HomeMy WebLinkAboutC2014-259 - 7/3/2014 - NA • AMENDMENT NO. 11 RATIFICATION TO CONTRACT FOR PROFESSIONAL SERVICES The City of Corpus Christi, Texas hereinafter called "CITY", and Freese and Nichols, Inc. agree to the following amendment to the Contract for Professional Services for Garwood Water Supply Project (Project No. 8424), as authorized and amended by: Original Agreement October 28, 2003 Motion No. M2003-394 $116,100.00 Amendment No. 1 October 19, 2004 Motion No. M2004-387 $285,490.00 Amendment No. 2 Ciecember 18, 2007 Motion No. M2007-334 $911,997.00 Amendment No. 3 March 11, 2009 Administrative Approval $0.00 Amendment No. 4 March 9, 2010 Motion No. M2010-051 $9,676,590.00 Amendment No. 5 November 30, 2011 Administrative Approval $0.00 Amendment No. 6 January 14, 2012 Administrative Approval $49,940.00 Amendment No. 7 April 24, 2013 Administrative Approval $49,822.00 Amendment No. 8 May 29, 2013 Administrative Approval $49,900.00 Amendment No. 9 July 30, 2013 Motion No. 2013-125 $195,664.00 Amendment No. 10 February 15, 2014 Motion No. 2014-027 $3,965,785.00 Amendment No. 11 revises the project scope for Mary Rhodes Pipeline Phase 2 (Proiect No. E10008) to the Garwood Water Supply Project as follows: Exhibjt "A", Section 1. Scope of Services, Part A. Basic Services 3. Design Phase and 4.Bid Phase, shall be modified to include services for the pre-purchase of pumps and motors for the Intake and Booster Pump Stations as specified in Amendment No. 11 Exhibit "A". Exhibjt "A", Section 3. Fees, shall be modified as specified in Amendment No. 11 Exhibit "A" for a revised fee not to exceed $49,000.00 (Forty-Nine Thousand Dollars and Zero Cents), for a total restated fee not to exceed $15,350,288.00 (Fifteen Million Three Hundred Fifty Thousand Two Hundred Eighty-Eight Dollars and Zero Cents). Monthly invoices shall be submitted in accordance with Amendment No. 11 Exhibit "B". All other terms and conditions of the October 28, 2003 contract and amendments between the City and Freese and Nicho will r- .in full force and effect. CITY0/. • - J FREESE AND NICHOLS, INC. i`14j�!�/�/ 12- .lam *14- Ronald le!on, (Date) Ron G zman, P.E., (Date) City -n- ,er Principal 800 North Shoreline Blvd., Suite 1600N 1 , 3. N Corpus Christi, TX 78401 Gustavo G 'nzalez, P.E.,O (Date) (361)561-6500 Office Assistant C y Manager, (361)561-6501 Fax Public Works and Utilities 0-1C) ÷e -VOX Daniel Biles, P.E., (Date) 2014-259 7/03/14 AMEND. NO. 11 Page 1 of 2 Freese and Nichols Inc. I0008 MARY RHODES PIPELINE,PHASE 2\FREESE AND NICHOLS,INC\AMENDMENT NO.11\CONTRACT.DOCX INDEXED RECOMMEND ' '41t? .i _, , r e-( o.- at' f epartmen' - Date) • APPR VED AS TO FORM -251# Legal Department (Datb) APPR ED Offic46kL44v anagement and Budget Date) ATTEST Rebecca Huerta, City Secretary Project No: E10008 Fund Source No: 550950-4095-00000-E10008 Fund Name:Water 2014 CIP Encumbrance No: E R9 AMEND. NO. 11 Page 2 of 2 EXHIBIT "A" CITY OF CORPUS CHRISTI, TEXAS Mary Rhodes Pipeline, Phase 2 Amendment No. 11 (City Project No. E10008) I. Scope of Services: A. Basic Services Scope Revision: Add the following tasks as shown below: 3. Design Phase Produce a bid package for the pre-purchase of pumps and motors for the Intake and Booster Pump Stations. Work with the Purchasing, Legal and Engineering Departments to produce front-end documents and technical plans and specifications for the pre-purchase of pumps and motors. 4. Bid Phase Perform bid phase services including pre-bid meeting attendance, answering bidders questions, bid opening, bid tabulation, and award recommendation for the pre-purchase of pumps and motors for the Intake and Booster Pump Stations. II. Schedule: Final Design Phase October, 2013 Bid Phase February, 2014 III. Fee: The total authorized fee for all services added to the contract with through this Amendment will be$49,000. Fees for individual additional tasks are shown in the Summary of Fees table. The table Summary of Fees set forth on the following page will be used by the Consultant Engineer to determine the amount to be invoiced for each task. The fee shown for each task is inclusive of all expenses as set forth by the original contract. Summary of Fees TASK Description Fee Original Contract—Phase 1 I.A.1 Screening Study of Delivery Options $116,100.00 I.A.2 Detailed Study of Delivery Options TBN I.A.3 Pipeline Route Study TBN I.A.4 Pipeline Surveying, Easement Acquisition, and Permitting TBN I.A.5 Pipeline Topographic Survey and Preliminary Design TBN AMENDMENT NO. 11 EXHIBIT"A" Page 1 of 8 Revised March 6,2014 I.A.6 Final Design Phase TBN I.A.7 Bid, Award, and Construction TBN Original Contract Fee $116,100.00 Amendment No. 1 —Phase 2 2.A Detailed Study of Delivery Option 5 $152,532 2.B Detailed Study of Delivery Option 1 $64,328 2.0 Detailed Study of Delivery Option 6 $68,630 Amendment No. 1 Fee $285,490 Amendment No. 2—Phase 2A 2A-0001 Field Studies 2A.1.A —Ownership Mapping $ 20,631 2A.1.B —Risk Analysis $ - Prepare Risk Analysis $ 5,853 Risk Analysis Workshop (in CC) $ 4,533 2A.1.0 Field survey of West Mustang Creek $ 46,922 2A.1.D —West Mustang Creek Habitat Assessment $ 34,272 2A.1.E —Coordination Re-Calib. Of Gannado Gauging Station $ 6,168 2A.1.F —Summary $ - Prepare Task Summary $ 11,650 Task Summary Workshop (in CC) $ 8,383 Total Fee by Classification $ 138,411 2A-0002 LCRA Agreement 2A.2.A —Agreement Framework $ - Prepare Framework $ 12,695 Submit Framework $ 431 Schedule Framework Meeting $ 451 2A.2.B —Framework Meeting (Garwood) $ 7,235 2A.2.0 —Prepare Draft LCRA Agreement $ 10,525 2A.2.D —Draft LCRA Agreement Workshop (Garwood) $ 6,366 2A.2.E Prepare Final Agreement $ 8,740 2A.2.F Task—Execute Agreement(1 meeting Austin, 1 meeting Corpus Christi) $ 8,151 2A.2.G —Task 2 Summary $ 14,675 Total Fee by Classification $ 69,268 2A-0003 LNRA Agreement 2A.3.A —Agreement Framework $ - Prepare Framework $ 13,025 Submit Framework $ 431 Schedule Framework Meeting $ 451 AMENDMENT NO. 11 EXHIBIT"A" Page 2 of 8 Revised March 6,2014 2A.3.B —Framework Meeting (Edna) $ 7,191 2A.3.0 —Prepare Draft Agreement $ 10,525 2A.3.D —Draft LNRA Agreement Review Workshop (Edna) $ 7,191 2A.3.E —Regulatory Coordination (2 meetings Austin) $ 10,137 2A.3.F —Prepare Final LNRA Agreement $ 6,815 2A.3.G —Execute Agreement(1 meeting Edna, 1 meeting Austin) $ 11,360 2A.3.H —Task 3 Summary $ 14,125 Total Fee by Classification $ 81,250 2A-0004 Permitting and Agency Coordination 2A.4.A —Coord w/TPWD re: GSM Permit(2 meetings Austin) $ 3,737 2A.4.B —Coord w/TPWD re: LNRA Inflow/Release Agreement(3 meetings Austin) $ 5,156 2A.4.0 —Coord w/TCEQ re: Bed and Banks Permit(3 meetings Austin) $ 7,104 2A.4.D —Coord w/TGLO re: Bed and Banks Permit(3 meetings Austin) $ 7,104 2A.4.E —Coordination with TCEQ and TWDB re: Regional Water Planning (2 meetings Austin) $ 1,437 2A.4.F —Regional Water Planning Group Coordination (1 meeting Austin, 1 meeting Corpus Christi) $ 2,979 2A.4.G —Monitor LCRA/SAWS Project (2 meetings Garwood) $ 6,437 2A.4.H —USACE Coord (1 meeting Galveston) ' $ 8,253 2A.4.I —TPDES Coordination (1 meeting Austin) $ 6,566 2A.4.J —Landowner Issues and Communications (3 meetings Edna) $ 20,785 2A.4.K —Meet w/ Environmental Groups $ - Prepare Exhibits $ 13,093 Meeting 1 $ - Plan $ 501 Schedule $ 471 Prepare for Meeting $ 3,745 Attend Meeting (Austin) $ 2,376 Meeting 2 $ - Plan $ 501 Schedule $ 471 Prepare for Meeting $ 3,745 Attend Meeting (Austin) $ 2,376 Meeting 3 $ - Plan $ 501 Schedule $ 471 Prepare for Meeting $ 3,745 Attend Meeting (Edna) $ 3,591 2A.4.L —Task 4 Summary $ 16,070 AMENDMENT NO. 11 EXHIBIT"A" Page 3 of 8 Revised March 6,2014 • Total Fee by Classification $ 121,216 2A-0005 Permitting Activities 2A.5.A —Bed and Banks Permit Application $ - Prepare Permit $ 20,655 Submit Permit $ 6,360 Agency Review $ 8,115 Permit Approval $ 5,203 2A.5.B —Prepare Amendment to TPWD/LNRA Inflow& Release Agreement $ - Develop Amendment Framework $ 3,815 Meet with LNRA and TPWD to develop amendment outline (1 mtg Edna) $ 4,441 Develop Draft Amendment $ 4,075 Meet with LNRA and TPWD to review Draft Amendment(1 mtg Edna) $ 4,441 Prepare Final Amendment $ 3,735 Obtain Written Approval (1 mtg Austin, 1 mtg Edna) $ 6,540 2A.5.0 —Water Right Amendment Application $ - Prepare Permit $ 10,815 Submit Permit $ 961 _ Agency Review $ 4,210 _ Permit Approval $ 1,023 2A.5.D —Monitor Permit Application Status $ 2,045 2A.5.E —Regulatory Agency Coord During Permit App Process $ 2,945 2A.5.F —Develop Supporting Info for Region N Amendment $ 5,130 2A.5.G —Coordinate Region N Amendment(2 meetings CC) $ 11,475 2A.5.H —Amend Water Conservation/Drought Management Plan $ - Prepare Draft Amendment $ 3,408 Plan Workshop (CC) $ 4,533 Submit Draft Amendment $ 1,120 City Review of Draft Amendment $ - Review Workshop (CC) $ 4,533 City Review Complete $ - Incorporate City Comments/Prepare Final Amendment $ 3,535 City Council Approval of Final Amendment(CC) $ 4,533 2A.5.F —Task 5 Summary $ 15,227 Total Fee by Classification $ 142,870 2A-0006 Conceptual Facility Design 2A.6.A —GIC Facility Requirement Workshop $ 330 Schedule Workshop $ 681 Conduct Workshop (Garwood) $ 6,393 AMENDMENT NO. 11 EXHIBIT"A" Page 4 of 8 Revised March 6,2014 2A.6.B —Concept Design of GIC Canal System Improvements $ 4,800 2A.6.0 —Concept Design of West Mustang Creek Div. Structure $ 4,800 2A.6.D —Design Review Workshop $ _ Schedule Workshop $ 681 Conduct Workshop (Garwood) $ 6,393 2A.6.E —W. Mustang Creek Gauging Facility Workshop $ 6,900 Schedule Workshop $ 681 Conduct Workshop (Edna) $ 4,193 2A.6.F —Concept Design, W. Mustang Creek Gauging Facility $ 3,960 2A.6.G —W. Mustang Creek Gauging Facility Workshop $ - Schedule Workshop $ 681 Conduct Workshop (Edna) $ 6,393 2A.6.H —Task Summary $ 10,275 Total Fee by Classification $ 57,164 2A-0007 Mary Rhodes Pipeline Assessment 2A.7.A —Data Collection and Review $ 8,648 2A.7.B —Facilities Site Visit $ 23,266 2A.7.0 —Task Kickoff Workshop (Corpus Christi) $ 8,605 2A.7.D —Pump Station Assessment $ 17,008 2A.7.E —SCADA System Assessment $ 11,840 2A.7.F —Operational Integration of Garwood Water $ 6,200 2A.7.G —Alternatives Identification and Screening $ 27,613 2A.7.H —Alternative Control Strategies $ 11,335 2A.7.I —Recommended Mary Rhodes Pipeline Improvements $ 6,205 2A.7.J —Task 7 Summary $ - Prepare Summary $ 16,200 Attend Workshop $ 5,768 Total Fee by Classification $ 142,686 2A-0008 Task 8— Phase 2A Report 2A.8.A —Prepare Draft Report $ - Prepare Report $ 25,656 Submit Draft Report to City for Review $ 1,292 City Review of Draft Report $ - City Review Complete $ - 2A.8.B —Prepare Draft Report Presentation $ 7,112 2A.8.0 —Draft Report Workshop (Corpus Christi) $ 9,169 2A.8.D —Draft Report Comments Meeting (Corpus Christi) $ 9,169 2A.8.E —Prepare Final Report $ 10,321 2A.8.F —Final Report Presentation (up to 3 meetings in Corpus Christi) $ 34,669 AMENDMENT NO. 11 EXHIBIT"A" Page 5 of 8 Revised March 6,2014 • $ 97,388 2A-0009 Project Management 2A.9.AOBC1 Task 9.A—Project Schedule $ 10,060 2A.9.BOBC2 Task 9.B—Progress Reports and Invoices $ 23,342 2A.9.COBC3 Task 9.0—Phase 3 Scoping $ 28,343 Total Fee by Classification $ 61,744 Amendment No. 2 Fee $ 911,997 Amendment No. 3 2A-0005 Task 5 - Permitting Activities (Deleted in its Entirety) $ -142,870 2A-0008 Task 8—Phase 2A Report(Deleted in its Entirety) $ -97,388 3-00010 Task 10 -Garwood Alignment Study Scope of Work 3-0010.1 Data Collection $ 49,709 3-0010.2 Preliminary Hydraulic Study $ 21,975 3-0010.3 Preliminary Environmental Review $ 60,294 3-0010.4 Preliminary Route Analysis $ 45,364 3-0010.5 Final Route Analysis $ 62,916 Amendment No. 3 Fee $ 0 Amendment No. 4 1 Study Phase $ 0 2 Preliminary Phase $ 1,514,814 3 Design Phase $ 3,068,522 4 Bid Phase $ 102,000 5 Construction Phase $ 1,200,000 A- 1 Permitting $ 267,414 A—2 ROW Acquisition Survey $ 350,000 A-3 Topographic Survey $ 891,165 A—4 Subsurface Utility Exploration $ 286,000 A—5 Aerial Photography $ 23,750 A—6 Corrosion Engineering $ 122,768 A—7 Surge Analysis $ 104,181 A—8 Geotechnical Investigation $ 312,737 A—9 Archeological Investigation $ 184,650 A— 10 Hydraulic Modeling $ 37,398 A— 11 ROW Acquisition $ 1,060,601 A— 12 Construction Observation Services $ TBD A— 13 Start-Up Services $ TBD AMENDMENT NO. 11 EXHIBIT"A" Page 6 of 8 Revised March 6,2014 A— 14 O&M Services $ 150,590 A— 15 Warranty Phase $ TBD A— 16 Provide SCADA Documentation $ TBD Amendment No. 4 Fee $ 9,676,590 Amendment No. 5 2 Preliminary Phase $ 0 3 Design Phase $ 183,179 4 Bid Phase $ 82,814 A- 1 Permitting $ 53,696 A- 3 Topographic Survey $ 37,035 A—4 Subsurface Utility Exploration $ -121,045 A—8 Geotechnical Investigation $ 18,749 A—9 Archeological Investigation $ -87,808 A— 10 Hydraulic Modeling $ 36,102 A— 11 ROW Acquisition $ -202,722 Amendment No. 5 Fee $ 0 Total Fee $10,990,177 Amendment No. 6 2 Preliminary Phase $ 2,340 A— 11 ROW Acquisition $ 47,600 Amendment No. 6 Fee $ 49,940 Total Fee $11,040,117 Amendment No. 7 Study Phase $ $49,822 Amendment No. 7 Fee $ $49,822 Total Fee $ 11,089,939 Amendment No. 8 A-4 Subsurface Utility Exploration $ 49,900 Amendment No. 8 Fee $ 49,900 Total Fee $ 11,139,839 Amendment No. 9 3 Design Phase Monthly Meetings $ 14,554 60% and 90% Review Meetings/Workshops $ 10,943 Develop Sequence of Operations/Control Narratives $ 22,080 Integration, Verification, and Validation (IW) Specs $ 20,315 AMENDMENT NO. 11 EXHIBIT"A" Page 7 of 8 Revised March 6,2014 • Coordination with Electrical Subcontractor $ 5,378 Integration of Mary Rhodes Phase 1 with Phase 2 $ 15,206 5 Construction Phase Answer RFI's $ 2,588 Construction Meetings/Site Visits $ 30,708 Review Shop Drawings $ 10,876 Control Meetings with Contractor(System Integrator) $ 12,911 Factory Acceptance Testing (FAT) $ 17,271 Start-up/Checkout of Controls $ 20,315 Site Acceptance Testing $ 12,519 Amendment No. 9 Fee $ 195,664 Total Fee $ 11,335,503 Amendment No. 10 12 Construction Management Services $ 3,965,785 Amendment No. 10 Fee $ 3,965,785 Total Fee $15,301,288 Amendment No. 11 3 Design Phase $ 20,000 4 Bid Phase $ 29,000 Amendment No. 11 Fee $ 49,000 Total Fee $ 15,350,288 AMENDMENT NO. 11 EXHIBIT"A" Page 8 of 8 Revised March 6,2014 tone Srto Payment Rows* COMPLETE PROJECT NAME Revised 07/27409 Project No.XXXX Invoice No. 12345 invoice Date: Total Amount Previous Total Percent Basic Services: Contract Amd No. 1 Amd No. 2 Contract invoiced invoice invoice Complete Preliminary Phase $1,000 $0 $0 $1,000 $0 $1,000 $1,000' 100% • Design Phase 2,000 1,000 0 3,000 1,000 500 1,500 50% Bid Phase 500 0 250 750 0 0 0 0% • Construction Phase 2,500 0 1,000 3,500 0 0 0 0% Subtotal Basic Services $6,000 $1,000 $1,250 $8,250 $750 $1,500 $2,500 30% Additional Services: Permitting $2,000 $0 $0 $2,000 $500 $0 $500 25% Warranty Phase 0 1,120 0 1,120 0 0 0 0% Inspection 0 0 1,627 1,627 0 0 0 0% Platting Survey TBD TBD TBD TBD TBD TED TBD 0% 0& M Manuals TBD TBD TBD TBD TBD TBD TBD 0% SCADA TBD TBD TBD TBD TBD TBD TBD 0% Subtotal Additional Services $2,000 $1,120 $1,627 $4,747 $500 $0 $500 11% . Summary of Fees . Basic Services Fees $6,000 $1,000 $11250 $8,250 $750 $1,500 $2,500 30% Additional Services Fees 2,000 1,120 1,627 4,747 500 0 500 11% Total of Fees $8,000 $2,120 $2,877 $12,997 $1,250 $1,500 $3,000 23% c R .a • CTS OF CORPUS CHRISTI DISCLOSURE OF INTEREST City ofChristi Ordinance 17112 as amended,requires all persons or firms Acing to do business Corpusith the City to provide the followinginformatlon. Everyymust , If the is not applicable, answer with''NA", Sc.reverse Filing Certifications end definitions. COMPANY NAME: Freese and Nichols P.O.BOX: N/A STREET ADDRESS: saw i Shoreline fid' an,: Corpus Christy ZIP: nal FIRM IS; 4. Caporation 2. Partnership 8 3, Sole Owner 0 DISCLOSURE QUESTIONS If additional specs is necessary+,please use the reverse side of thisor attach separate sheet. I. State the names of each employee" of the Citi;of Corpusplhaving an "ownership interest"constituting 3%or more of the ownership in the above named"firm. Name Job Title and City Department(if known) 2. State die names of each"official"of the City of Corpus Christi having an"ownership interest" constituting 3%or more of the ownership in the above named"firm." Name V-)/Par Title 3. State the names of each"board member"of the City of Corpus Christi having an"ownership interest"constituting 3%or more of the ownership in the above named"firm. Name Board, Commission or 1%-)Ate Committee 4. State die names of each employee or officer of a"consultant" for the City of Core Christi who worked on any matter related to the subject of this contract and has an ownership interest"constituting 3%or more of the ownership in the above named"firm." Name /rair Consultant p a p FILING REQUIREMENTS If a person who requests official action on a matter knowsthat the uested action will confer an economic benefit on any City official or employee that is le from the effect that the action will have on members of the public in general ora substantial segment thereof,you shall disclose that fact in a signed writing to the City official,employee or body that has been requested to act in the natter,unless the interest of the City,oDeist or employee in the matter is The disclosure sha11 also be made in a signed writing filed with the City Secretary. tgritcysittordinance Section 2-349 OM CERTIFICATION I certify that all information provided is true and correct as of the date of this statement,that I have not_la owingly withheld disclosure of any infomation , and that supplemental statements will be promptly submitted to the City of Corpus�exas as changes occur. Certifying Person: Ron Comm,P.E. Title: Principal erne sr min Signature of Certify Date: Person. DEFINITIONS a. "Board member." A member of any board, commission, or committee appointed by the City Council of the City of Corpus Christi,Texas. b. "Economic benefit". An action that is likely to affect an economic interest if it is likely to have an effect on that interest that is distinguishable from its effect on members of the public in general or a substantial segment thereof. c. "Employee." Any person employed by the City of Corpus Christi,Texas either on a full or part-time basis,but not as an independent contractor. d. "Firm." Any entity operated for economic gain, whether professional, industrial or commercial,and whether established to produce or deal with a product or service, including but not limited to, entities operated in the form of sole proprietorship, as self-employed person,partnership,corporation,.Wint stock company,.Wint venture,receivership or trust,and entities which for purposes of taxation are treated as non-profit organizations. e. "Official." The Mayor, members of the City Council, City Manager, Deputy City Manager, Assistant City Managers, Department and Division Heads, and Municipal Court Judges of the City of Corpus Christi,Texas. f. "Ownership Interest." Legal or equitable interest,whether actually or constructively held, in a firm, including when such interest is held through an agent, trust, estate, or holding entity. "Constructively held"refers to holdings or control established through voting trusts, proxies,or special terms of venture or partnership agreements." g. "Consultant"Any person or firm, such as engineers and architects, hired by the City of Corpus Christi for the purpose of professional consultation and recommendation.