HomeMy WebLinkAboutC2018-181 - 4/9/2018 - NA CITY OF CORPUS CHRISTI
AMENDMENT NO. 2
MASTER SERVICES AGREEMENT
FOR PROFESSIONAL SERVICES
The City of Corpus Christi, Texas, a Texas home-rule municipal corporation ("City") and Maldonado-Burkett
Intelligent Transportation Systems, LLP ("Consultant"), agree to the following amendments to the Master
Services Agreement for Spur 3 Corridor(Ennis Joslin Road) Traffic Improvements from SH 358 (SPID) to
Ocean Drive(Project No. El 5165):
Original Master Services Agreement February 9, 2016 Ordinance No. 030757 $547,275.87
Amendment No. 1 September 27, 2016 Administrative Approval $27,586.08
In the Original Master Services Agreement, Article II. Compensation, Section 2.3 Consultant shall submit a
proposal to the City, which shall be incorporated into this agreement shall be amended as set forth in the
attached Amendment No. 2, Exhibit "A".
In the Original Contract, Master Services Agreement, Article II. Compensation, Section 2.1 shall be amended
based on the modified scope of services in the attached Amendment No. 2, Exhibit "A" for a fee not to exceed
$8.107.74, for a total restated fee not to exceed $582,969.69.
All other terms and conditions of the February 9, 2016 Master Services Agreement between the City and
Consultant,and of any amendments to that contract,which are not specifically addressed herein shall remain in full
force and effect.
CITY OF ORP, CHRI I MALDONADO-BURKETT INTELLIGENT
,- TRANSPORTATION SYSTEMS, LLP
l P L . 04/02/2018
Jeff . Edmonds, P. E., D. e on H Idonedo, Jr., P. E. Date
Director of Engineering Services Managing Partner
3833 S. Staples Street, Suite N214
• Corpus Christi, TX 78411
APPRnvFn ec Tn LEGAL FORM (361)236-4611 Office Number
9A-)// 2018.04.04 08:21:39 ramon@mbitsgroup.com
-05'00'
Assistant City Attorney Date
ATTEST
1 LL
City ecretary
Accounting Unit 3551-051
Account 550950
Activity E15113-01-3551-EXP
Account Category 50950
Fund Name Street 2015 GO Bond Fund
K:\ENGINEERING DATAEXCHANGE\VELMAPISTREETE15165 TRAFFIC SIGNALS AND LIGHTING IMPS ENNIS JOSLIN ROAD TRAFFIC SIGNAL IMPS FORMERLY E15113\AMASTER SERVICE
AGREEMENTAMENDMENT NO.2 TO MASTER SERVICES AGREEMENT\2015 1001 AMENDMENT.DOC REV.1011115
2018-181
4/09/18
Maldonado-Burkett Intelligent
INDEXED
•
•
MA L DON A DO.KU K KE IT
INTELLIGENT TRANSPORTATION SYSTEMS.LIP
January 25, 2018
Mr.Jeff Edmonds, P.E.
Director
Engineering Services
1201 Leopard Street
Corpus Christi,TX 78401
Re:Traffic Signal and Lighting Improvements Project#E151b5—Master Services Agreement—Amendment No.2
Dear Mr. Edmonds:
This is an ongoing Master Services Agreement for traffic signal improvements(City wide).
As requested, MBITS has prepared the HSIP 2017 Candidate projects and will revise the traffic signal plans to
remove the right-turn-lane and redesign the signal to be within the existing right-of-way.
Master Services Agreement amount: $547,275.87
Amendment No. 1: $27,586.08
Amendment No.2: $8,107.74
Total: $ 582,969.69
Task Order No.3
HSIP 2017 Development Reports to identify crash locations and problem areas, review candidate locations and
prepare estimates and finalize report for a total lump sum fee of$3,342.25.
Task Order No.4
Revise traffic signal plans on Ennis Joslin Road with Islander Way to remove the right-turn-lane and redesign the
signal to be within the existing right-of-way for a total lump sum fee of$4,765.49.
Task Order No. 3 and No.4 total $8,107.74
Contents for Master Services Agreement
Technical specifications and front-end documents will be required.
If you have any additional questions please let us know.
Best regards,
Ramon H. Maldonado Jr., P.E.
Managing Partner
CC: Jerry Shoemaker, P.E.
Chris Hale, P.E.
Raymond Chong, P.E, PTOE
3833 SOUTH SPAI'LES Sr SUITE N214 CORPUS CIIRISTI,TX 78411 • Office: 361-236-4611 • www.mbitsgroup.com
AMEND. NO. 2
EXHIBIT"A"
Page 1 of 5
Page 1
TRAFFIC SIGNAL AND LIGHTING IMPROVEMENTS
(CITY WIDE) BOND 2014 - Amendment No. 2
Discipline WBS Range Estimated by Rev
Date
Company
Maldonado -Burkett
Traffic Signal Design Ramon Maldonado 1
01/25/17
Task Description
DrawTask
Sheets y
Design
Fee
1
HSIP 2017 Development Reports
TASK ORDER NO.3
-------
$3,342.25
Additional Services
-------
-
Surve Topo and Utilities - TBD
-------
-
Bid Phase - To be included with Ennis Joslin Pro ect
----_--
-
Construction Administration Phase - Pro ect Wide - TBD
-------
-
Construction Observation Services - Project Wide - TBD
-------
-
Start-up Services - Pro ect Wide - TBD
-------
-
Subsurface Utility Investi.ation - Pro'ect Wide - TBD
-------
Total
53,342.25
2TASK
Ennis Joslin Corridor Revisions
ORDE.4
-------
54,765.49
Additional Services
-_-----
-
Surve To.. and Utilities - TBD
_------
-
Bid Phase - To be included with Ennis Joslin Pro ect
-------
-
Construction Administration Phase - Pro ect Wide - TBD
-------
-
Construction Observation Services - Project Wide - TBD
-------
-
Start -u. Sermces - Project Wide - TBD
-------
-
Subsurface Utilit Investi.ation - Project Wide - TBD
-------
Total
54,765.49
TOTAL LUMP SUM DESIGN FEE SUMMARY =
$8,107.74
1
ASSUMPTIONS
Plans to be submitted as one •acka.e.
2
Additional Services to be determined.
3
1
To .0 and Utilities CAD files to be su..lied b the Cit .
EXCLUSIONS to be Provide by Client
2
3
4
5
Page 1
Page 2
TRAFFIC SIGNAL AND LIGHTING IMPROVEMENTS (CITY
Company Discipline
WIDE) BOND 2014 - TASK ORDER NO.3
WBS Range Estimated by
Rev Date
WBS
Maldonado -Burkett
Task Description
TASK ORDER NO.3
Traffic
Drawing
Sheets
--------
Project
Manager
0.00
Signal
Design
Engineer
12.00
Design
Hours
EIT
0.00
Ramon Maldonado
by Classification
Senior
Engineering
Tech
6.00
Engineering
Tech
5.00
0
Junior
Engineering
Tech
0.00'
01/25/18
Admin
7.00
HSIP 2017 Develoement Re.orts
--------
-
Task 1: Identif crash locations and .roblem areas
--
2.00
3.00
2.00
-_
Task 2: Review candidate locations and .re.are estimates
--
6.00
3.00
3.00
6.00
Task 3: Finalize re.ort
--
4.00
1.00
QA QC
Coordination and Meetin.s
--------
Ii
Subtotal
-
0.00
12.00
0.00
6.00
5.00
0.00
7.00
Direct Labor Rates (2014)
-
$ 202.03
$ 130.89
$ 110.53
$ 145.43
$ 116.35
S 58.17
$ 45.32
Weighted Average Labor Escalation Rate (2014 thru 2016)
-
1.00
1.00
1.00
1.00
1.00
1.00
1.00
E.
Subtotal Direct Labor Costs
$ -
$ 1,570.68
$
S 872.58
$ 581.75
$ -
$ 317.24
Total Hours
Total Direct Labor
Costs
30
$3,342.25
Exclusions
Page 2
Page 3
TRAFFIC SIGNAL AND LIGHTING IMPROVEMENTS (CITY WIDE) BOND 2014 - TASK ORDER NO. 4
Company
Discipline WBS Range
Estimated by
Rev
Date
Maldonado -Burkett
Traffic Signal Design
Ramon Maldonado
1
01/25/17
�vBS
Task Description
P
Drawing
Sheets
Hours by Classification
Senior
Project Design
EIT Engineering
Manager Engineer
Tech
Engineering
Tech
Junior
Engineering
Tech
Admin
3.00 6.00 0.00 12.00
14.00
0.00
0.00
Ennis Joslin Corridor Design
Revise Summary of Materials Sheet
1.00
2.00
4.00
Revise Traffic Signal Plans to remain within existing ROW
1.00
4.00
6.00
Revise Standard Sheets to Latest Standards
1.00
2.00
Revise Plan Set to Remove Right Turn Lane
1.00
2.00
Revise OPCC
2.00
2.00
QA/QC
2.00
1.00
1.00
Coordination and Meetings
1.00
1.00
1.00
Subtotal
Direct Labor Rates (2014)
-
3.00
$ 202.03
6.00
$ 130.89
0.00
$ 110.53
12.00
$ 145.43
14.00
$ 116.35
0.00
$ 58.17
0.00
$ 45.32
Weighted Average Labor Escalation Rate (2014 thru 2016)
Subtotal Direct Labor Costs
Exclusions
1.00
$ 606.09
1.00
$ 785.34
1.00
S -
1.00
$ 1.745.16
1.00
$ 1,628.90
1.00
$ -
1.00
$ -
Total Hours
Total Direct Labor Costs
35
$4,765.49
Page 3
SUMMARY OF FEES
Spur 3 Corridor(Ennis Joslin Road)Traffic Improvements
from SH 358 (SPID)to Ocean Drive
Project No. E15165 (formerly Project No. E15113)
MASTER AMENDMENT AMENDMENT
SERVICES TOTAL
NO. i NO. 2
AGREEMENT
TASK ORDERS:
Task Order No. 1
Location 1 Ennis Joslin Road Simulation Study $15,128.84 $0.00 0.00 15,128.84
Location 2 Ennis Joslin Road with Islander Way Signal 98,746.16 0.00 0.00 98,746.16
Location 3 Ennis Joslin Road with Nile Drive Signal 23,401.64 0.00 0.00 23,401.64
Location 4 Ennis Joslin Road with McArdle Road 23,401.64 0.00 0.00 23,401.64
Location 5 Ennis Joslin Road with Alameda Street Signal 23,401.64 0.00 0.00 23,401.64
Location 6 Ennis Joslin Road Signal Interconnect 21,504.72 0.00 0.00 21,504.72
Location 7 Ennis Joslin Road Corridor Signal Coordination 38,426.61 0.00 0.00 38,426.61
Location 8 Ocean Drive with Doddridge Street Signal 23,401.64 0.00 0.00 23,401.64
Location 9 Ocean Drive with Island Blvd. Signal 23,401.64 0.00 0.00 23,401.64
Location 10 Ocean Drive with Sand Dollar Blvd. 23,401.64 0.00 0.00 23,401.64
Location Ennis Joslin Road with Ocean Drive 0.00 25,871.53 0.00 25,871.53
Location McArdle Road with Nile Drive 0.00 1,714.55 0.00 1,714.55
Task Order No. 2
Location 11 Flour Bluff Drive with Purdue Road Signal 22,444.94 0.00 0.00 22,444.94
Location 12 Home Road with Columbia Drive Signal 23,401.64 0.00 0.00 23,401.64
Location 13 Ayers Street with Roosevelt Drive Signal 23,401.64 0.00 0.00 23,401.64
Location 14 Staples Street with Brownlee Blvd. Signal 23,401.64 0.00 0.00 23,401.64
Location 15 Nueces Bay Blvd. w Buddy Lawrence Dr. Signal 23,401.64 0.00 0.00 23,401.64
Location 16 Leopard Street with Battlin Buc Blvd. Signal 23,401.64 0.00 0.00 23,401.64
Location 17 Leopard Street with Palm Drive Signal 23,401.64 0.00 0.00 23,401.64
Location 18 Leopard Street with Lantana Street Signal 23,401.64 0.00 0.00 23,401.64
Location 19 McKinzie Road with Haven Drive Signal 23,401.64 0.00 0.00 23,401.64
Location 20 Santa Fe with Texas Trail Signal 23,401.64 0.00 0.00 23,401.64
---- - Task Order No.3
HSIP 2017 Development Reports 0.00 0.00 3,342.25 3,342.25
Task Order No. 4
Ennis Joslin Road Corridor Revisions 0.00 0.00 4,765.49 4,765.49
Total $547,275.87 $27,586.08 $8,107.74 $582,969.69
02/09/16 09/27/16
030757 Admin Approval Admin Approval
AMEND. NO.2
EXHIBIT"A"
Page 5 of 5