HomeMy WebLinkAboutC2016-093 - 2/26/2016 - NA CITY OF CORPUS CHRISTI
AMENDMENT NO. 4
CONTRACT FOR PROFESSIONAL SERVICES
The City of Corpus Christi, Texas, a Texas home-rule municipal corporation ("City") and Urban Engineering
("Consultant"), agree to the following amendments to the Contract for Professional Services for Staples Street
Pumping Plant New 10 MGD Pumps (Project No. E12004):
Original Contract March 27, 2012 Motion No. M2012-065 $87,400.00
Amendment No. 1 March 19, 2013 Motion No. M2013-046 $129,070.00
Amendment No. 2 October 8, 2013 Motion No. M2013-150 $135,640.00
Amendment No. 3 August 11, 2015 Administrative Approval $8,700.00
In the Original Contract, Exhibit"A", Section 1. Scope of Services shall be amended as set forth in the attached
Amendment No.4, Exhibit"A".
In the Original Contract, Section 3 shall be amended based on the modified scope of services in the attached
Amendment No. 4, Exhibit "A" for a fee not to exceed $49,950.00, for a total restated fee not to exceed
$410,760.00.
All other terms and conditions of the March 27, 2012 Contract for Professional Services between the City and
Consultant, and of any amendments to that contract,which are not specifically addressed herein shall remain in full
force and effect.
CITY OF CORPUS CHRISTI URBAN NGINEERING
°4
Ronald L. Ols i Date James L. Urban, P.E. Date
City Manager Principal
2725 Swantner
41C)(2,,-
1 •- Z /4� Corpus Christi, Texas 78404
(361) 854-3101 Office
Mark Van Vleck, P. E., Date (361) 854-6001 Fax
Assistant City Manager
of Public Works and Utilities
ovi
-40 "
Val- H. Gray, .E. (/So Date
11
Exe• ive Director P blic ork
f
RE OMMED;NDED //
(/ 4 r,/4
Op ting Dep- men Date
APP OVED AS TO LEGAL,FORM
�,/Olte
2011 6-093
2/26/16 Date
INDEXED
Urban Engineering 54 STAPLES STREET PUMPING PLANT NEW 10 MGD\URBAN ENGINEERING\AMENDMENT NO.4/CONTRACT DOC REV.10/1/15
•
APP OVEQ
Mnitb*: 41i
Office of Management and Budget Date
9 9
ATTEST
I le_1--e-c-c,c. , 3/z (/i3O
City Secretary Date
Project Number E12004
Accounting Unit 4091-041
Account 550950
Activity E12004014091 EXP
Account Category 50950
Fund Name Water 2012B RVBD
K:\ENGINEERING DATAEXCHANGEUENNIFER\WATER\E12004 STAPLES STREET PUMPING PLANT NEW 10 MGD\URBAN ENGINEERING\AMENDMENT NO.4\CONTRACT.DOC REV.10/1/15
laURBAN
ENGINEERING
Job No.: 33760.61.03
December 30, 2015
Jeff Edmonds, P. E.
Director of Capital Programs
City of Corpus Christi
P.O. Box 9277
Corpus Christi, Texas 78469
Subject: Staples Street Pumping Plant New 10 MGD Pumps - Project No. E12004
Proposed Amendment No.4
Dear Jeff:
In response to a request by City staff we have reviewed the scope of services outlined in the
original contract and the two (2) executed amendments. We have also discussed the project
with our sub-consultant Bath Engineering and offer the following with respect to the current
scope of services. In 2013 we prepared and submitted to the City for approval, a 50% complete
package describing the proposed improvements at the Staples Street Pumping Station. Since
this submission, the scope of the project has changed from what was originally planned and it is
our opinion that we will need to undertake a significant amount of rework in order to get the
project back to 50% complete. We propose to complete the design phase work as noted
below, for an additional fee of$49,950.
Design Phase:
We will incorporate the approved pump configuration (three (3) 7.5 MGD) into the design,
update the work that was previously completed (submitted to the City in 2013) and prepare a
new 60% design submission for the City to review.
We propose to undertake the following design phase tasks;
• Meetings with the City to kick off the design phase and to review the new 60%
submission package.
• Review and update the design calculations to incorporate the recommendations from
the preliminary phase.
(361)854-3101 2725 SWANTNER DRIVE CORPUS CHRISTI,TEXAS 78404 FAX(361)854-6001
www urbaneng corn
TBPE Firm#145
TBPLS Firm#10032400
AMEND. NO. 4
EXHIBIT "A"
Page 1 of 2
• Review and update the 50% submission package, to incorporate the recommendations
from the preliminary phase. The following previously submitted documents will be
updated:
o Preliminary set of Plans (26 Sheets)
o Project Manual
o Project Checklist and Drawing Checklist
o Specification List
o Major Equipment List
o Project Schedule
o Opinion of Probable Construction Cost
o Control System Integrator Assessment Methodology
Project Schedule:
Once we receive the notice to proceed we propose to complete the design per the following
schedule.
Day Date Activity
Wednesday_ December 30, 2015 Submit Fee Proposal
Wednesday January 27, 2016 Negotiate Fee
Wednesday January 29, 2016 Notice To Proceed
Wednesday March 9, 2016 60% Submittal
Wednesday March 23,2016 City Review
Wednesday May 4, 2016 100%Submittal
Wednesday May 18, 2016 City Review
Wednesday June 1, 2016 Final Submittal
Monday June 13,2016 Advertise for Bids
Tuesday June 21, 2016 Pre-Bid Conference
Wednesday July 6, 2016 Receive Bids
Wednesday August 10,2016 Contract Award
Wednesday September 7, 2016 Begin Construction
Wednesday March 8, 2017 Complete Construction(Est.)
Please review the above scope, schedule and fee. If our proposal is acceptable please prepare
an amendment to our contract in the amount of$49,950.
Sincerely,
URBAN ENGINEERING
J. Douglas McMullan, P. E.
JDM/
Page 2 of 2
AMEND. NO. 4
EXHIBIT "A"
Page 2 of 2
. •
EXHIBIT B
SAMPLE PAYMENT REQUEST FORM
Sample form for:
COMPLETE PROJECT NAME PayRevi esed Request
Revid o7nnoo
Project No.XXXX
Invoice No.12345
Invoice Date:
Total Amount Previous Total Percent
Basic Services: Contract Amd No.1 Amd No.2 Contract Invoiced Invoice Invoice Complete
Preliminary Phase $1,000 $0 $0 $1,000 $0 $1,000 $1,000 100%
Design Phase 2,000 1,000 0 3,000 1,000 500 1,500 50%
Bid Phase 500 0 250 750 0 0 0 0%
Construction Phase 2,500 0 1,000 3,500 0 0 0 0%
Subtotal Basic Services $6,000 $1,000 $1,250 $8,250 $750 $1,500 $2,500 30%
Additional Services:
Permitting $2,000 $0 $0 $2,000 $500 $0 $500 25%
Warranty Phase 0 1,120 0 1,120 0 0 0 0%
Inspection 0 0 1,627 1,627 0 0 0 0%
Platting Survey TBD TBD TBD TBD TBD TBD TBD 0%
0&M Manuals TBD TBD TBD TBD TBD TBD TBD 0%
SCADA TBD TBD TBD TBD TBD TBD TBD 0%
Subtotal Additional Services $2,000 $1,120 $1,627 $4,747 $500 $0 $500 11%
Summary of Fees
Basic Services Fees $6,000 $1,000 $1,250 $8,250 $750 $1,500 $2,500 30%
Additional Services Fees 2,000 1,120 1,627 4,747 500 0 500 11%
Total of Fees $8,000 $2,120 $2,877 $12,897 $1,250 $1,500 $3,000 23%