AMENDMENT NO. 2
CONTRACT FOR PROFESSIONAL SERVICES
The City of Corpus Christi, Texas, a Texas home-rule municipal corporation ("City") and LJA Engineering, Inc.
("Consultant"), agree to the following amendments to the Contract for Professional Services for McArdle Road
Improvements Ennis Joslin Road to Whitaker Drive BOND 2012 (Project No. E12097 & E12098):
I Original Contract January 29, 2013 Motion No. M2013-019 $957,720.00
Amendment No. 1 October 8, 2013 Motion No. M2013-151 $155,520.00
In the Original Contract, Exhibit "A", Section I. Scope of Services shall be amended as set forth in the attached
Amendment No. 2, Exhibit "A".
In the Original Contract, Section 3.1 shall be amended based on the modified scope of services in the attached
Amendment No. 2, Exhibit "A" for a fee not to exceed $14,250.00, for a total restated fee not to exceed
$1,127,490.00.
All other terms and conditions of the January 29, 2013 Contract for Professional Services between the City and
Consultant, and of any amendments to that contract, which are not specifically addressed herein shall remain in full
force and effect.
CIT %(CO5S iàTi
(91C;(4, LJAZINE INE , INC.
- - ' Date -- e 72rZZ4e .
Vale . Gray, I ((p �ogE2i . F��c 70":
Exec e Director of "ublic Wor sSTz.
820 Buffalo Street
Corpus Christi, TX 78401
361-887-8851 Office
RECOMMENDED
Operating Department ate
APPROVED AS TO LEGAL FORM
(Lu, _ yam" Z(lul Ise
Assistant City Attorney Date
2016-056
2/19/16
LJA Engineering Inc.
97 E12098 MCARDLE ROAD BOND 2012\AMENDMENT 2 LJA\2015-1001 AMENDMENT TO CONTRACT PROFESSIONAL
SERVICES DOC REV.10/1/15 INDEXED
APP OVED
g bindit
ick 9
of Management
.210110 Date6
and Budget
ATTEST
17II
laces x-c-.. i,�.r�.L,C C^ a /( G(/ic
City Secretary Date
Fund Name Accounting Unit Account No. Activity No. Account Category Amount
Street CIP Bond 2012 3549-051 550950 E12097013549EXP 50950 $7,125.00
Street CIP Bond 2012 3549-051 550950 E12098013549EXP 50950 $7,125.00
Total $14,250.00
K:\ENGINEERING DATAEXCHANGE\ANGIEM\STREET\E12097 E12098 MCARDLE ROAD BOND 2012\AMENDMENT 2 LJA\2015-1001 AMENDMENT TOO CONTRACT PROFESSIONAL
SERVICES.DOC
•
•
•
LJA Engineering, Inc. 114
820 Bullalo SI. Phone 361.881.8851
Corpus Christi.TX 78401 Fax 361.887.8855
www llaengineering corn
TBPE Ns F•1386 TBPLS Ns 10016600
January 18, 2016
City of Corpus Christi
Engineering Services
P. O. Box 9277
Corpus Christi, Texas 78469-9277
Attn: Mr. Chris Hale, P.E.
Project Manager
Re: Engineering Services Agreement Between
City of Corpus Christi and LJA Engineering, Inc.
McArdle Road Improvements—Ennis Joslin Road to Whitaker Drive
City Project No(s) E12097&E12098
Revised Contract Amendment No.2—Requested Additional Services
LJA Project No. C007-13002
Dear Mr. Hale:
I. ADDITIONAL SERVICES—SCOPE OF WORK
As requested, we have removed from our August, September and October invoices time spent
on additional services requested by the City Construction Inspection Department, which were
deemed non-Construction Administration services, and we have prepared this contract
amendment to cover those efforts. Our efforts on the additional services are described as follows:
1. Additional Topo Surveys: LJA was asked to perform additional topographic surveys to
verify existing drainage from approximate project Station 76+00 to the east.
2. Plan Revisions to Modify Storm Sewer Improvements: LJA was asked to modify the
drainage sheets within the plans to address stormwater drainage issues that arose during
construction. The following plan sheets were revised and sent back out to the field:
Sheets 52-54, 62, 80, 84, 106-107, and 118.
3. Plan Revisions to Modify Wastewater Improvements: LJA was asked to modify the
wastewater sheets within the plans to address wastewater issues that arose during
construction. The following plan sheets were revised and sent back out to the field:
Sheets 52,62, 84, 106-108, 110, and 113.
The above-described scope of work has been completed by LJA and delivered to the City. With
this contract amendment, LJA is requesting reimbursement for its expended efforts.
II. BASIS OF COMPENSATION
Engineering efforts expended by LJA to perform the scope of services listed in the items above
are as follows:
AMD. NO. 1
EXHIBIT"A"
Page 1 of 3
Mr.Chris Hale, P.E. McArdle Road Improvements January 18,2016
Revised Contract Amend. No.2 (City Proj.No(s): E12097&E12098)
1. Survey Work: $ 2,137.50
2. Storm Sewer Plan Revisions: $ 6,056.25
3. Wastewater Plan Revisions: $ 6,056.25
Total Fee: $14,250.00
III. SCHEDULE OF PAYMENT
Invoices shall be prepared, submitted and paid on a monthly basis in accordance with the original
contract. Invoices will be based upon engineering efforts spent at the time of invoicing.
Contract Amendment No. 2 documents are attached. We appreciate the opportunity to provide
these engineering services to you. If you have any questions regarding this Contract Amendment,
or need any additional information, please do not hesitate to contact me at(361) 887-8851.
Best Regards,
•
•
_ f
D. Scot1Ja es P.E. /i Date
Office Manager
Patrick D.Veteto, P.E. Date
Vice President
DSJ/PDV/dcr
Attachment
AMD. NO. 1
EXHIBIT"A"
Page 2 of 3
. •
McARDLE ROAD IMPROVEMENTS
ENNIS JOSLIN ROAD TO WHITAKER DRIVE
(Project No.E120971E12098)
SUMMARY OF FEES
ORIGINAL
CONTRACT AMD.NO.1 AMD.NO.2 TOTAL
Basic Services Fees ,_,_
1. Preliminary Phase $110,700.00 - $0.00 $0.00 $110,700.00
2. Design Phase $422,655.00 $122,780.00 $0.00 $545,435.00
3. Bid Phase $30,225.0_0 $1,4_40.00 $0.00 $31,665.00
4. Construction Phase $80,850.00 $81,300.00 $0.00 $112,150.00
Subtotal Basic Services Fee $644,430.00 $155,520.00 $0.00 $799,950.00
Additional Services(Allowance)
1. Perrnitting1TxDOT)(Authorized) $10,290.00 $0.00 $0:00 $10,290.00
2. Permltting(TDLR)(Authorized) $3,230.00 $0.00 $0.00 $3,230.00
3. ToQog_raphic Survey and ROW Verification(Authorized) $126,380.00 $0.00 $0.00 $126.380.00
4. SUE Exploration(Hydro Excavation) Authorized) $62,500.00 $0.00 $0.00 $62,500.00
Public Meetings (2 Meetings) & Oversight Committee
5. Presentation(Authorized) $18,750.00 $0.00 $0.00 $18,750.00
6. Construction Observation Services(To Be Determined) TBD
7. Drainage Analysis of Existing Storm Infrastructure
(Authorized) $88,840.00 $0.00 $0.00 $88,840.00
8. Warranty Phase(Authorized) $3,300.00 $0.00 $0.00 $3,300.00
9. Requested Additional Services(Authorized) $0.00 $0.00 $14,250.00 $14,250.00
Subtotal Additional Services Fee $313,290.00 $0.00 $14,250.00 $327,540.00
Total Fees $957,720.00 $155,520.00 $14,2�$1,127,490.00