HomeMy WebLinkAboutC2018-184 - 4/11/2018 - NA CITY OF CORPUS CHRISTI
AMENDMENT NO.7
CONTRACT FOR PROFESSIONAL SERVICES
The City of Corpus Christi, Texas, hereinafter called'CITY,' and Freese and Nichols. Inc. hereinafter
called "ENGINEER; agree to the following amendment to the Contract for Professional Services for
South Staples Street from Browner Parkway to Kostoryz Road(Bond 20121(Prolect No. El 20951
as authorized and administratively amended by:
Original Contract January 29, 2013 Motion No. M2013-017 $731,030.00
Amendment No. 1 July 11,2014 Administrative Approve $49,537.00
Amendment No. 2 January 23, 2015 Administrative Approve $39,154.00
Amendment No. 3 April 25, 2018 Administrative Approve $37,454.00
Amendment No.4 October 13, 2016 Administrative Approve $49,883.00
Amendment No. 5 November 28,2017 Administrative Approve $42,769.00
Amendment No. 6 March 23, 2018 Administrative Approve $49,951.00
EXHIBIT A,SECTION 1.SCOPE OF SERVICES,PART B.ADDITIONAL SERVICES shall be modified
as shown below.
6A. Public Meetinos: "ENGINEER" will participate in one public meeting prior to start of project
construction and more fully described in Exhibit"A".
8. Warranty Phase: "ENGINEER'will provide a maintenance guaranty inspection toward the end of
the one-year period after acceptance of the project and more fully described in Exhibit"A".
EXHIBIT A, SECTION 3. FEES, PART B. SUMMARY OF FEES shall be modified by the attached
Summary of Fees as shown in the attached Exhibit"B"for an additional fee not to exceed $14.887 for
jl a total restated fee not to exceed$1.014,665.
All other terms and conditions of the January 29, 2013 contract between the "CITY' and 'ENGINEER"
and of any amendments to that contract which are not specifically addressed herein shall remain in full
force and effect.
a rc.•F CORP'n ` • - STI FREES
'''''j'��ND,__NICHOLS,INC.
s .'1 cSU '.' • ��r +/j XO na/mpma
VII 'et H. Gra; - Da on G zm n, .E. Date
Executive� =• orks Vice N.
ShoenVerBlvd.,
800 Shoreline Blvd., Suite 1600N
�/ Corpus Christi,Texas 78401
���W?�/• 9 /i< (361)561-6500 Office
Aeff H. Edmonds, P.E. • e (361)561-6501 Fax
Director of Engineering Services rg@freese.com
APPROVED AS TO LEGAL FORM
(7/,Jw. i 2018.04.04
08:25:07-05'00'
Legal Department Date
AMEND.NO. 7
Page 1 of 2
vacwvrcerw n.T.cvrv,v .."+^""PE12B•58CUTH STAPLES FROM BRAWNEA TO KOSTORYZ 00110 ISSUE aWTCONeULTMT FREE
SE
FREE
w 2018184 2005 FREESE NICHOLS.DOa
4/11/18
Freese and Nichols Inc. INDEXED
•
ATTEST ,�
Ee-1G1-� wc_r 1 S
Rebecca Huerta, City ecretary
South Staples Street from Brawner Parkway to Kostoryz Rd (Project No. E12095)
Freese and Nichols
Amendment No. 7, $14,887 Not to Exceed $1,014,665
Fund Name Accounting Account Activity No. Account Amount
Unit No. Category
ST 2013 GO Bond 2012 3549-051 550950 E12095-01-3549-EXP 50950 $14,887.00
Total $14,887.00
AMEND. NO. 7
Page 2 of 2
K:IENGINEERING DATAEXCHANGEIVELMAPISTREET1E12095 SOUTH STAPLES FROM BRAWNER TO KOSTORYZ BOND ISSUE 20121CONSULTANT CONTRACT FREESE
NICHOLS\AMENDMENT NO.71AMENDMENT NO.7 E12095 FREESE NICHOLS.DOCX
#.
FR E E S E innovative approaches
°NICHOLS Practical results
a Outstanding service
800 N.Shoreline Blvd.,Suite 1600N • Corpus Christi,Texas 78401 • 361-561-6500 • fax 361-561-6501 www.freese.com
February 16, 2018
Mr.Jeff Edmonds, P.E.
Director of Engineering Services
City of Corpus Christi
P.0. Box 9277
Corpus Christi,Texas 78469-9277
Re: South Staples Street from Brawner Parkway to Kostoryz Road (Bond 2012)
City Project No. E12095-Amendment#7
Dear Mr. Edmonds,
At the request of your staff, Freese and Nichols, Inc. is pleased to submit our contract amendment#7 for
South Staples Street from Brawner Parkway to Kostoryz Road. This amendment includes exhibit
preparation and participation in one additional Public Meeting held prior to the start of construction,
and Warranty Phase services. These items were previously deleted by Amendment#4 to support the
requested redesign effort for the project. This amendment will include the following:
1. Add Public Meetings. Amendment#4 previously deleted the Public Meetings.
a. As part of the project redesign,Amendment#4 deleted the amount for public meetings.
This amendment proposes to add public meetings back into the contract.
b. FNI will attend one public meeting held prior to start of project construction. FNI will
prepare exhibits for the meeting and address citizen comments as directed by the City.
FNI will provide follow-up responses to citizen comments and concerns.
2. Add Warranty Phase Services. Amendment#4 previously deleted the Warranty Phase Services.
a. As part of the project redesign,Amendment#4 deleted the amount for warranty phase
services. This amendment proposes to add warranty phase services back into the
contract.
b. Warranty phase services will include providing a maintenance guaranty inspection
toward the end of the one-year period after acceptance of the Project. FNI will note
defects requiring contractor action to maintain, repair,fix, restore, patch,or replace
improvement under the maintenance guaranty terms of the contract. FNI will
document the condition and prepare a report for the City staff of the locations and
conditions requiring action,with its recommendation for the method or action to best
correct defective conditions and submit to City Staff. FNI will complete the inspection
and prepare the report no later than sixty(60)days prior to the end of the maintenance
guaranty period.
AMEND. NO. 7
EXHIBIT"A"
Page 1 of 3
•
•
•
•
Summary of Fees
1 Public Meetings $9,388.00
2 Warranty Phase Services $5,499.00
TOTAL $14,887.00
Freese and Nichols, Inc. respectfully requests a contract amendment in the amount of$14,887.00 to
address the aforementioned items.
Please feel free to contact me at 361.561.6500 should you have any questions regarding this matter.
Respectfully,
T2 (....39evie,7
Ron Guzman, P.E.
Principal/Vice President
Enclosures
AMEND. NO. 7
EXHIBIT"A"
Page 2 of 3
Frena and Nichols, Inc.
P. O. Box 98004 '..
Fort Worth. Texas 76198-0004
(817) 735-7300
Please contact Lisa Boggs at 361.561.6510 regarding billing questions
SOUTH STAPLES FROM BRAWNER TO KOSTORYZ ROAD (BOND ISSUE 2012)
Project No. El 2095
Purchase Order No. 1297 -0 -CPG
Basic Services:
Preliminary Phase
Design Phase
Bid Phase
Construction Phase
Subtotal Basic Services
Additional Services:
Permit Preparation (Authorized)
ROW Acquisition Survey (Authorized)
Topographic Survey (Authorized)
Environmental Issues (Not Authorized)
Public Meetings (Authorized)
Additional Public Outreach (Authorized - 5/29/14)
Subsurface Utility Investigation (Authorized)
Construction Observation Services (Not Authorized)
Warranty Phase (Authorized)
Signalization Improvements (Staples/Kostoryz)
(Authorized)
Traffic Control (Authorized)
Bicycle Standard Details & Signalization Specs
Subtotal Additional Services
Summary of Fees
Basic Services Fees
Additional Services Fees
Total of Fees
FNI Project No CORRIN
Contract Amd No. 1 Amd No. 2 Amd No. 3
Amd No. 4 Amd No. 5
Amd No. 6
Amd No. 7
Total
Contract
$58,066
$0
$0
$0
$0
$0
$0
$0
$58,066
252,367
22,296
39,154
0
140,783
23,114
0
0
477,714
12,363
0
0
0
-12,363
12,363
0
0
12,363
62,185
0
0
0
-62,185
0
49,951
0
49,951
$384,981
$22,296
$39,154
$0
$66,235
$35,477
$49,951
$0
$598,094
$25,007
$0
$0
$0
$0
$0
$0
$0
$25,007
TBD
7,561
0
0
0
0
0
0
$7,561
$69,663
$0
$0
$0
-$1,465
0
0
0
$68,198
TBD
TBD
TBD
TBD
TBD
0
0
0
0
$24,875
$0
$0
$0
-$9,388
0
0
9,388
$24,875
36,935
$0
$0
$0
$0
0
0
0
$36,935
69,378
19,680
0
0
0
0
0
0
89,058
TBD
TBD
TBD
TBD
TBD
0
0
0
0
5,499
0
0
0
-5,499
0
0
5,499
5,499
58,821
0
0
0
0
0
0
0
58,821
55,871
0
0
0
0
7,292
0
0
63,163
0
0
0
37,454
0
0
0
0
37,454
$346,049
$27,241
$0
$37,454
416,352
$7292
$0
$14,887
$416,571
$384,981
$22,296
$39,154
$0
$64235
$34477
$49,951
$0
$598,094
346,049
27,241
0
37,454
-16,352
7,292
0
14,887
416,571
$731,030
$49,537
$39,154
$37,454
$49,883
$42,769
$49,951
$14,887
$1,014,665
Bas c Services Fees
Preliminary Phase
Design Phase
Bid Phase
1
2
3
4
Construction Administration Phase
Subtotal Basic Services Fees
Additional Services Fees (Allowance)
1 Permitting
ROW Acquisition Survey
Topographic Survey
Environmental Issues
Public Meetings
Additional Public Outreach
Subsurface Utility Investigation
Construction Observation Services
2
3
4
5A
5B
6
7
Warranty Phase
Signalization Improvements
Traffic Control
Subtotal Additional Services Fees Authc
8
9
10
Total Authorized Fee
South Staples Street
from Brawner Parkway to Kostoryz Road (Bond 2012)
Project No. E12095
SUMMARY OF FEES
Original Contract
Street
Wastewater
Storm Water
Water
Gas
MIS
Total
$32,813.10
$3,611.71
$16,734.62
$4,267.85
$325.17
$313.56
$58,066.00
142,612.59
15,697.23
72,732.17
18,548.97
1,413.26
1,362.78
252,367.00
6,986.33
768.98
3,563.02
908.68
69.23
66.76
12,363.00
35,140.74
3,867.91
17,921.72
4,570.60
348.24
335.80
62,185.00
217,552.76
23,945.82
110,951.52
28,296.10
2,155.89
2,078.90
384,981.00
14,131.46
1,555.44
7 207.02
1,838.01
140.04
135.04
25,007.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
39,366.56
4,333.04
20,076.88
5,120.23
390.11
376.18
69,663.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
14, 056.86
1 547.23
7,168.98
1,828.31
139.30
134.33
24, 875.00
20,871.97
2,297.36
10,644.67
2,714.72
206.84
199.45
36 935.00
39,205.51
4,315.31
19,994.74
5,099.28
388.52
374.64
69,378.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
3,107.48
342.04
1,584.81
404.18
30.79
29.69
5,499.00
33,239.75
3,658.67
16,952.21
4,323.34
329.40
317.63
58,821.00
31,572.70
3,475.18
16,102.02
4,106.52
312.88
301.70
55,871.00
195,552.29
21,524.25
99,731.32
25,434.60
1,937.87
1,868.66
346,049.00
$413,105.05
$45,470.07
$210,682.85
$53,730.71
$4,093.77
$3,947.56
$731030.00
01/29/13
Motion No. M2013 017
South Staples Street
from Brawner Parkway to Kostoryz Road (Bond 2012)
Project No. E12095
SUMMARY OF FEES
Bast Services Fees
Preliminary Phase
Design Phase
Bid Phase
1
2
3
4
Construction Administration Phase
Subtotal Basic Services Fees
Addtional Services Fees (Allowance)
Permitting
ROW Acquisition Survey
Topographic Survey
Environmental Issues
Public Meetings
Additional Public Outreach
Subsurface Utility Investigation
Construction Observation Services
1
2
3
4
5A
5B
6
7
Warranty Phase
Signalization Improvements
Traffic Control
Subtotal Additional Services Fees Auth
8
9
10
Total Authorized Fee
Amendment No
1
Amd. No. 2
Amd. No. 3
Amd. No. 4
Street
Storm Water
Total
Street
Street
Street
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
0.00
0.00
0.00
39,154.00
37,454.00
140,783.00
0.00
0.00
0.00
0.00
0.00
(12,363.00)
0.00
0.00
0.00
0.00
0.00
(62,185.00)
0.00
0.00
0.00
39,154.00
37,454.00
66,235.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
(1,465.00)
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
(9,388.00)
0.00
0.00
0.00
0.00
0.00
0.00
7,432.00
42,105.00
49,537.00
0.00
0.00
0.00
0.00
(100
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
(5,499.00)
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
7,432.00
42,105.00
49,537.00
0.00
0.00
(16,352.00)
$7,432.00
$42,105.00
$49,537.00
$39,154.00
$37,454.00
$49,883.00
07/11/14
Admin. Approval
01/23/15
Ad. Approval
04/25/16
Ad. Approval
10/13/16
Ad. Approval
Basic Services Fees
1 Preliminary Phase
Design Phase
Bid Phase
2
3
4
Construction Administration Phase
Subtotal Basic Services Fees
Additional Services Fees (Allowance)
1 Permitting
ROW Acquisition Survey
Topographic Survey
Environmental Issues
Public Meetings
Additional Public Outreach
Subsurface Utility Investigation
2
3
4
5A
58
6
7
Construction Observation Services
Warranty Phase
Signalization Improvements
Traffic Control
Subtotal Additional Services Fees Autho
8
9
10
Total Authorized Fee
South Staples Street
from Brawner Parkway to Kostoryz Road (Bond 2012)
Project No. E12095
SUMMARY OF FEES
Amd. No. 5
Amd. No. 6
Amd. No. 7
Street
Wastewater
Storm Water
Water
Gas
Total
Street
Street
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
0.00
7,107.00
0.00
0.00
16,007.00
23,114.00
0.00
0.00
7,053.09
768.98
3,563.02
908.68
69.23
12,363.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
49,951.00
0.00
7,053.09
7,875.98
3,563.02
908.68
16,076.23
35,477.00
49,951.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
9,388.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
5,499.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
7,292.00
0.00
0.00
0.00
0.00
7,292.00
0.00
0.00
7,292.00
0.00
0.00
0.00
0.00
7,292.00
0.00
14,887.00
$14,345.09
$7,875.98
$3,563.02
$908.68
$16,076.23
$42,769.00
$49,951.00
$14,887.00
11/28/17
Administrative Approval
03/23/18
Ad. Approval
Ad. Approval
drn
A.71
WO
O _ Z
A di
-4
Vasaa
South Staples Street
from Brawner Parkway to Kostoryz Road (Bond 2012)
Project No. E12095
SUMMARY OF FEES
Total
Street
Wastewater
Storm Water
Water
Gas
MIS
Total
Basic Services Fees
1
Preliminary Phase
$32,813.10
$3,611.71
$16,734.62
$4,267.85
$325.17
$313.56
$58,066.00
2
Design Phase
360,003.59
22,804.23
72,732.17
18,548.97
17,420.26
1,362.78
492,872.00
3
Bid Phase
1,676.42
1,537.96
7,126.04
1,817.36
138.46
66.76
12,363.00
4
Construction Administration Phase
22,906.74
3,867.91
17,921.72
4,570.60
348.24
335.80
49,951.00
Subtotal Basic Services Fees
417,399.85
31,821.80
114,514.54
29,204.78
18,232.12
2,078.90
613,252.00
Additional Services Fees (Allowance)
1
Permitting
14,131.46
1,555.44
7,207.02
1,838.01
140.04
135.04
25,007.00
2
ROW Acquisition Survey
0.00
0.00
0.00
0.00
0.00
0.00
0.00
3
Topographic Survey
37,901.56
4,333.04
20,076.88
5,120.23
390.11
376.18
68,198.00
4
Environmental Issues
0.00
0.00
0.00
0.00
0.00
0.00
0.00
5A
Public Meetings
14,056.86
1,547.23
7,168.98
1,828.31
139.30
134.33
24,875.00
5B
Additional Public Outreach
20,871.97
2,297.36
10,644.67
2,714.72
206.84
199.45
36,935.00
6
Subsurface Utility Investigation
46,637.51
4,315.31
62,099.74
5,099.28
388.52
374.64
118,915.00
7
Construction Observation Services
0.00
0.00
0.00
0.00
0.00
0.00
0.00
8
Warranty Phase
3,107.48
342.04
1,584.81
404.18
30.79
29.69
5,499.00
9
Signalization Improvements
33,239.75
3,658.67
16,952.21
4,323.34
329.40
317.63
58,821.00
10
Traffic Control
38,864.70
3,475.18
16,102.02
4,106.52
312.88
301.70
63,163.00
Subtotal Additional Services Fees Autho
208,811.29
21,524.25
141,836.32
25,434.60
1,937.87
1,868.66
401,413.00
Total Authorized Fee
$626,211.14
$53,346.05
$256,350.87
$54,639.39
$20,170.00
$3,947.56
$1,014,665.00