HomeMy WebLinkAboutC2013-270 - 5/29/2013 - NA AMENDMENT NO. 8
TO CONTRACT FOR
PROFESSIONAL SERVICES
The City of Corpus Christi, Texas hereinafter called "CITY', and Freese and Nichols, Inc. agree to the
following amendment to the Contract for Professional Services for Garwood Water Supply Project
(Project No. 8424), as authorized and amended by:
Original AIE Agreement October 28, 2003 Motion No. M2003-394 $116,100.00
Amendment No. 1 October 19, 2004 Motion No. M2004-387 $285,490.00
Amendment No. 2 December 18, 2007 Motion No. M2007-334 $911,997.00
Amendment No. 3 March 11, 2009 Administrative Approval $0.00
Amendment No. 4 March 9, 2010 Motion No. M2010-051 $9,676,590.00
Amendment No. 5 November 30, 2011 Administrative Approval $0.00
Amendment No. 6 January 14, 2012 Administrative Approval $49,940.00
Amendment No. 7 April 24, 2013 Administrative Approval $49,822.00
Amendment No. 8 revises the project scope for Mary Rhodes Pipeline Phase 2 (Project No. E10008)
to the Garwood Water Supply Project as follows:
Exhibit "A" Section I. Scope of Services Part B. Additional Services shall be modified to include
Subsurface Utility Exploration as specified in Amendment No. 8 Exhibit "A".
Exhibit "A", Section II. Schedule, shall be modified as specified in the attached Amendment No. 8
Exhibit"A", Schedule.
Exhibit "A" Section Ill. Fees shall be modified as specified in Amendment No. 8 Exhibit "A" for a
revised fee not to exceed $49,900.00 (Forty-Nine Thousand Nine Hundred Dollars and Zero Cents),
for a total restated fee not to exceed $11,139,839.00 (Eleven Million One Hundred Thi -Nine
Thousand Eicht Hundred Thirty-Nine Dollars and Zero Cents). Monthly invoices shall be submitted
in accordance with Amendment No. 8 Exhibit"B".
All other terms and conditions of October 28, 20003 contract and amendments between the City and
Freese and Nichols, Inc. will remain in full force and effect.
CITY OF CORPUS CHRISTI FREES AND NICHOLS, INC.
Oscar R. Martinez""' (Date) Aon G izman,"P.E., (Date)
Assistant City Manager Principal
800 North Shoreline Blvd., Suite 160ON
Corpus Christi, TX 78401
RECOMENDED (361)561-6500 Office
5A a- (361)561-6501 Fax
Daniel s, P.E., (D te,
Dire r Engine n 'Services
2013-270 (Date)
5129113 AMEND.NO. 8
Page I of 2
Freese and Nichols Inc. kTER%E1DDDB MARY RHODES PIPELINE.PHASE ZAMENDMENT NO MCONTRACT DOCX
INDEXED
APPRO D AS TO FORM:
LZ
Office o agement and Budget (Dat')
Legal Department (Date)
ATTEST
Armando Chapa, City Secretary ENTERED
MAY 0 2013
Project No: E10008
Fund Source No: 550950-4091-00000-E10008 cummui MANAUhR
Fund Name: Water 2012B CIP Fd (RvBd)
Encumbrance No:
( "n d
y"71C
j
AMEND. No.8
Page 2 of 2
K%ENGINEERING OATAEXCHANGEVENNIFERWATERV OWS MARY RHODES PIPELINE PHASE 21AMENDMENT NO MCONTRACT,DOCX
EXHIBIT "A"
CITY OF CORPUS CHRISTI, TEXAS
Mary Rhodes Pipeline Phase 2 (Project No. E10008)
Parent Project: Garwood Water Supply Project (Project No. 8424)
Amendment No. 8
I. SCOPE OF SERVICES
Scope Revision: Add the following task as shown below:
B. Additional Services
A-4. Subsurface Utility Exploration
Add the following activities to the Subsurface Utility Exploration scope:
• Probe pipelines at 85 utility locates to determine depth of cover (limited to
pipelines with less than 8 feet of cover).
II. SCHEDULE
Final Design Phase September 1, 2013
III. FEES
The total authorized fee for all services added to the contract with through this
Amendment will be $49,900. Fees for individual additional tasks are shown in the
Summary of Fees table. The table Summary of Fees set forth on the following page
will be used by the Consultant Engineer to determine the amount to be invoiced for
each task. The fee shown for each task is inclusive of all expenses as set forth by
the original contract„
Summary of Fees
TASK Description Fee
Original Contract-Phase 1
I.A.1 Screening Study of Delivery Options $ 116,4TB
I.A.2 Detailed Study of Delivery Options
I.A.3 Pipeline Route Study TBN
I.A.4 Pipeline Surveying, Easement Acquisition, and Permitting TBN
I.A.5 Pipeline Topographic Survey and Preliminary Design TBN
I.A.6 Final Design Phase TBN
I.A.7 Bid, Award, and Construction TBN
Original Contract Fee $ 11fi,100.00
AMEND. NO. 8
EXHIBIT"A"
Page 1 of 7
KlEnginming DetaEchangeUENNIFEMWATERIE10005 NARY RHODES PIPELINE„PHASE ENDMENT NO,SZAibit Adoc
Amendment No. 1 - Phase 2
2.A Detailed Study of Delivery Option 5 $ 152,532
2.13 Detailed Study of Delivery Option 1 $ 64,328
2.0 Detailed Study of Delivery Option 6 $ 68,630
Amendment No. 1 Fee $ 285,490
Amendment No. 2 - Phase 2A
2A-0001 Field Studies
2A.1.A —Ownership Mapping $ 20,631
2A.1.B —Risk Analysis $ -
Prepare Risk Analysis $ 5,853
Risk Analysis Workshop (in CC) $ 4,533
2A.1.0 Field survey of West Mustang Creek $ 46,922
2A.1.13 West Mustang Creek Habitat Assessment $ 34,272
2A.1.E —Coordination Re-Calib. Of Gannado Gauging Station $ 6,168
2A.1.F —Summary $ -
Prepare Task Summary $ 11,650
Task Summary Workshop (in CC) $ 8,383
Total Fee by Classification $ 138,411
2A-0002 LCRA Agreement
2A.2.A —Agreement Framework $ -
Prepare Framework $ 12,695
Submit Framework $ 431
Schedule Framework Meeting $ 451
2A.2.B —Framework Meeting (Garwood) $ 7,235
2A.2.0 —Prepare Draft LCRA Agreement $ 10,525
2A.2.D —Draft LCRA Agreement Workshop (Garwood) $ 6,366
2A.2.E Prepare Final Agreement $ 8,740
2A 2 F Task—Execute Agreement (1 meeting Austin, 1 meeting Corpus
Christi) $ 8,151
2A.2.G —Task 2 Summary $ 14,675
Total Fee by Classification $ 69,268
2A-0003 LNRA Agreement
2A.3.A Agreement Framework $ -
Prepare Framework 13,025
Submit Framework 431
Schedule Framework Meeting $ 451
2A.3.13 —Framework Meeting (Edna) $ 7,191
2A.3.0 —Prepare Draft Agreement $ 10,525
2A.3.13 —Draft LNRA Agreement Review Workshop (Edna) $ 7,191
2A.3.E —Regulatory Coordination (2 meetings Austin) $ 10,137
AMEND. NO. 8
EXHIBIT"A"
Page 2 of 7
MEnginsaft DatsExch"1JENNIFER4WATIERIZIDDOO MARY RHODES PIPELINE,PHASE 21AMENDMENT NO,S EXhibit kdoc
2A.3.F —Prepare Final LNRA Agreement $ 6,815
2A.3.G —Execute Agreement (1 meeting Edna, 1 meeting Austin) $ 11,360
2A.3.H —Task 3 Summary $ ____j,41125
Total Fee by Classification $ 81,250
2A-0004 Permitting and Agency Coordination
2A.4.A —Coord w/TPWD re: GSM Permit (2 meetings Austin) $ 3,737
2A 4 B —Coord w/TPWD re: LNRA Inflow/Release Agreement(3 meetings
Austin $ 5,156
2A.4.0 —Coord w/TCEQ re: Bed and Banks Permit (3 meetings Austin) $ 7,104
2AA.D —Coord w/TGLO re: Bed and Banks Permit(3 meetings Austin) $ 7,104
2A.4.E —Coordination with TCEQ and TWDB re: Regional Water Planning (2
meetings Austin) $ 1,437
2A.4.17 —Regional Water Planning Group Coordination (1 meeting Austin, 1
meeting Cor us Christi $ 2,979
2A.4.G —Monitor LCRA/SAWS Project (2 meetings Garwood) $ 6,437
2A.4.H —USACE Coord (1 meeting Galveston) $ 8,253
2A.4.1 —TPDES Coordination (1 meeting Austin) $ 6,566
2AA J —Landowner Issues and Communications (3 meetings Edna) $ 20,785
2A.4.K —Meet w/Environmental Groups $ -
Prepare Exhibits $ 13,093
Meeting 1 $ -
Plan $ 501
Schedule $ 471
Prepare for Meeting $ 3,745
Attend Meeting (Austin) $ 2,376
Meeting 2 -
Plan $ 501
Schedule 471
Prepare for Meeting $ 3,745
Attend Meeting (Austin) $ 2,376
Meeting 3 $ -
Plan $ 501
Schedule $ 471
Prepare for Meeting $ 3,745
Attend Meeting (Edna) $ 3,591
41 —Task 4 Summary $ 16,070
Total Fee by Classification $ 121,216
2A-0005 Permitting Activities
5.A —Bed and Banks Permit Application $ -
Prepare Permit $ 20 655
Submit Permit $ 6,360
AMEND. NO. 8
EXHIBIT"A°
Page 3 of 7
K%Engineedng DetaExdvmpUENN1FER%WATEME10DDS MARY RHODES PIP UN ,PHASE MAMENDUENT NO.5T_,4 tibit Adoc
Agency Review $ 8,115
Permit Approval $ 5,203
—Prepare Amendment to TPWD/LNRA Inflow& Release Agreement $ -
Develop Amendment Framework $ 3,815
Meet with LNRA and TPWD to develop amendment outline (1
m!g Edna) $ 4,441
Develop Draft Amendment $ 4,Q75
Meet with LNRA and TPWD to review Draft Amendment(1 mtg
Edna) $ 4,441
Prepare Final Amendment $ 3,735
Obtain Written Approval (1 mtg Austin, 1 mtg Edna) $ 6,540
Water Right Amendment Application $ -
Prepare Permit $ 10,815
Submit Permit $ 961
Agency Review $ 4,210
Permit Approval $ 1,023
—Monitor Permit Application Status $ 2,045
—Regulatory Agency Coord During Permit App Process $ 2,945
—Develop Supporting Info for Region N Amendment $ 5J30
—Coordinate Region N Amendment (2 meetings CC) $ 11,475
—Amend Water Conservation/Drought Management Plan $ -
Prepare Draft Amendment $ 3,408
Plan Workshop (CC) $ 4,533
Submit Draft Amendment $ 1,120
City Review of Draft Amendment $ -
Review Workshop (CC) $ 4,533
City Review Complete $ -
Incorporate City Comments/Prepare Final Amendment $ 3,535
City Council Approval of Final Amendment (CC) $ 4,533
2A.5.1 —Task 5 Summary $ 15,227
Total Fee b Classification $ 142,870
2A-0006 Conceptual Facility Design
2A.6.A —GIC Facility Requirement Workshop $ 330
Schedule Workshop $ 681
Conduct Workshop (Garwood) $ 6,393
—Concept Design of GIC Canal System Improvements $ 4,800
—Concept Design of West Mustang Creek Div. Structure $ 4,800
—Design Review Workshop $ -
Schedule Workshop $ 681
Conduct Workshop (Garwood) $ 6,393
. 2A.6.E Mustang Creek Gauging Facility Workshop $ 6,900
AMEND. NO. 8
EXHIBIT"A"
Page 4 of 7
K"inewing DamExcliangsUENNIFERWATERVOWS MARY RNOM PIPELINE,PKASE MAMENDMENT NO$4E hibil,4doc
Schedule Workshop $ 681
Conduct Workshop (Edna) $ 4,193
2A.6.F —Concept Design, W. Mustang Creek Gauging Facility $ 3,960
2A.6.G W. Mustang Creek Gauging Facility Workshop $ -
Schedule Workshop $ 681
Conduct Workshop (Edna) $ 6,393
2A.6.H Task Summary $ 10,275
Total Fee by Classification $ 57,164
2A-0007 Mary Rhodes Pipeline Assessment
2A.7.A —Data Collection and Review $ 8,648
2A.7.6 —Facilities Site Visit $ 23,266
2A.7.0 —Task Kickoff Workshop (Corpus Christi) $ 8,605
2A.7.D —Pump Station Assessment $ 17,008
2A.7.E —SCADA System Assessment $ 11,840
2A.7.F —Operational Integration of Garwood Water $ 6,200
2A.7.G Alternatives Identification and Screening $ 27,613
2A.7.H Alternative Control Strategies $ 11,335
2A.7.1 —Recommended Mary Rhodes Pipeline Improvements $ 6,205
2A.7.J Task 7 Summary $ -
Prepare Summary $ 16,200
Attend Workshop $ 5,768
Total Fee by Classification $ 142,686
2A-0008 Task 8 -Phase 2A Report
2A.8.A —Prepare Draft Report $ -
Prepare Report $ 25,656
Submit Draft Report to City for Review $ 1,292
City Review of Draft Report $ -
City Review Complete $ -
2A.8.B —Prepare Draft Report Presentation $ 7,112
2A.8.0 —Draft Report Workshop (Corpus Christi) $ 9,169
2A.8.D —Draft Report Comments Meeting (Corpus Christi) $ 9,169
2A.8.E —Prepare Final Report $ 10,321
2A.8.F —Final Report Presentation (up to 3 meetings in Corpus Christi) $ 34,669
Total Fee by Classification $ 97,388
2A-0009 Project Management
2A.9.AOBC1 Task 9.A—Project Schedule $ 10,060
2A.9.130BC2 Task 92—Progress Reports and Invoices $ 23,342
2A.9.COBC3 Task 9.0—Phase 3 Scoping $ 28,343
Total Fee by Classification $ 61,744
Amendment No. 2 Fee $ 911,997
AMEND. NO. 8
EXHIBIT"A"
Page 5 of 7
K inewingDatsExMaMoUENNIFERXWATERMI DOW MARY RHODES PIPELINE,PHASE ZMENDMENT NO bit Adoc
Amendment No. 3
2A-0005 Task 5- Permitting Activities (Deleted in its Entirety) $ -142,870
2A-0008 Task 8 - Phase 2A Report (Deleted in its Entirety) $ -97,388
3-00010 Task 10 -Garwood Alignment Study Scope of Work
3-0010.1 Data Collection $ 49,709
3-0010.2 Preliminary Hydraulic Study $ 21,975
3-0010.3 Preliminary Environmental Review $ 60,294
3-0010.4 Preliminary Route Analysis $ 45,364
3-0010.5 Final Route Analysis $ 62,916
Amendment No. 3 Fee $ 0
Amendment No. 4
1 Study Phase $ 0
2 Preliminary Phase $ 1 514 814
3 Design Phase $ 3,068,522
4 Bid Phase $ 102,000
5 Construction Phase $ 1,200,000
A- 1 Permitting $ 267,414
A-2 ROW Acquisition Survey $ 350,000
A-3 Topographic Survey $ 891,165
A -4 Subsurface Utility Exploration $ 286,000
A- 5 Aerial Photography $ 23,750
A- 6 Corrosion Engineering $ 122,768
A- 7 Surge Analysis $ 104,181
A- 8 Geotechnical Investigation $ 312,737
A- 9 Archeological Investigation $ 184 650
A- 10 Hydraulic Modeling $ 37,398
A- 11 ROW Acquisition $ 11060.601
A- 12 Construction Observation Services $ TBD
A- 13 Start-Up Services $ TBD
A- 14 OW Services $ 150,590
A- 15 Warranty Phase $ TBD
A- 16 Provide SCADA Documentation $ TBD
Amendment No. 4 Fee $ 9,676,590
Amendment No. 5
2 Preliminary Phase $ 0
3 Design Phase $ 183,179
4 Bid Phase $ 82,814
A - 1 Permitting $ 53,696
A -3 Topographic Survey $ 37,035
-4 Subsurface Utility Exploration $ -121,045
AMEND. NO. 8
EXHIBIT"A"
Page 6 of 7
KXEWineednq D UENNIFER%wA 1 8 MARY RHODES PIPELINE,,PHASE 2%AMENDMENT NO Mxhiblt Adoc
A- 8 Geotechnical Investigation $ 18,749
A-9 Archeological Investigation $ -87,808
A- 10 Hydraulic Modeling $ 36,102
A- 11 ROW Acquisition $ -202,722
Amendment No. 5 Fee $ 0
Total Fee $ 10,990,177
Amendment No. 6
2 Preliminary Phase $ 2,340
A- 11 ROW Acquisition $ 47,600
Amendment No. 6 Fee $ 49,940
Total Fee $ 11,040,117
Amendment No. 7—Joint City of Corpus Christi and LCRA Feasibility Study
Study Phase $ 49,822
Amendment No. 7 Fee $ $49,822
Total Fee $ 11089,939
Amendment No. 8
A-4 Subsurface Utility Exploration $49 900
Amendment No. 8 Fee $ $49,900
Total Fee $ 11,139,839
AMEND. NO. 8
EXHIBIT 1,A1!
Pa e7of7
K%Engineering DeteExd=geUENNIFER%WATER%EI0008 MARY RHODES PIPELINE,PHASE 2VWVNDMENT NO SlExhibit A.doc
L• y O
O O O
r� 0 0 0 0 0 0 0 0 0 0 0.e lae,Qrra r
OOOOO 000000r Orr)
(D N O l!) Cr) N r cr) r N
E 5 a
•�
comes �, E
Nam a v
m °0 °o ° ° °0 °0 ° ° ❑ ❑ ❑ °o °0 ° °
0 0
O 7 �+ r dN4
F- c
3 00 00 ° ° 00 0 O o m m m ° °o ° °o
n
O �_ o Ln L F- I- F-
0
6c), 64
i C
a --
C os� 0 0 0 o 00 O O ❑ ❑ ❑ °O u°) O t°n
o o co H co 64 LO CN
E � r
Q S
o g o g 0 0 o ti 0 0 0 ti o ti ti
LU +�+ o Ln W) O N N d w A 0
I� W) N O r 0 m m m ti N t-
Q X44 rim 4 � � 40 � � r
z c Vk
LO
W
cc 0 ° °
N O m 0� Z Z O N 0 N co 000
a. � QI V Z r r
r r r r N
LU I- -'o a E
JO` C
FL C Q
CL ,_
° O O ° O ° N ° ❑ N O N N 2 r � �
O 0 O r
O r r
(� Z r r r r r T--r N
.0 ER i,R 69 i,R
E
0 0 0 0 0 0 0 0 ❑ ❑ ❑ 0 Cl 0 0
0 0 00 0 o m m m 0 0 0 0
ogLn o PPP0 000
C � N N � NEF3 NEF3 (6 N C6
O
CO U
cn •� N
U- U
to
.� = m W a r
co Q Z Li
a. U
Mm 2 20 E
C .0 L
m a ❑ m 0 cn Q a a. 0 CO CO Cn m
L . NO. 8
IT "B"1 of 1
SUPPLIER NUMBER
M DE ASSIGNED DY-=
PURCHASING DIVISION
`city of CITY OF CORPUS CHRISTI
R DISCLOSURE OF INTEREST
City of Corpus Christi Ordinance 17112,as amended,requires all persons or firms seeking to do business
with the City to provide the following information. Every question must be answered. If the question is
not applicable, answer with "NA". See reverse side for Filing Requirements, Certifications and
definitions.
COMPANY NAME: Freese and Nichols,Inc.
P.O.BOX:
STREET ADDRESS: NOON.Shoreline Blvd"Suite 160ON CITY: Corpus Christi ZIP: 78401
FIRM 1S: 1. Corporation ® 2. Partnership e 3. Sole Owncr ❑
4. Association 5. Other
DISCLOSURE QUESTIONS
If additional space is necessary,please use the reverse side of this page or attach separate sheet.
1. State the names of each `employee" of the City of Corpus Christi having an "ownership interest"
constituting 3%or more of the ownership in the above named"firm."
Name Job Title and City Department(if known)
NIA NIA
Z. State the names of each "official" of the City of Corpus Christi having an "ownership interest"
constituting 3%or more of the ownership in the above named"firm."
Name Title
NIA NIA
3. State the names of each"board member"of the City of Corpus Christi having an `ownership interest"
constituting 3%or more of the ownership in the above named"firm."
Name Board,Commission or Commitice
NIA NIA
4. State the names of each employee or officer of a "consultant" for the City of Corpus Christi who
worked on any matter related to the subject of this contract and has an "ownership interest'
constituting 3%or more of the ownership in the above named"firm."
Name Consultant
NIA NIA
F1L1NG REQUIREMENTS
If a person who requests official action on a matter knows that the requested action will confer an
economic benefit on any City official or employee that is distinguishable from the effect that the action
will have on members of the public in general or a substantial segment thereof,you shall disclose that fact
in it signed writing to the City official,employee or body that has been requested to act in the matter,
unless the interest of the City official or employee in the matter is apparent. The disclosure shall also be
made in a signed writing filed with the City Secretary. [Ethics Ordinance Section 2-349(d)]
CERTIFICATION
I certify that all information provided is true and correct as of the date of this statement,that l have not
knowingly withheld disclosure of any information requested; and that supplemental statements will be
promptly submitted to the City of Corpus Christi,Texas as changes occur.
Certifying Person: Ron Guzman.P.E. Title: Principal
(Tnw m Fri
Signature of Certifying Date: - L 13 • 3
Person:
DEFINITIONS
a. "Board member." A member of any board, commission, or committee appointed by the City
Council of the City of Corpus Christi,Texas.
b. "Economic benefit". An action that is likely to affect an economic interest if it is likely to have an
effect on that interest that is distinguishable from its effect on members of the public in general or a
substantial segment thereof.
c. Employee. Any person employed by the City of Corpus Christi,Texas either on a full or part-
time basis,but not as an independent contractor.
d. "Firm." Any entity operated for economic gain,whether professional, industrial or commercial,and
whether established to produce or deal with a product or service, including but not limited to,entities
operated in the form of sole proprietorship, as self-employed person, partnership, corporation,joint
stock company,joint venture, receivership or trust, and entities which for purposes of taxation are
treated as non-profit organizations.
e. "Official." The Mayor, members of the City Council, City Manager, Deputy City Manager,
Assistant City Managers, Department and Division Heads,and Municipal Court Judges of the City of
Corpus Christi,Texas.
f. "Ownership interest." legal or equitable interest, whether actually or constructively held, in a
firm, including when such interest is held through an agent, trust, estate, or holding entity.
"C.onstructively held" refers to holdings or control established through voting trusts, proxies, or
special terms of venture or partnership agreements."
g. "Consultant."Any person or firm, such as engineers and architects, hired by the City of Corpus