HomeMy WebLinkAboutC2018-280 - 7/6/2018 - NA TASK ORDER NO. 31
This Task Order pertains to a Master Services Agreement for Professional Services by and between City of Corpus
Christi, Texas (City) and LNV, Inc. (Consultant) dated August 16, 2016 (Agreement). Consultant shall perform
services on the project described below as provided in this Task Order and in the Agreement. This Task Order
shall not be binding until it has been properly signed by both parties. Upon execution, this Task Order shall
supplement the Agreement as it pertains to the project described below.
PROJECT NAME/NUMBER: Water and Wastewater Treatment On-Call Support, E16264
1. PROJECT DESCRIPTION–This project provides the Utility Department with on-call services to assist with
any technical, operational, maintenance,diagnostic and design concerns for the City's O.N.Stevens Water
Treatment Plant and six wastewater treatment plants.
2. SCOPE OF SERVICES – Ship Channel Waterline Crossing at Cantwell Lane Evaluation more fully
described in Exhibit A.
3. COMPENSATION –The total amount not to exceed for Task Order No. 31 only is $23,480.
This Task Order is approved and Consultant may proceed. All other terms and conditions of the Agreement
remain in full force and effect.
CITY OF CORPU= ' HRI I LNV, INN
AK& •
Jeff H. dmonds, P. . late Dan S. —4444- . .# er, P.E. Date
Director of Engineering Services President
801 Navigation, Suite 300
Corpus Christi, TX 78408
(361) 883-1984 Office
loganb@Invinc.com
Fund Name Accounting Unit Account No. Activity No. Amount
Water Operating Fund 4010-31010-062 530000 E16264-01-4010-EXP $23,480.00
2018-280
7/06/18
LNV Inc.
INDEXED
City Project No. E16264
Professional Services Contract
City of Corpus Christi
Water/Wastewater Treatment On-Call Support
Task Authorization No. 31—Ship Channel Waterline Crossing at
Cantwell Ln Evaluation
June 19, 2018
LIMA,
EXHIBIT A
Penn 4 of 7
8.
LNV Ay
SCOPE OF WORK
Project No. E16264
Water and Wastewater Treatment On-Call Support
Task Authorization No.31— Ship Channel Waterline Crossing at Cantwell Ln Evaluation
PURPOSE
The U.S. Army Engineering District, Galveston (USAED), will soon commence construction of the
deepening and widening of the Corpus Christi Ship Channel,located in Corpus Christi Bay.The City's water
system currently consists of two locations where waterlines cross the Corpus Christi Ship Channel. One
location consists of twin 12-inch waterlines crossing parallel to and just east of the existing Harbor Bridge. A
second location is at Cantwell Lane and consists of twin 16-inch waterlines. It is believed that the Cantwell
crossing was installed at a depth that will conflict with the deepening of the channel and as a result, the
USA ED has requested the City of Corpus Christi to remove the 16-in waterlines.These lines are depicted in
Attachment B.
The purpose of previously executed Task Authorization 30 was to provide technical assistance to the City
staff in modeling different scenarios to determine the effects of removal of the 16-inch lines on the
distribution system, particularly in the North Beach area. This Task Authorization is an extension of the
scope provided under Task Authorization 30. Under this task authorization, the modeling results for the 16-
inch waterlines will be evaluated from both a capacity and water quality perspective to determine the
number, size, and location of the proposed replacement pipe(s) for the Cantwell Crossing waterlines. The
benefits of replacement and relocation of the waterline will be evaluated from both the City's and the Port
of Corpus Christi's perspective.
Based on the evaluation, a recommendation will be provided to the City regarding the pipe replacement. In
addition,the Engineer's opinion of probable construction costs(OPCC)and a schedule will be provided for
the demolition of the existing pipes and construction of the new replacement pipe(s).This task authorization
will also assist in coordination with the Port of Corpus Christi Authority (PCCA) and preparing relevant
documentation/presentations for meetings with City Staff/City Council on the project.
SCOPE OF WORK
ADDITIONAL SERVICES:
Task 0009—General Engineering
The Engineer will perform the following:
• Attend up to four(4)meetings with City Staff and Port of Corpus Christi Authority(PCCA).
• Review plans on existing Cantwell Crossing 16-inch waterline and other relevant plans,permits
and documentation.
• Coordinate with PCCA regarding master plans for proposed port expansion and easement
requirements to avoid conflict.
EXHIBIT A
ai..o7 ,,f7
14 irtr •l
C, �n
INV -,
• Analyze modeling results(to be obtained under the scope of Task Authorization 30)to evaluate
different replacement alternatives in terms of water quality and capacity concerns.
• Analyze benefits from different replacement and relocation alternatives to the City's water
distribution system and the PCCA.
• Select most feasible alternative and provide recommendation for proposed number of
replacement pipe(s),size(s)and location(s).
• Provide simple exhibits to show proposed demolition and replacement plan.
• Provide an OPCC for the demolition of existing pipe and construction of new replacement pipe.
• Provide an anticipated schedule for construction.
• Conduct final submittal workshop to discuss recommendations with the City.
• Assist in preparing presentation/documentation for meetings with City Staff/City Council.
DELIVERABLES
1. The Engineer will prepare a Technical Memorandum including:
• Evaluation of modeling results
• Recommendation for proposed pipe replacement including location and pipe sizes
• Simple Exhibits
• OPCCs
• Schedule for construction
2. The Engineer will assist in preparing PowerPoint presentations and meeting notes as requested
by the City.
SCHEDULE
The Engineer's services shall be performed in a timely manner consistent with sound professional
practices. The Engineer will complete the work according to the following schedule:
Activity Completion Date
Contract Execution-Notice to Proceed(NTP) TBD
Task 0009—General Engineering
• Evaluation of modeling results I week after Model Completion by City
• Technical Memorandum 4 weeks after evaluation results
• Final submittal workshop Within I week of Technical Memorandum submission
• Meetings As per City's Request
The time limits set forth in the schedule shall include allowances for reasonable and expected review time
by the City and approval by authorities having jurisdiction over this project, and shall not be allowed as
cause for delay or adjustments to the schedule. Delays caused by review times by the City exceeding those
anticipated by the Engineer's schedule are cause for adjustments in the schedule. Any adjustments made to
the agreed upon schedule shall be made in writing and accepted by both parties.
EXHIBIT A
PmnoZnf7
6,4
i
CNV
The Engineer shall begin work immediately upon receipt of the executed Task Authorization and/or Notice
to Proceed(written or emailed).
FEE
The services under this task authorization will be provided on a Time and Materials (T&M) basis. The
anticipated amount for this task authorization is$23,480.00,as shown in ATTACHMENT A.The Engineer
shall not incur cost in excess of this not-to-exceed amount without prior written authorization from the City.
EXHIBIT A
Porno A. of 7
p��us r,r
a( ..tt,
, ,;:.
TASK AUTHORIZATION MANAGER
The Task Authorization Manager will be the primary contact person during the performance of this work.
All correspondence or inquiries should be addressed to the Task Authorization Manager. This work task
will be coordinated by:
Dan Grimsbo, P.E.A.I.C.P.
Executive Director of Utilities Department
City of Corpus Christi
Office:361-826-1874
Fax: 361-826-1889
Email: DanGncctexas.com
APPROVAL
The undersigned has reviewed and approved this Task Authorization and recommends LNV,lnc.to perform
the work as presented:
Rec• mended by:
dr ,
Al
DAt`i 6/2 f rr7sL v (Printed Name)
/ -3-Je4 r� /g- (Date)
EXHIBIT A
Pio c of 7
ATTACHMENT A-MAN-HOUR AND FEE ANALYSIS
SIN Mc Project MrSOr yt Mader E+Minw holed EnOMer ST i CAM Teelriclee TOTALS1
i s 206.110 I$ 760.06 $ 170.00 S t7lM i 6860
,- r 1
M
TuOen
41141/011 OtMn NIL u$ Ht
leu1a0e. lea4SU$ 1. Hrs. i8o6u1M $ub
14n. � aMal 1 Hrs. ie4NM I Ted Hrs. Taal Fee
0001 General Engmeenn0 _.-
f
Moores rot,all shift(4)M 2Ne pat mee0n0 6 $ 1.040 5 0 $ 1.360 0 $ 900 S • 24 S 3.000.00
:wow plan and coon:Macon won PCU 2 s 410 iS • d
$ 1.020 2 $ 240 1 10 s 1.e70 00
Eralwuon of modeln0 tunnies 2 $ 410 $ 1C S 1700 2 S 240 S 14 ;$ 2 350 00
`
Benet ena/ps to Oaten matt 1441104 2 $ 410 $ - 4 $ 1 360 4 $ 460 $ - 14
na $ 2.250 00
Extetab '$ - $ - 1 $ 170 4 f 460 6 7 760 13 $ 1 410 00
,. 4 1
' I OPCC 1 $ 205 0 $ 1020• 12 $ 1,440 $ 19 S 2.065.00
t t
;MYcpafad tdrdule lot WnsOunon 1 $ 20S' f 340 4 f 4501 $ 7 S 1 ljeennicatmtngnMum 2 $ ata e S 1300 le s 1920 $ - 20 $ 3.09040
i ,
Ariel submits,rAttsnoo 2 1 110' 4 1 000 e $ 720 1,
12 S 1.$1000
Presentation for Ce't Stall and)ot Ory Council
b
S 410 4 w f 400 0 $ 960 .8 14 S 2050 00;
QM= t 3 1 003 $ 's - 5 • 3 1 80000
T1 4 •-----
II 14.119 s 6 0M; 11 3 6660 60 6 7.110 $ PM 1114 $ 22.06010
EXHIBIT A
Pnice Anf7
•
: l ,�
�Rpos �,;(!•-7. ), _s+.► ::4; !:__1
coPu+O a�Y)_�+.� 'Tack Authorization No.11 ,
r.. Ibil.i y{ Existing Water System Map \ • Si IP
f 1111P S
*turf C 11•1.1
D.0
"S
Md. / � yL i 4 .r..0•.I •- ' /91 /
aa.ccs' N k
9 .r O ,l'd" ^ s lilt
I
Li A1.6
g: ZO,LLAIP
C 1 (
i
� �
, Vt1-C7,` 1
y \. KIECt9 BAY1 TI O �.
TT it
iiii 'ii . . .:Z7z-r --N--- — — - - ,te.t..
L.,_ _i
ii, s. •; . { ''-'---=.4"1-=1 CORPUS MAIM BAY i. 1
INt
I 11, ifsi1 ITi, ter...w, 'i -,___.. he'
ri
•,..: • , .
{� V It
bk
y"�• p 11 'Is- I w.. , 'I. 10116COuP r,l z2T
; '
�I . ✓L �� -. ,. 3
Lit --z.-..... ' • ' V j,.) "6".* 'II, ( II3E1
Lpi i
EXHIBIT A
Dien 7 of 7