HomeMy WebLinkAboutC2016-349 - 7/20/2016 - NA CITY OF CORPUS CHRISTI
AMENDMENT NO. 1
CONTRACT FOR PROFESSIONAL SERVICES
The City of Corpus Christi, Texas, a Texas home-rule municipal corporation ("City") and LJA Engineering, Inc.
("Consultant"), agree to the following amendments to the Contract for Professional Services for Barge Dock
Improvements (Prolect No. 34261:
Original Contract • August 28, 2012 Ordinance No. 029617 $309,870.00
In the Original Contract, Exhibit"A". Section I Scope of Services shall be amended as set forth in the attached
Amendment No. 1, Exhibit"A".
In the Original Contract, Section III shall be amended based on the modified scope of services in the attached
Amendment No. 1, Exhibit"A"for a fee not to exceed$0.00, for a total restated fee not to exceed $309,870.00.
All other terms and conditions of the August 28, 2012 Contract for Professional Services between the City and
Consultant,and of any amendments to that contract,which are not specifically addressed herein shall remain in full
force and effect.
CI ��u 11 "P iS ;H' �TI( LJA N IN ING,I C.
Veil; H. Gray P. . sate Patrick 4.4&dteto, P'E. Date
Ex- tive Director of P blic Wo ks Vice President
820 Buffalo Street
Corpus Christi, TX 78401
(361) 887-8851 Office
APPROVED AS TO LEGAL FORM
Digitally signed by Aimee Alcorn-Reed
Date:2016.07.06 16:58:27-05'00'
Assistant City Attorney Date
AT
+LtEW
City Secretary
2016-349
7/20/16
;11.111 S 425 BARGE DOCK IMPROVEMENTSMMENDMENT NO I UA ENGINEERING12015 1001 AMENDMENT TO CONTRACT
LJA Engineering Inc. "-
INDEXED
•
LJA Engineering, Inc. 114
820 Buffalo St. Phone 361.887 8851
Corpus Christi,TX 78401 Fax 361.887 8855
www ljaengineering corn
TBPE Ns F-1386 TBPLS No 10016600
June 23, 2016
City of Corpus Christi
Engineering Services
P. O. Box 9277
Corpus Christi, Texas 78469-9277
Attn: Mr. Shane Torno, P.E.
Project Manager
Re: Engineering Services Agreement Between
City of Corpus Christi and LJA Engineering, Inc.
Barge Dock Improvements
City Project No: 3426
Contract Amendment No. 1 —Professional Engineering Services
LJA Project No. C007-12040
Dear Mr. Torno:
I. SCOPE OF WORK
As requested, we have prepared Contract Amendment No. 1 (CA1) to remove Additional
Services - Project Definition and to create Basic Services. The purpose of CA1 is to reallocate
unused existing contract funds to provide additional funds for design, bid, and construction
phase services for City-requested barge dock improvements. The net result of CA1 is a zero-
dollar change to the Original Contract. The proposed changes to the Original Contract are as
follows:
1. Increase Basic Services: Preliminary Phase scope of services to perform a site visit,
prepare a scope of work, and opinion of probable construction cost for recommended
improvements and meet with City for final approval;
2. Increase Basic Services: Design Phase scope of services to create plans and contract
documents for bidding and construction;
3. Increase Basic Services: Bid Phase scope of services to provide Bid Phase Services;
4. Increase Basic Services: Construction Phase scope of services to provide Construction
Phase Services; and
5. Remove Additional Services: Project Definition.
The need for CA1 arose from the City's request to LJA to recommend repairs to the Barge
Dock, to design construction documents for those repairs, and to provide bid and construction
phase services.
AMD NO. 1
EXHIBIT'A'
Page 1 of 4
Mr.Shane Torno,P.E. Barge Dock Improvements June 23,2016
Contract Amend.No. 1 (City Project No: 3426)
II. CONTRACT CONDITIONS
Preliminary Phase Basic Services as described in the original Exhibit "A" are hereby removed
and replaced with the following services:
• Perform a site visit to quantify scope: Recommended improvements are a result of the
investigation of findings report dated 4/27/16. Improvements included patch, fill, and
seal of concrete within the paving, along the bulkhead, and on top of the seawall; fill void
below the seawall; repair void around stormwater outfall RCP pipe; seal concrete paving
adjacent to bulkhead to protect against saltwater attacking; and parking lot striping.
• Prepare a scope, exhibit and opinion of probable construction cost for recommended
improvements.
• Meet with City staff to discuss and finalize the scope of improvements.
Design Phase Basic Services as described in the original Exhibit "A" are hereby removed and
replaced with the following services:
• Prepare construction drawings and contract documents with specifications for repairs
agreed upon during preliminary phase.
• Prepare and submit 100% review package.
• Attend review meeting with the City.
• Revise construction documents per comments received at the 100% review meeting.
• Prepare and submit final sealed plans and contract documents for bidding.
Bid Phase Basic Services shall be provided in accordance with Original Contract, Exhibit "A"
excluding Item e).
Construction Phase Basic Services shall be provided in accordance with Original Contract for
an estimated 3-month duration. If construction extends beyond three (3) months, additional
fees will be required.
Improvements do not include repairs to timber piles, sheet piles, tiebacks, and storm sewer
pipes.
The scope of work of this Contract Amendment is limited to the above-described work only. Any
engineering efforts requested outside of the stated scope of work will require another
amendment to the contract and additional fees.
II. BASIS OF COMPENSATION &SCHEDULE OF PAYMENT
LJA proposes to perform the above-described scope of work for a zero-dollar change to the
Original Contract. The additionally-required fees are as follows:
- Preliminary Phase $ 6,545.88
- Design Phase $ 29,267.41
- Bid Phase $ 8,401.14
- Construction Phase $ 15,170.86
- Total Additional Fees $ 59,385.29
To create the funds to cover the additionally-required fees, a portion of the AMD NO. 1
approved fees for Additional Services: Project Definition ($59,385.29) will be EXHIBIT'A'
Page 2 of 4
•
Mr.Shane Torno,P.E. Barge Dock Improvements June 23,2016
Contract Amend.No. 1 (City Project No: 3426)
reallocated, thereby creating a zero-dollar change contract amendment as shown in the
attached Summary of Fees.
Invoices shall be prepared, submitted and paid on a monthly basis in accordance with the
Original Contract. Invoices will be based upon engineering efforts spent at the time of invoicing.
Contract Amendment No. 1 documents are attached. We appreciate the opportunity to provide
these engineering services to you. If you have any questions regarding this Contract
Amendment, or need any additional information, please do not hesitate to contact me at (361)
887-8851.
Best Re
r 0-Z3-/!P
Sones, ' ' . Date
Corpus Chris office Manager
b ��jb
Car • Marti ez, P. Date
Project Manager
DSJ/CAM/dcr
Attachment
AMD NO. 1
EXHIBIT'A'
Page 3 of 4
BARGE DOCK IMPROVEMENTS
(Project No. E3426)
SUMMARY OF FEES
ORIGINAL
Fees CONTRACT AMD.NO.1 TOTAL
Basic Services
1. Preliminary Phase $0.00 $6,545.88 $6,545.88
_2. Design Phase
9 $0.00 $29,267.41 $29,267.41
3. $
Bid Phase - ---
_.- $0.00 $8,401.14 $8,401.14
4. Construction Phase(3 month duration) $0.00 $15,170.86 $15,170.86
Subtotal Basic Services Fee $0.00 $59,385.29 $59,385.29
Additional Services(Allowance)
1. Permitting
a. USACE $0.00 $0.00 $0.00
b. GLO Easement $0.00 $0.00 $0.00
c. LSLS Survey $0.00 $0.00 $0.00
d. TDLR Registration $0.00 $0.00 $0.00
------------
e. Other $0.00 $0.00 $0.00
Subtotal FEE for Permitting $0.00 $0.00 $0.00
2. ROW Acquisition Survey $0.00 $0.00 $0.00
3. Topographic Survey $0.00 $0.00 $0.00
4. Subsurface Utility Engineering(SUE) $0.00 $0.00 $0.00
5. Public Meetings(3 Meetings) $0.00 $0.00 $0.00
6. Environmental Issues $0.00 $0.00 $0.00
7. Construction Observation Services(Duration TBD) $0.00 $0.00 $0.00
8. Warranty Phase $0.00 $0.00 $0.00
9. Project Investigation
a Project Management(Authorized) $13,620.00 $0.00 $13,620.00
b. Topographic and Bathymetric Surveys(Authorized) $12,180.00 $0.00 $12,180.00
c. Geotechnical and Concrete Testing(Authorized) $7,210.00 $0.00 $7,210.00
d. Seawall Void Survey(Authorized) $15,930.00 $0.00 $15,930.00
e. Timber Pile Assessment(Authorized) $33,370.00 $0.00 $33,370.00
f. Bulkhead and Tie Back Assessment(Authorized) $31,690.00 $0.00 $31,690.00
g. Storm Sewer Cleaning and Video(Authorized) $5,920.00 $0.00 $5,920.00
h. Storm Water Outfall U/W Inspection(Authorized) $8,080.00 $0.00 $8,080.00
i. Wave Loading Analysis $73,780.00 $0.00 $73,780.00
j. Structural Stability Analysis $28,260.00 $0.00 $28,260.00
k. Comprehensive Report of Findings(Authorized) $18,560.00 $0.00 $18,560.00
Subtotal for Project Investigation $248,600.00, $0.00 $248,600.00
10. Project Definition(Removed) $0.00 $0.00 $0.00
a. Initial Meeting with Staff $990.00 ($990.00) $0.00
b. Develop Initial Project Program $11,180.00 ($11,180.00) $0.00
c. Initial Meeting with Stakeholders $11,760.00 ($11,760.00) $0.00
d. Revise Program and Meet with Staff $6,860.00 ($6,860.00) $0.00
e. Revise and Prepare Concept Drawings and ROM $12,040.00 ($12,040.00) $0.00
f. Meet with Staff to Review Concept and ROM $1,440.00 ($1,440.00) $0.00
g. Present Concept and ROM to Stakeholders $4,240.00 ($4,240.00) $0.00
h. Revise Concept and ROM $3,740.00 ($3,740.00) $0.00
i. Council Presentation $3,100.00 ($3,100.00) $0.00
j. Final Concept,ROM and Report $5,920.00 ($4,035.29) $1,884.71
Subtotal for Project Definition $61,270.00 -$59,385.29 $1,884.71
Subtotal Additional Services(Allowance) $309,870.00 -$59,385.29 $250,484.71
Total Fee $309,870.00 $0.00 $309,870.00
AMD NO.1
EXHIBIT'A'
Page 4 of 4