HomeMy WebLinkAboutC2016-504 - 10/13/2016 - NA CITY OF CORPUS CHRISTI
AMENDMENT NO.4
CONTRACT FOR PROFESSIONAL SERVICES
The City of Corpus Christi, Texas, a Texas home-rule municipal corporation ("City") and Naismith Engineering,
Inc. ("Consultant"), agree to the following amendments to the Contract for Professional Services for Horne Road
Improvements Avers Street to Port Avenue BOND 2012(Project No. E12100):
Original Contract January 29, 2013 Motion No. M2013-021 $244,362.50
Amendment No. 1 August 16, 2013 Administrative Approved $17,000.00
Amendment No. 2 August 26, 2014 Ordinance No. 030264 $104,000.00
Amendment No. 3 August 23, 2016 Administrative Approved $21,030.00
In the Original Contract, Exhibit"A", Section I. Scope of Services shall be amended as set forth in the attached
Amendment No. 4, Exhibit"A".
In the Original Contract, Section III. shall be amended based on the modified scope of services in the attached
Amendment No. 4, Exhibit "A" for a fee not to exceed $47,074.00, for a total restated fee not to exceed
$433,466.50.
All other terms and conditions of the January 29, 2013 Contract for Professional Services between the City and
Consultant,and of any amendments to that contract,which are not specifically addressed herein shall remain in full
force and effect.
CITY OF CORPUS CHRISTI N• ITH N ERI I, INC.
1\r/C1))4
1( ) BCAl j°113 !ic I _ S • 27 2016
Margie C. Rose Date G Int Ja kson, Date
City Manager Vice President
4501 Gollihar Road
Corpus Christi, TX 78411
361-814-9900 Office
RECOMMENDED
Mark Van Vleck Date
Assistant City Manag
L----/q4
Valeri H. Gray, P.E. Date
Executive Director of Public Works
84
2016-504
ate
10/13/16
E12100 HORNE-AYERS TO PORT BOND 20121AMENDMENT 4 NAISMITHl2015 1001 AMENDMENT/ S O CONTRACT PROFESSIONAL
Naismith Engineering Inc. INDEXED
•
ROVED AS TO LEGA FORM g'2,-A,
/41i—li
ssistant City Attorney ij
Date
AP 9 ED G
`, Dat'e
office of Management r.�� �
and Budget �", Project No. E12100
Accounting Unit: 3549-051
Account: 550950
Activity: E12100013549EXP
ATTEST Account Category: 50950
Fund Name: Street CIP Bond 2012
�,i)e(���f_I4„,
t iU7144
Encumbrance No.
C. Secretary
Date
KIENGINEERING DATAEXCHANGEV+NGIEM\STREET1E12100 HORNE-AYERS TO PORT BOND 20121AMENDMENT 4 NAISMITH120151001REV. OWAMENDMENT5 TOO CONTRACT PROFESSIONAL
SERVICES.DOC
, . . , .
EllNaismithEngineering,Inc
ARCHITECTURE■ENGINEERING ■ ENVIRONMENTAL■SURVEYING
ESTABLISHED 1949
March 11, 2016
TRANSMITTED BY E-MAIL:JeffreyE@cctexas.com
Mr. Jeff H. Edmonds, P.E.
Director of Capital Programs
City of Corpus Christi
P.O. Box 9277
Corpus Christi, TX 78469-9277
Re: Request for Contract Amendment No. 4
Horne Road Improvements-Ayers Street to Port Avenue (City Project E12100)
Bond 2012 Program
Dear Mr. Edmonds:
Naismith Engineering, Inc. (NEI) respectfully submits this request for an amendment to our
contract for engineering and related services on the above referenced project. As you are
aware, there have been several things that have occurred on the project where the City has
requested that we provide services outside the scope of our original contract and previously
approved amendments. Some of these additional services resulted from the City's decision to
terminate the original construction contract with Salinas Construction Technologies, Ltd.
(Salinas) and letting a new construction contract with Clark Pipeline Services, J.V. (Clark), while
others resulted from changes requested by City personnel. We believe we have faithfully
assisted the City with these additional requested services and that these additional services
have allowed the City to keep this project progressing toward completion. This letter outlines
the nature and extent of the additional services we have provided and presents our request for
a contract amendment, broken out by several categories of additional work.
Construction Contract Termination Assistance
NEI performed additional services in conjunction with the City's termination of the original
construction contract with Salinas in association with termination of the Salinas Contract.
Including meetings with City and Contractor, correspondence with Contractor, developing
documentation (RFI's, EPP, Correspondence, emails, misc. data, etc.), coordinating with City
Legal Department and coordination with the Bonding Company. This time and costs were
incurred during the period that the Salinas contract was extended through final termination on
June 19, 2015. The additional cost associated with the construction contract termination was
$18,862.50.
4501 Gollihar Road. Corpus Christi,TX 78411 • 800-677-2831 361-814-9900 Fax 361-814-4401 • naismith-engineering.com
IEXHIBIT "A" I
Page 1 of 3
•
Mr. Jeff H. Edmonds, P.E.
Director of Capital Programs
City of Corpus Christi
March 11, 2016
Page 2
Remaining Assistance with Bonding Company and Closeout
It is anticipated that the City will require additional assistance during the closeout of the
contract and coordination with the Bonding Company. The estimated cost for the closeout is
$5,000.
Contractor Debarment Proceedings
As you are aware, the City opted to proceed with Debarment proceedings to exclude Salinas
Construction from completing any City of Corpus Christi projects based on past performance on
numerous contracts, including the Horne Road Project. NEI was asked to provide
documentation and correspondence related to issues on the Horne Road Project.
NEI performed additional services in conjunction with the City's debarment proceedings for
Salinas Construction. Including meetings with City Staff, developing documentation (RFI's, EPP,
Correspondence, emails, misc. data, etc.), coordinating with City Legal Department and
discussions with representative from the Meridian Group Mr. Karl Moser. These costs incurred
during the process was$2,500.
Transition to new Contractor
NEI assisted the City with assessing the work completed by the Salinas Contract and developing
a plan for hiring Clark Pipeline Services to complete the project. Services included as-built
surveys, pavement condition assessments, revising designs, developing cost estimates and
coordinating the effort to hire the new contractor. This costs were incurred during the process
was $20,711.50
Fee Summary
1. Contract Termination Assistance $18,862.50
2. Remaining Future Assistance $ 5,000.00
3. Debarment Proceedings $ 2,500.00
4. Transition to New Contractor $20,711.50
Total $47,074.00
NEI believes that we have aggressively worked with the City to keep this project moving and
have not used the fact that these services were outside the scope of our amended contract as
an excuse to delay the project. However, we also believe that we are due compensation for
these additional services. Based on the items outlined above, we are hereby requesting that
the City approve an amendment to our contract in the amount of $47,074.00 to our existing
contract amount of$386,392.50 for a total restated fee of$433,466.5
NaismithEngineering,Inc
ARCHITECTURE■ENGINEERING■ ENVIRONMENTAL•SURVEYING
EXHIBIT "A"
Page 2 of 3
Mr.Jeff H. Edmonds, P.E.
Director of Capital Programs
City of Corpus Christi
March 11, 2016
Page 3
We appreciate the opportunity to assist the City with this project. If you have any questions or
require additional information, please contact us.
Sincerely,
NAISMITH ENGINEERING, INC. (TBPE Firm No. F-355)
Willie Rivera,Jr., P.E.
Vice President/Project Manager
Z/9008/contract/Amendment4/E12100-Amendment4
NaismithEngineering,Inc
ARCHITECTURE■ENGINEERING■ ENVIRONMENTAL U SURVEYING
IEXHIBIT "A"