CHANGE ORDER
INTRODUCTION
This Change Order document ("Change Order") is subject to all terms and conditions of the
Software Services Agreement(or, if applicable, the Professional Services Agreement) between
Infor and Licensee with an Effective Date of May 15, 2013(the "Services Agreement") and
constitutes a change to the Services Work Order identified below by Work Order Number("Work
Order"). All terms of the Services Agreement and Work Order are incorporated herein by
reference. Capitalized terms not defined in this Change Order are defined in the Services
Agreement or Work Order. In the event of a conflict, the terms of this Change Order control over
the terms of the Services Agreement and Work Order.
1.0 CHANGE ORDER
Licensee(customer) City of Corpus Christi
Project Name Hansen CDR
Project Number 32381430
Project Manager Benjamin Zimon
Project Phase Design
Product(s) Hansen 8.3
Work Order Number Amendment 2
Change Number CO2014 001
Issue Number 001
Description Hansen 8.3, CDR Implementation, Design, and Consulting Services for the Health
Department
Requestor Aurora Parlamas
Identified Date 06/16/2014
Prepared By Benjamin Zimon
Change Status Log Date
Initial identification/assessment 6/2/2014
Approved for detailed impact analysis(optional)
2014-324
9/16/14
N12014-117
Infor INDEXED
Pending Approval
Final Approval Approved Denied
Updated project and budget plans
1.1 Preliminary identification and assessment
Describe the change in detail
City of Corpus Christi, Health Department will need Infor consultants to provide Design,
Configuration of 8 newly indentified Applications (shown below), Assistance with Data Migration
Mapping to Hansen, and Testing.
odule. Dept App type Description Worktype
Swimming
BL Health To be defined Pool
To be defined 1) Day Care
Supervised 2) Foster
BL Health Care Home
BLDG Health To be defined Septic
BL Health To be defined Restaurant
To be defined 1) Food
Food Handler
Handler/ 2) Food
Trade Health Manager Manager
To be defined Mobile Food
BL Health Vending
To be defined Health Temp
BL Health Event
Case Health To be defined Health Case
Reason for the change
Health Department was not included part of the original CDR project scope of work. the majority of data
required for Health's migration sits outside of Sungard"s H.TE.
High level impact assessment
Additional project scope to support Health Department functionality will require additional resources and
will increase project duration and budget
The impact will extend the project duration another month from February 2015 to March 2015, we will also
look to double up on our configuration resources COE and internal for several weeks The resource impact
to the city is more noticeable as MIS resources will need to be involved for the data migration out of the
legacy Health department applications/databases.
It is proposed and mutually agreed the Health Department will go live in production with the overall project
The project schedule is being revised to a March 2015 CDR go-live to support inclusion of the Health
Department in the City's go-live.
2
inFor Change Order(Americas PMO-v5b,Nov 2012)
1.2 Approval for detailed impact analysis (optional)
Reviewer No additional information
Review Date
1.3 Detailed impact analysis
Impact on project plan(including estimated timelines)
Schedule and Resource constraints. Estimated duration of Design to Deliver effort is 8 weeks.
Upon approval, the project plan will be updated and extended based on the changes detailed above. The
Infor and Licensee Project Managers have agreed to these changes and will reflect the changes in the
latest version of the overall project plan.
Target date(for implementation)
March 2015,overall Hansen CDR project
Impact on resource requirements
Infor project resource requirements will be increased by a total of 280 hours
Additional risk
Extend overall Hansen, CDR Project timeline along with city resource constraints which are already limited.
Impact on project cost
Project Budget will increase a total of.
Total Service Work Change Order 001 Revised Contract
Order Contract Increase Total
1,194,444.000 $76,263.00 $1,270,707.00
The targeted milestone payments and revised dates have been changed as reflected in Exhibit A
3
in for Change Order(Americas PMO-v5b,Nov.2012)
Estimated time and costs listed in this Change Order represent a fixed fee offer and are in
addition to the estimates provided in the original Work Order. Actual project time and cost may
vary from the estimates provided. Where a substantial variation from this Change Order is
foreseen, both parties must agree in writing to the additional work and document the change in a
subsequent Change Order.
Other Projects Affected
Hansen CDR and CIS Billing
Who needs to be notified of the change
Susan Manna,Debby Studder,Michael Hernandez
Comments
2.0 CHANGE APPROVAL / PAYMENT
By signing below, Licensee authorizes Infor to proceed with the work set forth in this Change
Order and bill Licensee per the payment terms set forth in the original Work Order for any
additional Services fees. Please return a signed copy of this Change Order to Infor PSO.
THE PARTIES have executed this Change Order through the signatures of their respective
authorized representatives.
INFOR: LICENSEE:
SignatureSign. re:
41k. A01,f‘ls sy
.......„...Z.1.--e3 ",iii.-4/ .44'-'ii-,'Illimm... -
Printed Name Patricia lias Printe& : Ro n al a L . so IkE ' _
Title: Associate General Counsel Title CO-u)
t Iv\QA-\a.ayey
Address: 380 St. Peter Street Address. 12_01 t.��arct.
Address: St. Paul, MN 55102 Address: CC Y 9 US Ct,6s1 1-)C 1 t+L I
Signature Date: August 4, 2014 Signature Date: j�/ I I Li
---2ATTEST: ' ' 4-G- ;�, ' '
REBECCA HUERTA
(r' I ' CITY SECRETARY
L-.iI ..1..:--- 1 ,Alf I r KULA. 4
in For CUIICIL..-7.L`("..
.1.±. ,
Change Order(Americas P v5b,Nov
SECRETARY
Attachment A: Revised Milestone Payment Schedule
0001
CDR(Plan,Permit,Business License,Code Enforcement)
Establish Phase
M-1 Milestone-Project Initialization X2/.2914 5179.166.60 $17,5116.66 $161,249.94
M-2 Miledone-hs alt the Insepe Products in Project environment: $0.00 $0.00 $0.00
M-3 Mlestone-Project Team Learning 11/2812014 5107,499.96 910,75000 596.749 96
M-4 Milestone-Meal Bate Prototype: 7)14/2014 $119.444 40 511,944.44 5107,499.96
M-45 Milestone- Initial Beta Prototype. Health Department 8/31/2014 ' 519.065.75 $1,906.58 $17,159.18 $19,065.75
M-5 Milestone-Final Prototype: 9/12/2014 5179.166.60 $17,916.66 $161,249.94
M-5.5 Milestone- Final Prototype- Health Department 9/26/2014 515.252.60 51,525.26 $13.727.34 515,252.60
M-6 Milestone-Acceptance Tet 10/24/2014 5166.717.17 $16,671.72 5150,04545 $11,43945
Execute Phase $0.110 $0.00 $0.00
M-7 Milestone-System Test 1/9/2015 5190.606.05 $19.064.61 5171,545.45 511,439.45
13-8 Milestone-Full Sale Tet 1/23/2015 5'27,070.70 $12,707.07 $114.363.63 $7.626.30
M-9 Milestone-Production Readiness 2113/2015 563.535 35 56,353.54 557,181.82 $3,813.15
M-10 Milestone-Complete Peet-Go-Live Support 3/20/2015 5103.181.82 $10.318.18 592.863.64 57,626 30
M-11 Milestone-foss Project 4/24/2015 50.00 5127.070.70
•
Total Payment Milestone Amount for this Stage 8 $1.270,707.00
$127,070.70 51,270.707.00 576.26300
°Nina Contract 51,194.444.00
CO 001 Contract $76.263.00
(Revised Contract $1,270,707.001
5
in Fo r Change Order(Americas PMO-v5b,Nov. 2012)