Loading...
HomeMy WebLinkAboutC2014-111 - 3/13/2014 - NA AMENDMENT NO. 6 TO CONTRACT FOR PROFESSIONAL SERVICES The City of Corpus Christi,Texas hereinafter called"CITY",and HDR ENGINEERING,INC., hereinafter called "ENGINEER," agree to the following amendment to the Contract for Professional Services for Bayfront Development Plan, Phase 3—BOND 2008 (Protect No. 6511), as authorized and amended by: Original Contract June 19, 2009 Administrative Approval $42,000.00 Amendment No. 1 May 18, 2010 Motion No. 2010-115 $1,126,976.70 Amendment No. 2 July 7, 2010 Administrative Approval $3,500.00 Amendment No. 3 October 12, 2010 Administrative Approval $44,100.00 Amendment No. 4 January 09, 2012 Administrative Approval $37,700.00 Amendment No. 5 February 19, 2012 Administrative Approval $5,500.00 • EXHIBIT"A", PART 1. SCOPE OF SERVICES,SECTION A. BASIC SERVICES, Item No.2 DESIGN PHASE shall be modified to include revisions on plan sheets as shown on the attached Exhibit"A". • EXHIBIT"A",PART 3. FEES shall be modified as shown on the attached Exhibit"B"for a revised fee not to exceed$38,770.00(Thirty Eight Thousand Seven Hundred Seventy Dollars and Zero Cents),for a total restated fee not to exceed$1,298,546.70(One Million Two Hundred Ninety Eight Thousand Five Hundred Forty Six Dollars and Seventy Cents). All other terms and conditions of the June 19, 2009 contract and amendments between the City and Consultant will remain in full force and effect. CITY OF - •RPUS -ISTI HDR ENGINEERING, INC. AO 4111 3 . . , �- .��.� / y Gustavo G,,nzalez, P. '111 (Date) Carl E. Crull, P.E. (Date) Assistant CI Manag= of Public Works Vice President & Utilities 555 N. Carancahua, Suite 1600 Corpus Christi, TX 78401-0850 (361) 696-3300 Office; (361) 696-3385 Fax RECOMMENDED Daniel Biles, P.E. (Date) Executive Director of Public Works Project Number: 6511 Funding Source: 550950-3126-00000-170678 Encumbrance Number: E(.19 i A ND i_ ENTERED 3' 13. APPR• 'ED MAR 112014 Offi 'e o Management and Budget (Bat-) CONTRACT MANAGERS 2014-111 AMEND. No. 6 3/13/14 Page 1 of 2 s\6511-Bayfront Development Plan Phase 3\HDR-Amendment No.6\AMENDMENT No.6 doc HDR Engineering Inc. INDEXED APP ED AS TO FORM Assistant City Attorney (Date) ATTEST ebecca Huerta, City Secretary AMEND. No. 6 Pa•e 2 of 2 K:\Engineering DataExchange\Clarissa)\Parks\6511-Bayfront Development Plan Phase 3\HDR-Amendment No.6\AMENDMENT No 6.doc �;€�:z � v? ��n r,-mss •fklal ()NB COMI)A IY j 7�rrx I eht'uary .b.2014 111)1 Project 1!1.11570 Mrs. \atasha Fudge. P.1... Assistant I)trector. Capital Con.,:truction Ptojects City ofCorpus Christi knf!inccrinr! 12111 Leopard Street t:'orpus Christi. 1'X 78401 RI : Ba yfrtint I)evelopment Plan Ph 3 Project No. 6511 .Ainendmenf I() Dear\Its. 1°udae. As requested, 111)R has revised the scope and fee I t'tt inally presented h) the (ir by letter on January 7.2014 f modifying the 13a front consiructioi thaw anu:iry 7' letter incorrectly numerated the ptoposetl atitendntern as number 5. the correct amendment number is as seen in the subject line above, During a meeting on February I311', City stall informed 111)R that design modification Oplion (` h om the enclosed Fxhibit A Was their preferred alternative. Option C modifies the median locations and removes the reverse-in it kin_; areas. Feedback from ('itv stall during this meeting and a Fehruar■ I.7° nleetin,t utihred as the basis for updating the scope rtnil fi e. I.xltihit B is enclosed as a reference to which scope items City staff requested 111)R to remove and which scope items to retain. The following is a list of the scope items r etnrnved at the G'ig's request: o Assisting City staff fir generating change order presentation to City Council O (_coordination with traffic engineering lot traffic analysis O 1(10%City Review and Comment process o t'pdate of'Sheet Index m Update of l cl' Sheets 74 tluu tea for record chay.inigs G 1\9odifieation ol'sunlit sewer trunl: lire alignment o Rerun hydraulic analysis • Update SW3P sheets o Niodific ttietn of s.init ary se\';et tl uth. line alignment • Additional sanitary sewer stub-outs for future access o t?pd;itc of stripini' and signing sheets(to be deferred to a later time) o Coordination with Lauren (iriffith and Associates for hardseape. Iandseal.e.and irrigation updates "I he revised fee fir providing services detailed in FFxhihit B under Opton C in the amount of$38,770.(t0. Services provided encompass revisions ton a total of' I3 Matt ;i'ect 111)R i t prcpau'Cd to begin modifvinr! the I3ayfroitt construction edraw iii,ts upon receipt of an :ipproved and executed Aniendmcnt 116 to I ll)R's current contract. fiCir y err In i T:xa RC,s,�srt Er31t,=t'tnrFrrnr-i'.i; i>r if-_J r Corpus C SOS.rt 7r:DI iEG ',';'It n'n EXHIBIT"A" .y Ntex Page 1 of 2 F. nr, lit4 2 of 2 I flli� M=ould like to also take this ()pro,tunit) to rc'f ind the City of(he maintenance cost needed for the current proposed landscape plan oftile l a y front construction dla wines. 1 he maintenance cost for the project landscaping was intended to be funded by the 1)cstination liayliont park development. lithe City's budget cannot fund the maintenance cost oldie proposed landscaping. the (`it' may consider reducing the landscaping along the project to a manageable size. if the City has any questions regarding the infi7rmation provided, don't hesitate to contact us. Sincerely. I II)l' !"(i! ;I:::I:R['v(i • ('ctrl k. 01111. P.k. :attachments: I:,xhihit :A Project (.'onccpt Exhibit li Scope of Services for Sheet Modification: (.'c: David Ambriz. Senior i ngineer llr}n • TVX� iZ pi ?t ! trsnf:. rirrl:f ?`S Crirrj CI nsti TX 1'd101-0 irtl fifitifr:(nu EXHIBIT"A" Page 2 of 2 SUMMARY OF FEES BAYFRONT DEVELOPMENT PLAN, PHASE 3 BOND ISSUE 2008 Project No. 6511 Amendment Amendment Amendment Amendment Amendment Amendment No. Initial Contract No.1 No.2 No.3 No.4 No.5 6 Total Fee for Basic Services 1.Preliminary Phase $42,000.00 $74,836.40 $0.00 $23,000.00 $37,700.00 $0.00 $0.00 $177,536.40 2.Design Phase $0.00 $495,300.00 $0.00 $0.00 $0.00 $0.00 $38,770.00 $534,070.00 3.Bid Phase $0.00 $16,015.10 $0.00 $0.00 $0.00 $0.00 $0.00 $16,015.10 4.Construction Phase $0.00 $92,022.00 $0.00 $0.00 $0.00 $0.00 $0.00 $92,022.00 Subtotal Basic Services Fees $42,000.00 $678,173.50 $0.00 $23,000.00 $37,700.00 $0.00 $38,770.00 $819,643.50 Fee for Additional Services(Allowance) 1.Traffic Analysis $0.00 $32,563.20 $3,500.00 $21,100.00 $0.00 $5,500.00 $0.00 $62,663.20 2.Public Involvement and Coordination Meetings (Authorized) $0.00 $49,458.80 $0.00 $0.00 $0.00 $0.00 $0.00 $49,458.80 3.Permit Preparation(as applicable)(Authorized) $0.00 $13,906.40 $0.00 $0.00 $0.00 $0.00 $0.00 $13,906.40 4.Topographic and ROW Acquisition Survey and Parcel Maps(Authorized) $0.00 $91,320.20 $0.00 $0.00 $0.00 $0.00 $0.00 $91,320.20 5.Subsurface Utility Engineering(Authorized) $0.00 $83,446.00 $0.00 $0.00 $0.00 $0.00 $0.00 $83,446.00 6.Construction Observation Services(up to 20 hours per week for up to 14 months) $0.00 $163,353.00 $0.00 $0.00 $0.00 $0.00 $0.00 $163,353.00 7.Warranty Phase $0.00 $14,755.60 $0.00 $0.00 $0.00 $0.00 $0.00 $14,755.60 Sub-Total Additional Services Fees $0.00 $448,803.20 $3,500.00 $21,100.00 $0.00 $5,500.00 $0.00 $478,903.20 Total Fee $42,000.00 $1,126,976.70 $3,500.00 $44,100.00 $37,700.00 $5,500.00 $38,770.00 $1,298,546.70 6/19/2009 5/18/2010 7/7/2010 10/12/2010 1/9/2012 2/19/2012 Admin Approval M2010-115 Admin Approval Admin Approval Admin Approval Admin Approval Admin Approval IIIIMIONINIMI rn m k ca = O W O .a W Sample form for: COMPLETE PROJECT NAME Payment Request Revised 07/27/00 Project No. XXXX - Invoice No. 12345 Invoice Date: Total Amount Previous Total Percent Basic Services: Contract Amd No. 1 Amd No. 2 Contract Invoiced Invoice Invoice Complete Preliminary Phase $1,000 $0 $0 $1,000 $0 $1,000 $1,000 100% Design Phase 2,000 1,000 0 3,000 1,000 500 1,500 50% Bid Phase 500 0 250 750 0 0 0 0% Construction Phase 2,500 0 1,000 3,500 0 0 0 0% Subtotal Basic Services $6,000 $1,000 $1,250 $8,250 $750 $1,500 $2,500 30% Additional Services: Permitting $2,000 $0 $0 $2,000 $500 $0 $500 25% Warranty Phase 0 1,120 0 1,120 0 0 0 0% Inspection 0 0 1,627 1,627 0 0 0 0% Platting Survey TBD TBD TBD TBD TBD TBD TBD 0% 0&M Manuals TBD TBD TBD TBD TBD TBD TBD 0% SCADA TBD TBD TBD TBD TBD TBD TBD 0% Subtotal Additional Services $2,000 $1,120 $1,627 $4,747 $500 $0 $500 11% Summary of Fees Basic Services Fees $6,000 $1,000 $1,250 $8,250 $750 $1,500 $2,500 30% Additional Services Fees 2,000 1,120 1,627 4,747 500 0 500 11% Total of Fees $8,000 $2,120 $2,877 $12,997 $1,250 $1,500 $3,000 23% • DT K 0 al go 2 , . . . . • . n SIPP I R NtM3IR TO RI vSSi(;NED I) CT V _ PURCHASING DIVISION City of CITY OF CORPUS CHRISTI Corpus DISCLOSURE OF INTEREST Christi City of Corpus Christi Ordinance 171 12. as amended, requires all persons or firms seeking to do business with the City to provide the following information. Every question must be answered. If the question is not applicable. answer with "NA". See reverse side for Filing Requirements, Certifications and definitions. COMPANY NAME: HDR Engineering, Inc. P. O. BOX: N/A STREET ADDRESS: 555 N. Carancahua,Suite 16 O CITY: Corpus Christi ZIP: 78401 FiRM IS: I. Corporation I. 2. Partnership — 3. Sole Owner ❑ 4. Association 5. Other DISCLOSURE QUESTIONS If additional space is necessary. please use the reverse side of this page or attach separate sheet. I. State the names of each "employee" of the City of Corpus Cvisti having an "ownership interest'constituting 3%or more of the ownership in the above named "firm." Name Job Title and City A./4' Department(ii'known) 2. State the names of each "official"of the City of Corpus Christi having an "ownership interest constituting 3%or more of the ownership in the above named "firm. Nary Title 3. State the names of each "board member" of the City of Corpus Christi having an "ownership interest'constituting 3%or more of the ownership in the above named "firm." Name Board. Commission or _..................._.... Committee 4. State the names of each employee or officer of a "consultant" for the City of Corpus Christi who worked on any matter related to the subject of this contract and has an "ownership interest'constituting 3%or more of the ownership in the above named "firm." Name Consultant /04 — — EXHIBIT"D" Page 1 of 2 FILING REQUIREMENTS If a person who requests official action on a matter knows that the requested action will confer an economic benefit on any Cite official or employee that is distinguishable from the effect that the action ■+ill have on members of the public in general or a substantial segment thereof. you shall disclose that fact in a signed writing to the City official, employee or body that has been requested to act in the matter, unless the interest of the City official or employee in the matter is apparent. The disclosure shall also be made in a signed writing filed with the City Secretary. [Ethics Ordinance Section 2-349(d)] CERTIFICATION I certify that all information provided is true and correct as of the date of this statement, that I have not certify withheld disclosure of any information requested; and that supplemental statements will be promptly submitted to the City of Corpus Christi,Texas as changes occur. Certifying Person: Carl E. Crull,P.E. Title: Vice President (Type or r'rintl Signature of Certifying i Date: /// Person: I/ /67/,' DEFINITIONS a. "Board member." A member of any board. commission, or committee appointed by the City Council of the City of Corpus Christi. Texas. b. "Economic benefit". An action that is likely to affect an economic interest if it is likely to have an effect on that interest that is distinguishable from its effect on members of the public in general or a substantial segment thereof. c. "Employee." Ally person employed by the City'of Corpus Christi. Texas either on a full or part-time basis, but not as an independent contractor. d. "Firm." Any entity operated for economic gain. whether professional, industrial or commercial, and whether established to produce or deal with a product or service, including but not limited to. entities operated in the form of sole proprietorship, as self-employed person. partnership. corporation,joint stock company,joint venture. receivership or trust. and entities which for purposes of taxation are treated as non-profit organizations. e. "Official." The Mayor. members of the City Council, City Manager, Deputy City Manager, Assistant City Managers. Department and Division Heads. and Municipal Court Judges of the City of Corpus Christi. Texas. f: "Ownership Interest." Legal or equitable interest, whether actually or constructively held. in a firm, including when such interest is held through an agent, trust, estate. or holding entity. "Constructively held" refers to holdings or control established through voting trusts, proxies, or special terms of venture or partnership agreements." g "Consultant."Any person or firm, such as engineers and architects. hired by the City of Corpus Christi for the purpose of professional consultation and recommendation. EXHIBIT"D" Page 2 of 2