Loading...
HomeMy WebLinkAboutC2015-483 - 11/15/2015 - NA r a CITY OF CORPUS CHRISTI AMENDMENT NO. 7 CONTRACT FOR PROFESSIONAL SERVICES The City of Corpus Christi, Texas, a Texas home-rule municipal corporation ("City") and Carollo Engineers, Inc. ("Consultant"), agree to the following amendments to the Contract for Professional Services for New Broadway Wastewater Treatment Plant(Prosect No. 7293): Original Contract December 1, 2006 Administrative Approval $24,915.00 Amendment No. 1 February 12, 2008 Motion No. 2008-033 $7,306,047.00 Amendment No. 2 September 18, 2009 Administrative Approval $34,801.00 Amendment No. 3 November 10, 2009 Motion No. 2009-314 $885,669.00 Amendment No. 4 February 3, 2010 Administrative Approval $45,000.00 Amendment No. 5 August 9, 2011 Administrative Approval $48,750.00 Amendment No. 6 September 28, 2012 Administrative Approval $49,980.00 Exhibit "A", Scope of Services shall be amended as set forth in the attached Amendment No.7, Exhibit "A". Exhibit "A", Fees shall be amended based on the modified scope of services in the attached Amendment No. 7, Exhibit "A" for a fee not to exceed $49,980.00, for a total restated fee not to exceed $8,445,142.00. Monthly invoices will be submitted in accordance with the Payment Request as shown in Exhibit"B". All other terms and conditions of the December 1, 2006 Contract for Professional Services between the City and Consultant, and of any amendments to that contract,which are not specifically addressed herein shall remain in full force and effect. CITY OF CORPUS CHRISTI CA: •LLO ; NGI ERS A(C. $1gait 01�6C �"bobsRonald L. n Date . •1%'�Anderson, `.E. Date Ci . a•er Associate Vice President 8911 Capital of Texas Hwy North, Suite 2200 M/ '/. I°45- Austin, TX 78759 Gustay. Gonzalez, '.. Date (512) 882-0469 Office Assista t City an.ger of P • ip s rt. ilities Al , I) I Ii(t-071. - V- - ie H. Gra P.: . Date Executive Director if Public Works RECOMM NDED 741 c. per •ng Department Date AP i �� GVVED AS TO LEGAL FORM 2015-483 , ID--30-15 11/15/15 - Date Carollo Engineers Inc. INDEXED K trvbu «nu.v�r ���� �•��w�••• •• TER\7293 NEW BROADWAY WWTP\CAROLLO\AMENDMENT NO 7\CONTRACT DOC REV 10/1/15 APPROVE thltaw, Office of Management and Budget Dat ATTEST (1 . -e City Secretary Project Number 7293 Accounting Unit 4249-064 Account 550950 Activity 190130014249EXP Account Category 50950 Fund Name Water 2012B RVBD Waste waif r off, ))/ '--4t 51o3'�3 G.Ai - 3/ r/g K:\ENGINEERING DATAEXCHANGE\JENNIFER\WASTEWATER\7293 NEW BROADWAY WWTP\CAROLLO\AMENDMENT NO 7\CONTRACT.DOC REV 10/1/15 k led Ii7)o • • Attachment A AMENDMENT NO. 7 - SCOPE OF SERVICES CITY OF CORPUS CHRISTI NEW BROADWAY WASTEWATER TREATMENT PLANT PROJECT NO. 7293 SECONDARY CLARIFIER DESIGN MODIFICATIONS TO 30 MGD 1.0 BACKGROUND The City of Corpus Christi (City) has retained Carollo Engineers, Inc. (ENGINEER)to provide professional engineering services to complete the New Broadway Wastewater Treatment Plant (NBWWTP). This Amendment No. 7 provides for Design Engineering Services associated with a change in the existing Contract Documents as originally bid from construction of four Secondary Clarifiers providing a peak 2-hour flow capacity of 40 mgd, to three Secondary Clarifiers providing a peak 2-hour flow capacity of 30 mgd. 2.0 PURPOSE This Amendment No. 7 establishes the Scope of Work, the Time of Performance, and the Engineering Services Budget for Design Services to be provided by the ENGINEER for the City. The engineering services will consist of the following: • Task 100— Project Management and Meetings • Task 200—Quality Management • Task 300—Subconsultant Services • Task 500— Design Modification -Secondary Clarifiers and RAS Pump Station • Task 600— Permitting and Agency Coordination 3.0 PROJECT ELEMENTS The scope of services presented herein is based on a project that consists of the major elements summarized below: 1. Construction Document Preparation a. Modify the existing Phase 2 Secondary Clarifier design to reflect the delayed construction of Clarifier 4 as follows: 1) Update General Sheets (Drawings 01-G-06, 01-G-13, 01-G-14, and 01-G-19) 2) Update Site Development Sheets, and re-design site drainage at Clarifier 4 (Drawings 01-C-01, 01-C-03 and 01-C-04) 3) Update Yard Sheets, and modify yard piping (Drawings 01-Y-01, 01-Y-03, 01- Y-22, 01-Y-26, and 01-Y-27) 4) Increase area for hydroseeding (Drawings 01-L-01, 01-L-02, and 01-L-11) October 5, 2015 pw://Carollo/Documents/Client/TX/Corpus Christi/_Proposals/Amendment No.67 AMEND. NO.7 EXHIBIT"A" Page 1 of 9 5) Modify the walkway structure between Secondary Clarifiers 3 and 4 to accommodate support of the walkway in lieu of construction of Secondary Clarifier 4 (Drawings 24-S-01, 24-S-02, 24-S-03, and 24-S-05) 6) Re-route the non-potable water(NPW) line to serve Clarifier 3 directly from the NPW main line (Drawing 24-M-01, 24-M-02, and 24-M-03) 7) Update General Electrical Sheets, (Drawings 01-E-03, 01-E-04, 01-E-06, 01- E-24, 01-E-26, 01-E-32, and 01-E-37) 8) Modify electrical design as required (Drawings 24-E-04 and 24-E-06) 9) Modify Process and Instrumentation Diagrams (P&IDs) as required (Drawing 24-N-04) b. Modify the RASNVAS Pump Station Design to reflect delayed construction of Secondary Clarifier 4 1) Partial installation of the RAS suction line (Drawing 25-M-01, and 25-M-02) 2) Partial construction of the RAS/WAS Pumps and piping (Drawing 25-M-01, and 25-M-02) 3) Modify electrical design as required (Drawing 25-E-01, 25-E-02, 25-E-03, and 32-E-01) 4) Modify Process and Instrumentation Diagrams (P&IDs) as required (Drawing 25-N-04) c. Modify Clarifier 3 to allow draining by gravity 1) Add wall pipe for drain line (Drawing 24-S-01, 24-S-03, 24-M-01) 2) Route new plant drain line to influent 48-inch diameter sewer via an new 8- inch diameter drain line to a new manhole on the existing 48-inch diameter influent sewer line (Drawing 01-Y-03) 2. Permitting and Agency Coordination Services a. Prepare a Summary Letter of Transmittal to TCEQ summarizing the design changes 4.0 SCOPE OF SERVICES TASK 100 PROJECT MANAGEMENT AND MEETINGS Task 101 - Project Management, Planning and Reporting Plan, organize, staff, direct, manage, coordinate, and report work tasks of project team including subconsultants. Manage project budget, schedule, and invoicing. October 5, 2015 pw:l/Carollo/Documents/Client/TX/Corpus Christl/_Proposals/Amendment No.67 AMEND. NO.7 EXHIBIT"A" Page 2 of 9 Deliverables: a. Monthly progress reports, schedule updates, and invoices Task 102 - Design and Contract Document Coordination Meetings Prepare for, conduct, and perform follow-up actions for up to two design coordination meetings with Project Team. The purpose of the meetings will be to coordinate upcoming activities of the various disciplines engaged in the design. It is assumed that each meeting will last up to 2 hours. Deliverables: a. Agendas, meeting minutes, action and decision log updates b. Monthly design coordination status report as part of monthly project status reports TASK 200 QUALITY MANAGEMENT Task 201 - Internal Quality Management Perform quality management activities on Carollo tasks including on-going discipline coordination, technical review, document review, quality assurance/quality control activities, and checking. Task 202 - Subconsultant Quality Management Apply ongoing QM activities to Subconsultant work efforts including review of deliverables prior to distribution to City. TASK 300 SUBCONSULTANT SERVICES Task 301 -Civil Engineering It is anticipated that six existing Drawings must be modified to accommodate construction of Secondary Clarifier 3 without construction of Secondary Clarifier 4, and to provide for draining of Secondary Clarifier 3 and future Secondary Clarifier 4 by gravity(Drawings 01-G-13, 01-C-01, 01-C-03, 01-C-04, 01-Y-01, and 01-Y-03). 301.1 Subconsultant shall prepare Drawings for the following Project Elements: 1. Update General, Civil, and Yard Sheets for which the Subconsultant is responsible to reflect Secondary Clarifier 4 as future construction. 2. Re-grading of the site where Secondary Clarifier 4 would have been constructed 3. Modification to Yard Piping as required to delay construction of Secondary Clarifier 4. October 5, 2015 pw://Carollo/Documents/Client/TX/Corpus Christi/_Proposals/Amendment No.67 AMEND. NO.7 EXHIBIT"A" Page 3 of 9 • • 4. Addition of an 8-inch diameter drain line and a new manhole on the 48-inch diameter influent sewer line for the purpose of allowing draining of Secondary Clarifier 3 and future Secondary Clarifier 4 by gravity. 301.2 Subconsultant shall attend up to two Design Coordination Meetings (Task 102), and one Project Workshop (Task 103). 301.3 Subconsultant shall provide monthly project status reports. Deliverables: a. 90% Drawings for Task 301 (10 hardcopies, and PDF). b. 90% Cost Estimate for construction of the Project Elements associated with Task 301. Costs will be determined based on RS Means and by contacting suppliers. (Electronic PDF and Excel file). c. Final Drawings for the Project Elements associated with Task 301 (MicroStation, and PDF). Task 302 - Landscape Architecture It is anticipated that three existing Drawings must be modified to accommodate construction of Secondary Clarifier 3 without construction of Secondary Clarifier 4 (Drawing 01-L-01, 01-L-02, and 01-L-11). 302.1 Subconsultant shall prepare Drawings and Specifications for the following Project Elements: 1. Update Landscaping Sheets to reflect Secondary Clarifier 4 as future construction. 2. Increase of area to hydroseed as required to delay construction of Secondary Clarifier 4. 302.2 Subconsultant shall provide monthly project status reports. Deliverables: a. 90% Drawings for Task 302 (10 hardcopies, and PDF) b. 90% Cost Estimate for construction of the Project Elements associated with Task 302. Costs will be determined based on RS Means and by contacting suppliers. (Electronic PDF and Excel file). c. Final Drawings for the Project Elements associated with Task 302 (MicroStation, and PDF) October 5, 2015 pw://Carollo/Documents/Client/TX/Corpus Chrisfi/_Proposals/Amendment No.67 AMEND. NO.7 EXHIBIT"A" Page 4 of 9 • Task 303 - Electrical Design It is anticipated that 13 existing Drawings must be modified to accommodate construction of Secondary Clarifier 3 without construction of Secondary Clarifier 4 (Drawings 01-E-03, 01-E-04, 01-E-06, 01-E-24, 01-E-26, 01-E-32, 01-E-37, 24-E-04, 24-E-06, 25-E-01, 25-E-02, 25-E-03, and 32-E-01). 303.1 Subconsultant shall prepare Drawings and Specifications for the following Project Elements: 1. Update General Electrical Sheets to reflect Secondary Clarifier 4 as future construction. 2. Modification of electrical design as required to delay construction of Secondary Clarifier 4. 3. Modification of electrical design as required to delay construction of the RAS/WAS Pumps associated with Secondary Clarifier 4. 303.2 Subconsultant shall attend up to two Design Coordination Meetings (Task 102), and one Project Workshop (Task 103). 303.3 Subconsultant shall provide monthly project status reports. Deliverables: d. 90% Drawings for Task 303 (10 hardcopies, and PDF) e. 90% Cost Estimate for construction of the Project Elements associated with Task 303. Costs will be determined based on RS Means and by contacting suppliers. (Electronic PDF and Excel file). f. Final Drawings for the Project Elements associated with Task 303 (MicroStation, and PDF) TASK 400 PRELIMINARY DESIGN Phase not applicable to this Scope of Work TASK 500 DESIGN MODIFICATION Task 501 -Clarifier Design Modifications It is anticipated that 10 existing Drawings must be modified to accommodate construction of Secondary Clarifier 3 without construction of Secondary Clarifier 4, and to provide for draining of Secondary Clarifier 3 and future Secondary Clarifier 4 by gravity(General Sheets 01-G-06, 01- G-14, and 01-G-19, Structural Drawings 24-S-01, 24-S-02, 24-S-03, 24-S-05, Process/Mechanical Drawings 24-M-01, 24-M-02, and 24-M-03, and l&C Drawing 24-N-04) October 5, 2015 pw://Carollo/Documents/Client/TX/Corpus ChnsS/_Proposals/Amendment No.67 AMEND. NO. 7 EXHIBIT"A" Page 5of9 ♦ 501.1 Modify existing Drawings, and develop additional drawings as necessary to show construction of Secondary Clarifier 3 without construction of Secondary Clarifier 4. It will be assumed that Secondary Clarifier 4 will still be constructed in the future. It is assumed that four existing structural Drawings, three existing process mechanical Drawings, and two existing P&IDs will be modified, and that one Drawing may be added. 501.2 Prepare opinion of probable construction cost for a 90% level of design. Issue to City along with 90% Drawings. Cost opinion will be a Class 2 Estimate as defined by the American Association of Cost Engineers (AACE). Deliverables: a. 90% Drawings for Task 501 (10 hardcopies, and PDF). b. 90% Cost Estimate for construction of the Project Elements associated with Task 501. Costs will be determined based on RS Means and by contacting suppliers. (Electronic PDF and Excel file). c. Final Drawings for the Project Elements associated with Task 501 (MicroStation, and PDF). Task 502 - RAS/WAS Pump Station Modifications It is anticipated that three existing Drawings must be modified to accommodate construction of the RAS/WAS pumps and piping for Secondary Clarifier 3 without construction of the RAS/WAS pumps and piping for Secondary Clarifier 4 (Process/Mechanical Drawings 25-M-01, and 25-M- 02, and l&C Drawing 25-N-04) 502.1 Modify existing Drawings, and develop additional drawings as necessary to show construction of the RAS/WAS Pumps for Secondary Clarifier 3 without construction of the RAS/WAS Pumps for Secondary Clarifier 4. It will be assumed that Secondary Clarifier 4 will still be constructed in the future. It is assumed that two existing process/mechanical Drawings, and one P&ID will be modified. 502.2 Prepare opinion of probable construction cost for a 90% level of design. Issue to City along with 90% Drawings. Cost opinion will be a Class 2 Estimate as defined by the American Association of Cost Engineers (AACE). Deliverables: a. 90% Drawings for Task 502 (10 hardcopies, and PDF). b. 90% Cost Estimate for construction of the Project Elements associated with Task 502. Costs will be determined based on RS Means and by contacting suppliers. (Electronic PDF and Excel file). October 5, 2015 pw//Carollo/Documents/Client/TX/Corpus Chnstil_Proposals/Amendment No.67 AMEND. NO.7 EXHIBIT"A" Page 6 of 9 c. Final Drawings for the Project Elements associated with Task 502 (MicroStation, and PDF). Task 503 - Miscellaneous Yard Piping Modifications It is anticipated that three existing Yard Drawings must be modified to accommodate construction of Secondary Clarifier 3 without construction of Secondary Clarifier 4 (Drawings 01- Y-22, 01-Y-26, and 01-Y-27). 503.1 Modify existing yard piping Drawings, and develop additional drawings as necessary to show construction of Secondary Clarifier 3 without construction of Secondary Clarifier 4. It will be assumed that Secondary Clarifier 4 will still be constructed in the future. It is assumed that four existing yard piping Drawings will be modified. Deliverables: a. 90% Drawings for Task 503 (10 hardcopies, and PDF). b. 90% Cost Estimate for construction of the Project Elements associated with Task 503. Costs will be determined based on RS Means and by contacting suppliers. (Electronic PDF and Excel file). c. Final Drawings for the Project Elements associated with Task 503 (MicroStation, and PDF). TASK 600 PERMITTING, AND AGENCY COORDINATION Task 601 -TCEQ Summary Letter of Transmittal 601.1 Prepare Summary Letter of Transmittal for submission to TCEQ. Meet with TCEQ to review design at time of submittal. Deliverables: a. Summary Letter of Transmittal TASK 700 BID PHASE SERVICES Phase not applicable to this Scope of Work TASK 800 CONSTRUCTION PHASE SERVICES No Construction Phase Services are included in this Scope of Work TASK 900 SPECIAL SERVICES Not applicable to this Scope of Work October 5, 2015 pw://Carollo/Documents/Client/TX/Corpus Chnsti/_Proposals/Amendment No.67 AMEND. NO.7 EXHIBIT"A" Page 7 of 9 • ASSUMPTIONS AND CITY RESPONSIBILITIES In addition to specific assumptions presented within Tasks 100 through 900 above and the assumptions listed in Subconsultant proposals (attached herewith), the following major assumptions apply to the scope of services: 1. Schedule: a. It is assumed the Work will be completed within one month of Notice to Proceed 2. City Review Periods: a. It is assumed that one round of City reviews will be conducted for the 90% Submittal, and that City comments will be received within one week of submittal. 3. Decision Log: The Engineer will maintain a log of major decisions made throughout the project. The Decision Log will be reviewed with the City for concurrence. Changes to the agreed-to decisions or retroactive decisions may result in an increase to the schedule and/or fee. 4. File Management: ProjectWise®will serve as the file management system for all project documentation. All drawings and specifications will be saved to the ProjectWise®files created specifically for this project. 5. Site and Project Elements: The scope of services will be limited to those sites and project elements identified under the Project Elements listed above. 6. Deliverables: Up to ten (10) paper copies of all deliverables will be provided to the City. 90% drawing sets will be produced at half-size (11" x 17") scale. All deliverables will also be posted to ProjectWise®. 7. Changes in Laws or Regulations: In the event that changes in Laws or Regulations after the effective date of the authorization impose taxes, fees, or costs on Engineer's services, the costs shall be in addition to the Engineer's estimated total fee presented herein. 8. It is assumed that all equipment, piping, valves, and appurtenances required for construction of Clarifier 3 have been properly stored per the Contract Documents, and are in proper condition for installation, and operation, providing the service life expected of new equipment, piping, valves, and appurtenances. 9. It is assumed that all Shop Drawings and Submittals required for construction of Clarifier 3 have already been approved. 10. Project Management and Meetings (Task 100): a. Meetings will be limited to the number of meetings listed under the base services. Additional meetings will be covered under Task 900 through separate authorization. October 5, 2015 pw//CarolloiDocuments/Client/TX/Corpus Christi/_Proposals/Amendment No.67 AMEND. NO. 7 EXHIBIT"A" Page 8 of 9 • 11. Quality Management (Task 200): a. Internal Quality Management: Carollo will designate a quality management team to perform overall project review, and quality assurance/quality control of Carollo's tasks. Further, each subconsultant team will be responsible for quality management related to their tasks. 12. Design Modification (Task 500): a. 90% Deliverables: These deliverables will include the Drawings necessary to provide direction to the existing Contractor in construction of Secondary Clarifier 3 without construction of Secondary Clarifier 4. b. Bid-ready Contract Documents for bidding purposes are NOT provided by this Scope of Work. c. Cost estimates: The Engineer has no control over variances in the cost of labor, materials, equipment, services provided by others, contractor's methods of determining prices, competitive bidding or market conditions, practices or bidding strategies. The Engineer cannot and does not warrant or guarantee that proposals, bids, or actual construction costs will not vary from the costs estimated under Task 500. d. The attached drawing list(Exhibit V) summarizes the anticipated level of drawing effort. Drawings will be produced in MicroStation, and converted to AutoCAD for final Drawings. e. The existing Specifications and details are still in effect, as are all existing Drawings not modified under this Scope of Work. 13. Permitting, and Agency Coordination (Task 600): a. It is assumed that permit conditions will not result in additional drawing production beyond the deliverables identified herein nor require changes to design decisions. b. Permit submission fees payable to TCEQ are not included. COMPENSATION Compensation for the above Scope of Services shall be on a lump sum basis with payment made monthly on the basis of progress achieved. The Engineer shall prepare a schedule of values for review by the City. Upon acceptance, the schedule of values will be used to establish monthly progress payments versus percent complete. The projected cost for this amendment has been calculated and is defined in Attachment B. The total compensation for the above Scope of Services, including allowances, shall be forty-nine thousand nine-hundred eighty dollars ($49,980) and shall not be exceeded without prior written authorization from the City. October 5, 2015 pwa/CarollolDocuments/Client/TX/Corpus ChnsG/_Proposals/Amendment No.67 AMEND. NO.7 EXHIBIT"A" Page 9 of 9 EXHIBIT B SAMPLE PAYMENT REQUEST FORM Sample form for. Payment Request COMPLETE PROJECT NAME Revised 07/27/00 Project No.XXXX Invoice No.12345 Invoice Date: Total Amount Previous Total Percent Basic Services: Contract Amd No.1 Amd No.2 Contract Invoiced Invoice Invoice Complete Preliminary Phase $1,000 $0 $0 $1,000 $0 $1,000 $1,000 100% Design Phase 2,000 1,000 0 3,000 1,000 500 1,500 50% Bid Phase 500 0 250 750 0 0 0 0% Construction Phase 2,500 0 1,000 3,500 0 0 0 0% Subtotal Basic Services $6,000 $1,000 $1,250 $8,250 $750 $1,500 $2,500 30% Additional Services: Permitting $2,000 $0 $0 $2,000 $500 $0 $500 25% Warranty Phase 0 1,120 0 1,120 0 0 0 0% Inspection 0 0 1,627 1,627 0 0 0 0% Platting Survey TBD TBD TBD TBD TBD TBD TBD 0% O 8 M Manuals TBD TBD TBD TBD TBD TBD TBD 0% SCADA TBD TBD TBD TBD TBD TBD TBD 0% Subtotal Additional Services $2,000 $1,120 $1,627 $4,747 $500 $0 $500 11% Summary of Fees Basic Services Fees $6,000 $1,000 $1,250 $8,250 $750 $1,500 $2,500 30% Additional Services Fees 2,000 1,120 1,627 4,747 500 0 500 11% Total of Fees $8,000 $2,120 $2,877 $12,997 $1,250 $1,500 $3,000 23% Contract for Professional Services Exhibit B