Intersection Details
63 -66
Sign Layouts
67 -70
Pavement Marking Layouts
71 -73
SW3P
74 -77
Utility Basemaps
78 -79
Pavement Marking Standards
80 -91
Barricade and Construction Details
92 -95
Traffic Control Plan Typical Details
96 -100
Standard Water Details
101 -103
Sanitary Sewer Standard Details
104 -107
Storm Water Standard Details
108 -109
Miscellaneous Details
110
Commercial Driveway Details
111 -114
Pedestrian Facilities Details
115
Small Sign Summary
116 -118
Regulatory Sign Standards
119 -121
Sign Mounting Detail Standards
122 -124
Erosion Control Standards
p) NIA
q) NIA
r) NIA
s) NIA
City staff will provide one set only of the following information (as applicable):
a) NIA
b) NIA
c) NIA
d) N/A
e) NIA
f) NIA
g) NIA
h) NIA
2. Design Phase Upon approval of
authorization to proceed, the AIE will:
NIA
a) NIA
b) NIA
c) NIA
d) NIA
e) NIA
f) NIA
g) NIA
h) NIA
i) NIA
j) NIA
k) N/a
the preliminary phase, designated by receiving
EXHIBIT "A -1"
Page 2 of 4
Revised December 13, 2012
The City staff will:
a) NIA
b) NIA
c) NIA
3. Bid Phase The A/E will:
a) NIA
b) NIA
c) NIA
d) NIA
e) NIA
0 NIA
The City staff will:
a)
NIA
b)
NIA
C)
NIA
d)
NIA
4. Construction Administration Phase
a)
NIA
b)
NIA
C)
NIA
d)
Based on 20 hours per month for 12 months.
e)
NIA
f)
NIA
g)
NIA
h)
NIA
The City staff will:
a) NIA
b) NIA
B. ADDITIONAL SERVICES
1. Permit Preparation. NIA
a) NIA
b) NIA
2. Right -of -Way [ROW] Acquisition Survey. NIA
a) NIA
b) NIA
c) NIA
EXHIBIT "A -1"
Page 3 of 4
Revised December 13, 2012
3. Topographic
Survey and Parcel Descriptions
a)
NIA
b)
NIA
c)
NIA
d)
NIA
e)
NIA
f)
NIA
g)
NIA
h)
NIA
i)
NIA
j)
NIA
k)
NIA
4. Environmental Issues. NIA
5. Public Involvement. NIA
6. Subsurface Utilitv Investigation
a) NIA
i) It is anticipated that only 15 locations will be required for storm sewer, water
and sanitary combined.
ii) NIA
iii) NIA
iv) At this time no CCTV is anticipated given that these utilities are to be
replaced.
V) NIA
vi) NIA
b) NIA
7. Construction Observation Services. NIA
8. Start-u Services. NIA
9. Warranty Phase. NIA
10. Franchise Utilily Coordination. AIE to meet, coordinate, and resolve all required
Franchise Utilities that are in conflict with the construction of this project. (AEP, AT &T,
private gas lines, etc.)
EXHIBIT "A -1"
Page 4 of 4
Revised December 13, 2012
EXHIBIT "B"
MANDATORY INSURANCE REQUIREMENTS & INDEMNIFICATION
FOR A/E PROFESSIONAL SERVICESICONSULTANT SERVICES
(Revised October 2010)
A. Consultant must not commence work under this agreement until all insurance required
herein has been obtained and such insurance has been approved by the City. The
Consultant must not allow any subcontractor to commence work until all similar insurance
required of the subcontractor has been obtained.
B. Consultant must furnish to the City's Risk Manager, two (2) copies of Certificates of
Insurance, showing the following minimum coverages by insurance company(s) acceptable
to the City's Risk Manager. The City must be named as an additional insured for all liability
policies, and a blanket waiver of subrogation is required on all applicable policies.
TYPE OF INSURANCE
MINIMUM INSURANCE COVERAGE
30 -Day Written Notice of Cancellation, Bodily Injury & Property Damage
non - renewal or material change required Per occurrence - aggregate
on all certificates
COMMERCIAL GENERAL LIABILITY
including:
1. Broad Form
2. Premises - Operations
3. Products/ Completed Operations
4. Contractual Liability
5. Independent Contractors
$1,000,000 COMBINED SINGLE LIMIT
AUTOMOBILE LIABILITY to included $1,000,000 COMBINED SINGLE LIMIT
1. Owned vehicles
2.. Hired — Non -owned vehicles
PROFESSIONAL LIABILITY including:
Coverage provided shall cover all
employees, officers, directors and agents
1. Errors and Omissions
WORKERS' COMPENSATION
$1,000,000 per claim / $2,000,000
aggregate
(Defense costs not included in face value
of the policy)
If claims made policy, retro date must be
prior to inception of agreement; have
extended reporting period provisions and
identify any limitations regarding who is
an Insured
Which Complies with the Texas Workers
Compensation Act
EMPLOYERS' LIABILITY
500,000/500,0001500,000
EXHIBIT "B"
Pagel of 3
K%Engineedng DataExchange \VELMAPLFORMSICONTRACT PROFESSIONAL SERVICES B120121CONSLILTANT CONTRACT FORMSI4 EXHBIT B INDEMNIFICATION -
OCT 201 O.dacx
C. In the event of accidents of any kind, Consultant must furnish the Risk Manager with copies
of all reports within (10) ten days of accident.
D. Consultant must obtain workers' compensation coverage through a licensed insurance
company in accordance with Texas law. The contract for coverage must be written on a
policy and endorsements approved by the Texas Department of Insurance. The coverage
provided must be in amounts sufficient to assure that all workers' compensation obligations
incurred will be promptly met.
E. Consultant's financial integrity is of interest to the City; therefore, subject to
Successful Consultant's right to maintain reasonable deductibles in such amounts as are
approved by the City, Consultant shall obtain and maintain in full force and effect for the
duration of this Contract, and any extension hereof, at Consultant's sole expense, insurance
coverage written on an occurrence basis, by companies authorized and admitted to do
business in the State of Texas and with an A.M. Best's rating of no less than A -VII.
F. The City shall be entitled, upon request and without expense, to receive copies of the
policies, declarations page and all endorsements thereto as they apply to the limits required
by the City, and may require the deletion, revision, or modification of particular policy terms,
conditions, limitations or exclusions (except where policy provisions are established by law
or regulation binding upon either of the parties hereto or the underwriter of any such
policies). Consultant shall be required to comply with any such requests and shall submit a
copy of the replacement certificate of insurance to City at the address provided below within
10 days of the requested change. Consultant shall pay any costs incurred resulting from
said changes. All notices under this Article shall be given to City at the following address:
City of Corpus Christi
Attn: Risk Management
P.O. Box 9277
Corpus Christi, TX 78469 -9277
Fax: (361) 826 -4555
G. Consultant agrees that with respect to the above required insurance, all insurance policies
are to contain or be endorsed to contain the following required provisions:
Name the City and its officers, officials, employees, volunteers, and elected
representatives as additional insured by endorsement, as respects operations and
activities of, or on behalf of, the named insured performed under contract with the City,
with the exception of the workers' compensation and professional liability policies;
ii. Provide for an endorsement that the "other insurance" clause shall not apply to the City
of Corpus Christi where the City is an additional insured shown on the policy;
iii. Workers' compensation and employers' liability policies will provide a waiver of
subrogation in favor of the City; and
iv. Provide thirty (30) calendar days advance written notice directly to City of any
suspension, cancellation, non - renewal or material change in coverage, and not less than
ten (10) calendar days advance written notice for nonpayment of premium.
�� EXHIBIT "B"
Page 2 of 3
K:1Engineenng DataExchangelVELMAPIFORMSICONTRACT PROFESSIONAL SERVICES 91201ZCONSULTANT CONTRACT FORMSW EXHIBIT B INDEMNIFICATION -
OCT 2010.doox
H. Within five (5) calendar days of a suspension, cancellation, or non- renewal of coverage,
Successful Consultant shall provide a replacement Certificate of Insurance and applicable
endorsements to City. City shall have the option to suspend Consultant's performance
should there be a lapse in coverage at any time during this contract. Failure to provide and
to maintain the required insurance shall constitute a material breach of this contract.
I. In addition to any other remedies the City may have upon Consultant's failure to provide and
maintain any insurance or policy endorsements to the extent and within the time herein
required, the City shall have the right to order Consultant to stop work hereunder, and/or
withhold any payment(s) which become due to Consultant hereunder until Consultant
demonstrates compliance with the requirements hereof.
J. Nothing herein contained shall be construed as limiting in any way the extent to which
Successful Consultant may be held responsible for payments of damages to persons or
property resulting from Consultant's or its subcontractors' performance of the work covered
under this agreement.
K. It is agreed that Consultant's insurance shall be deemed primary and non - contributory with
respect to any insurance or self insurance carried by the City of Corpus Christi for liability
arising out of operations under this contract.
L. It is understood and agreed that the insurance required is in addition to and separate from
any other obligation contained in this contract.
INDEMNIFICATION AND HOLD HARMLESS
Consultant shall indemnify, sane harmless and defend the City of Corpus Christi, and
its agents, servants, and employees, and each of them against and hold it and them
harmless from any and all lawsuits, claims, demands, liabilities, losses and expenses,
including court costs and attorneys' fees, for or on account of any injury to any
person, or any death at any time resulting from such injury, or any damage to any
property, which may arise or which may be alleged to have arisen out of or in
connection with the negligent performance of Consultant's services covered by this
contract. The foregoing indemnity shall apply except if such injury, death or damage
is caused by the sole or concurrent negligence of the City of Corpus Christi, its
agents, servants, or employees or any other person indemnified hereunder.
EXHIBIT "B"
Pa e3of3
K:1Engineering DataExchangelVELMAP IFORMSICONTRACT PROFESSIONAL SERVICES 612012XCONSULTANT CONTRACT FORMSI4 EXHIBIT B INDEMNIFICATION -
OCT 2010.docx
-� M
� oa
1
s
0
Basic Services:
Preliminary Phase
Design Phase
Bid Phase
Construction Phase
Subtotal Basic Services
Additional Services:
Permitting
Warranty Phase
Inspection
Platting Survey
O & M Manuals
SCADA
Subtotal Additional Services
Summary of Fees
Basic Services Fees
Additional Services Fees
Total of Fees
COMPLETE PROJECT NAME
Project No. XXXX
Invoice No. 12345
Invoice Date:
Sample form for:
Payment Request
Revised 07/27/00
Total Amount Previous Total Percent
Contract Amd No. 1 Amd No. 2 Contract Invoiced invoice Invoice Complete
$1,000
$0
$0
$1,000
$0
$1,000
$1,000
100%
2,000
1,000
0
3,000
1,000
500
1,500
50%
500
0
250
750
0
0
0
0%
2,500
0
1,000
3,500
0
0
0
0%
$6,000
$1,000
$1,250
$8,250
$750
$1,500
$2,500
30%
$2,000
$0
$0
$2,000
$500
$0
$500
25%
0
1,120
0
1,120
0
0
0
0%
0
0
1,627
1,627
0
0
0
0%
TBD
TBD
TBD
TBD
TBD
TBD
TBD
0%
TBD
TBD
TBD
TBD
TBD
TBD
TBD
0%
TBD
TBD
TBD
TBD
TBD
TBD
TBD
0%
$2,000
$1,120
$1,627
$4,747
$500
$0
$500
11%
$6,000
$1,000
$1,250
$8,250
$750
$1,500
$2,500
30%
2,000
1,120
1,627
4,747
500
0
500
11%
$8,000
$2,120
$2,877
$12,997
$1,250
$1,500
$3,000
23%
7TBEA�G �BY't ffY —"
t srtao tm►tsM
Cie
y of vim.
crrY of CORPUS CHRISTI
Cldw DISCLOSURE OF INTEREST
of C�G�or�tpyyus ChrW Ordinance 171 l2, as smcmdcd, requi pe sons or � to do business
rear a�pplic�tile�, answer .. de of r be answex�ed.�qun is
owde ac definition-c.
°�* and
COMPANY NAME: GOVM DEVEWPMIW.itl'd�, LW
P. O. BOX:
STIItEET ADDR M.- %59M37
C1TY: Corp= ChrlsdT ZIP: 7W9
pIRM IS: I. Corpotawn 5. a 3. Sole Owner ❑
4.
DISCLOUME QUEMONS
if additional space is atec , please use the rcvease side ofthis or attach separate sheet.
1. State trite names of =& employae of the C.� Corput kW lavin8 an �'�ip its"
g 3% cr ose o
nf the ownastip is the named "firm."
N Name Job TRW and City Dicpatment (if loiw")
2. State the names of each "offreial" of the City of Corpus Christi ha - am "ownership into ur
Muting 3% or more of the ownership in the above maned "fkmn "
Now
Wane Tide
3. State the names of each "board member" of the Ctty of Corpas Christi Mft an , .dip ice"
consfttdng 3% or more of the ownership in rho above nod "firm."
Name Boarl, Commmas or Committee
Govind B. Nadkarni p!Mlh Caatntissian
4. State the names of eaeh kuplayee or officer of a "coasulbur for the City of Carpus Cheri who
w0dW d on MY matter Mbded to the subject of this contact and has as ` awnership WwreW
comstift ing 390 of mom of the ownership in the above named "firm,
Non N am Coaumrhant
FMING REQUIREMEWS
If a person who requests official action on a matter knows that the re action will confer an
economic benefit on any City official or loyee that is distinguishable from the effect that the action
will have on members of the public in em or a substantial se thereof, you shall disclose that fact
in a signed writing to the City of�5cia eritployee or body thatCbeen acted to act in the ir3�auel;
unless the interest of the City official or employee in the matter is appar tt a disclosure shall also be
made in a sighed writing filed urith the City Secaetary. [Ethics Ordinance Section 3 -349 (d)]
CERTMCATION
I certify that all information provided is true and correct as of the date of this statement, that I have not
knowingly withheld disclosdm of any information requested, and that supplemental statements will be
promptly submitted to the City of Corpus Christi, Texas as changes occur.
Certifying Person: Ranfim Munoz iII b Title: V ice Preside
trwRid"t
Signature of Certifying
Person:
Date: ,
DEMMOMS
a. "Board member." A member of any boast commission, or committee appointed by the City
Council of the City of Corpus Christi, Texas.
b. - Economic benefit". An action that is lit ei} to affect an economic interest if it is likely to have an
effect on that interest that is distinguishable from its effect on members of the public in general or a
substantial segment thereof.
c. °Eittployee." Arty person employed by the City of Corpus Christi Texas either on a full or parlR
time basis, but not as an independent contractor.
d. "Firm." Any entity operated for economic gain, whether prOfessiortal, industrial or Commercial, and
whether established to produce or deal with a product or service, including but not limited to, entities
operated in the form of sole proprietorship, as self - employed person, partnership, corporation, joint
stock company, joint venture, receivership or trust, and entities which for purposes of taxation are
treated as non-profit organizations.
e, "Olicial." The Mayor, members of the City Council, City Manager, Deputy City Manager,
Assistant City Managers, Department and Division heads, and Municipal Court Judges o f the City of
Corpus Christi, Texas.
f. "0wher5ltip Interest:' Legal or equitable interest, whether actually or constructively held, in a
firm, including whets such interest is held through an agora„ trust, Mate, or holding city.
''Constructively. held" refers to holdings or control established through voting trusts, proxies, or
special terms of venture or partnership agreements."
g. "Consultant. - Any person or firm, such as engineers and architects, hired by the City of Corpus
Christi for the psuposc Of professional consultation and reconimcudatiom.