CHANGE ORDER NO.: 13 CHANGE ORDER DATE: 12/17/2014
PROJECT: Bayfront Development Phase 3-Shoreline Blvd Realignment PROJECT NUMBER: 6511
CONTRACTOR: Bay,Ltd CONTRACT TIME: 400 CD
ENGINEER: HDR Engineering
Make the following additions,modifications or deletions to the work described in the Contract Documents:
Street Street Delay Time Item(Line Item 22...See Attachment 1)
1 Street Bay LTD Overhead Costs 165 Days @$3,323.00 DAY $548,295.00
2 Street DEDUCT:Resume negotiations between Albert Pardo and Frank Whiteaker overhead costs 165 Days @$1,060.35 DAY ($174,957.75)
Net Total of This Change Order $373,337.25
Why was this Change necessary:
:_ . ... . See attigka.e4,yig
How can similar changes be avoided in the future?
Unavoidable
The compensation agreed upon in this Change Order is full,complete and final payment for all costs the Contractor may incur as a result of or relating to this
change whether said costs are known,unknown,foreseen or unforseen at this time,including without limitation,any cost for delay,extended overhead,ripple or
impact cost,or any other effect on changed or unchanged work as a result of this Change Order.
Original Contract Amount $ 6,552,042.05
Previously Approved Change Order Amount $ 615,082.34
Proposed Change Order Amount $ 373,337.25
Revised Contract Amount $ 7,540,461.64 � \,
Percent of Total Change Orders(including this CO) 15.09% CC//
Previous Change Order Contract Time 0 CD
Additional Time on This Change Order 165 CD
Revised Contract Time 165 CD
Recommended by Approved by
[CONSULTING FI' [CONTRACTOR
•
By , 29-f.' By 2_ S — I — 15
/ Date Date
TOFC RPUS CHRISTI j�
Recommended by !/J.�%�� Y Approved or N//
Philip L.B P.E. Date Recommended by:Valerie H.Gray,P.E. Date
Acting Construction Engineer Executive Director of Public Works
Approved or N/A
Recommended by: Gustavo Gonzalez,P.E. Date
Assistant City Manager
Recommended by: ' 6*oOs,
,� , CITY OF CORP CHRISTI
Eddie Houlihan D
dip
Budget and Finance c 7 f A.•rove'• '+
Recommended by• 7/�1�`� '/ •� `L� Approved by
-15
net Kellogtj Date0. ,/ ' 6 5
City Attorney Director of Capital Programs ►'i
DEPARTMENT
APPROVAL Operating Department(Street) $ 373,337.25
INAILLS.—0 1J1 NUKILtL
{ tliaL
JTTc T: T
Ty
'I�•............ ' 3126-7 34
RE iECCA HUERTA
ECE Y ARY
550910
170678013126EXP
SECRFTAry 50910
2015-059 RMAY 01 2015
Page 1 of 1
4/14/15
M2015-033 BY:--- ---- INDEXED
Bay Ltd.
•
Albert Pardo
From: Mark Guerra
Sent: Thursday,April 03,2014 833 Am
To: Albert Pardo
Subject: FW:Shoreline utility delay
Original Message
From:Kenneth Kaper
Sent:Friday,December 13,2013 5:43 PM
To:Whiteaker,Frank
Cc:Mark Guerra;Lentz,Jon;Espindola,Tony
Subject:Re:Shoreline utility delay
Frank
All items have unknown resolution dates-please demobilize all of your equipment and only supply superintendent to
supervise Clark.
Thanks
Ken
Sent from my iPhone
>On Dec 13,2013,at 3:50 PM,"Whiteaker,Frank"<WhiteakerFCbayltd.corn>vrrote
>Ken,
>Can we meet on Tuesday morning to discuss the utility delays on this project.we need some clarifications en several
issues with Time Warner,AT&T, &AEP.
>Thank you
>Frank
>Sent from my iPhone
BAY LTD PROPOSAL
FOR SUSPENCION OF WORK
CONTRACT NO. 6511
BAY FRONT DEVELOPMENT PHASE 3
PAGE IOF2
Shoreline
Project details
Start date &duration November 4, 2013— Present.
2. Contract days: 400, Baseline Schedule shows 228 days
2. Overhead Claim. November 8, 2013 to April 21, 2013 (165 X$3,323 = $548,295).
4. Delay #1: TWC Utility Conflict and Re-Design
1. November 8, 2013 to April 21, 2014. (See Next Slide for Details)
Delay #2: MIS Conduit conflict with Street Excavation and Sub-grade work.
May 5, 2014 to Present.
G. Delay #3: AEP Underground, Encased Utility at Station 50+82
May 6, 2014 to July 7, 2014.
7. Delay #4: AEP Delay at Kinney Street Intersection •
May 6, 2014 to June 6, 2014.
8. Delay #5: Turnouts at Broadway and Born must be adjusted to match Replacement Curb.
Jun 16, 2014 to Present.
9. Delay#6: Conflict with 8"WL at Station 52+00.
1. June 30, 2014 to July 11, 2014.
10. Delay #7: AEP Line at Vet Park conflict with Street Excavation
Jun 30, 2014 to July 14, 2014.
BAY LTD PROPOSAL
FOR SUSPENCION OF WORK
CONTRACT NO. 6511
BAY FRONT DEVELOPMENT PHASE 3
PAGE 2 OF 2
•
Shoreline
I) PROJECT DELAY 41
a) Unmarked Utility Lines
i) November 3, 2013: Unmarked Coaxial and Fiber Optic cables were encountered
during construction.
ii) November 21,2013: Time Warner Cable began relocating lines. Crews were pulled-
off after the extent of the re-route was realized. It was determined that the unmarked
cables were running parallel and between the baseline and proposed curb line.
(a) Majority of construction impacted.
iii) Unmarked AT&T Line encountered at Kinney Street intersection
(a) Underground utility work impacted.
b) Work Stoppage
i) Bay Ltd. Crews and Subcontractors were instructed to halt work and demobilize until
external conflicts have been resolved by the City.
c) !Notification Letter
i) -December 11,2013: A Notification Letter was sent to the City and BDR outlining
the utility delays as well as to inform of a forthcoming delay claim.
d) The City's Response
i) December 13, 2013: Ken Kaper directs Bay Ltd. to demobilize all personnel and
equipment due to unknown resolution dates. Bay is only to supply a superintendent
to supervise utility subcontractor.
c) Claim Letter
i) January 15,2014: A Claim Letter was sent to Dan Biles,F.L. outlining a cost impact
due to ongoing delays.
ii) January, 31,2014: An updated cost impact was provided to the City.
iii) April 2,2013: An updated cost impact was provided to the City which included the
cost impact incurred by Bay's subcontractor,Clark Construction.
f) Work Resumes:
i) April 21,2014: Re-Desigi plansheets have been provided. Bay,Ltd. resumes all
construction activities.
RESUME OF NEGOTIATIONS
CONTRACTOR: BAY LTD
PROJECT:BAYFRONT DEVELOPMENT PHASE 3-SHORELINE BLVD REALIGNMENT
PROJECT NO:6511
Change Order No. 13,Suspension Of Work.
By email dated December 3,2013, Mr Kenneth Kaper directed the Contractor to demobilize
from the site and suspend the work,but maintain superintendence by Bay at the site for any
subcontractors that could do work-arounds in areas not affected by the re-design issues. This
directive was determined to be in the best interest of the City because several design changes
became apparent where only limited work could be performed.
Bay Ltd,submitted their proposal,see attached hereto,identifying all of the cost factors and
events as a result of the suspension of work,and requesting compensation for 165 days
suspension costs at$3,323 per day.
Negotiations were conducted on August 19,2014 between Albert Pardo representing the City
and Frank Whiteaker representing Bay LTD.
During discussions of the allowable and allocable costs,the contractor agreed to reduce his
proposal to$2,261.65 daily rate. With this revision the Contractor's price of$373,337.25 and a
time extension of 165 calendar days was accepted as an equitable adjustment for the
suspension of work.
Approval is recommended.
Albert Pardo,P.E
Construction Engineer
City of Corpus Christ