AMENDMENT NO. 6 to the
CONTRACT FOR PROFESSIONAL SERVICES
The City of Corpus Christi, Texas, a Texas home-rule municipal corporation("City')and LNV,Inc.("Consultant"),
agree to the following amendments to the Contract for Professional Services for O.N. Stevens Water Treatment
Plant High Service Building No. 3 (Project No. E11066):
Original Contract February 13, 2013 Administrative Approval $47,500.00
Amendment No. 1 October 15, 2013 Motion No. 2013-159 $2,358,103.00
Amendment No. 2 April 1, 2015 Administrative Approval $28,600.00
Amendment No. 3 February 15,2016 Administrative Approval $2,581.16
Amendment No. 4 May 5, 2017 Administrative Approval $20,300.00
Amendment No. 5 January 8, 2018 Administrative Approval $39,700.00
Exhibit A, Scope of Services shall be amended as set forth in the attached Amendment No. 6, Exhibit A.
Exhibit A, Fees shall be amended based on the modified scope of services in the attached Amendment No. 6,
Exhibit A for a fee not to exceed $23.718.75, for a total restated fee not to exceed $2.520,502.91.
All other terms and conditions of the February 13, 2013 contract between the City and Consultant, and of any
amendments to that contract, which are not specifically addressed herein shall remain in full force and effect.
CITY e F Co ' ' - RISTI LNV, IHC.J
Myr- lS -44°/1°P
via- H. Gray, . . Date Dan _. Leye •_ .r, P.E. 'a
Extive Director of P blic Works President
801 Navigation, Suite 300
Corpus Christi,TX 78408
(361)883-1984 Office
(361)883-1986 Fax
loganb@Invinc.com
RECOMME ;
-( ;)l 9 /8 '‘
J ff H. dmonds, P.E. ate
APPROVED AS TO LEGAL FORM
2018.08.31
9/1)/ 13:03:50 -05'00'
Assistant City Attorney Date
2018-453
9/06/18
LNV Inc.
ONS WTP HIGH SERVICE BUILDING N0 3+LNV AMENDMENT NO.8'1NV AMENDMENT NO 8 DOC REV.101!15
SCANNED
•
ATTEST
��.A l ( t /("/v
City Secretary Date
Accounting
Fund Name Unit Account No. Activity No. Amount
Water2012B RVBD 4091-041 550950 E11066-01-4091-EXP $23,718.75
Total $23,718.75
K:\ENGINEERING DATAEXCHANGE\CLARISSAJ\WATER\E11066-ONS WTP HIGH SERVICE BUILDING NO.3\LNV AMENDMENT NO.6\LNV AMENDMENT NO.6.DOC REV.10/1/15
LNV
Solutions Today with a
engineers ', architects contractors Vision for Tomorrow
August 17, 2018
Mr. Jeff Edmonds, P.E.
Director of Capital Programs
City of Corpus Christi
P.O. Box 9277
Corpus Christi, Texas 78469-9277
RE: AMENDMENT NO. 6 TO PROFESSIONAL SERVICES CONTRACT
O.N. Stevens Water Treatment Plant - High Service Pump Building No. 3
City Project E11066
Mr. Edmonds:
In response to the City's request, we are proposing Amendment No. 6 in the amount of $23,718.75
to provide additional services for the O.N. Stevens Water Treatment Plant - High Service Pump
Building No. 3 project (E11066) for a total re-stated project fee of$2,520,502.91.
PROJECT BACKGROUND
Original Contract
On February 18, 2013, LNV received formal Notice to Proceed (NTP) for engineering services
associated with the preliminary design of the new High Service Pump Building No. 3 for a total fee of
$47,500. This contract provided the scope of work for the full design and construction of the new
pump building by evaluating and inspecting the proposed site, performing system-wide hydraulic
modeling, and developing design criteria, including demand projections, master plan
recommendations, and recommendations from the Elevated Storage Tanks - Citywide and
Alternative Capacity Requirement (ACR) projects.
Amendment No. 1
On October 17, 2013, LNV received formal Notice to Proceed (NTP) for Amendment No. 1, which
was approved by City Council on October 15, 2013 by Motion No. M2013-159, to provide all Basic
and Additional Services associated with the design and construction of the new High Service Pump
Building No. 3 and Alternative Power Expansion for a fee not-to-exceed $2,358,103 for a total
restated fee not-to-exceed $2,405,603. The new pump building is anticipated to have the capability
to deliver treated water to the distribution system from the existing clearwells (Clearwell No. 1 and
Page 1 of 5
801 NAVIGATION I SUITE 300 I CORPUS CHRISTI,TEXAS 78408
OFFICE 361.883 1984 FAX 361883.1986 WWW.LNVINC.COM
EXHIBIT A
Page 1 of 5
No. 2) and future clearwells (Clearwell No. 3 and No. 4). The completion of this project would allow
the City to decommission High Service Pump Building No. 1.
Amendment No. 2
On April 9, 2015, LNV received formal Notice to Proceed (NTP) for Amendment No. 2 to provide
Additional Service No. 23 - Geotechnical - Subsurface Investigation for the new High Service Pump
Building No. 3 for a fee not-to-exceed $28,600 for a total restated fee not-to-exceed $2,434,203.
This additional service provided a geotechnical investigation of the proposed site for the new pump
building and a geotechnical engineering report, which included recommendations for the types of
foundations and pavement sections that should be considered in the design of the High Service
Pump Building No. 3.
Amendment No. 3
On February 16, 2016, LNV received formal Notice to Proceed (NTP) for Amendment No. 3 to
provide additional Basic Services (Design and Construction Administration) and Start-up, Warranty,
SCADA and Equipment O&M Manual, Windstorm Certification, and Geotechincal - Subsurface
Investigation Additional Services associated with the new High Service Pump Building No. 3 for a
fee not-to-exceed $2,581.16 for a total restated fee not-to-exceed $2,436,784.16. This amendment
reallocated unused funds from the Peer Review Coordination and Response Additional Service in
the amount of $138,053.70, along with the additional fee of $2,581.16 to complete the scope of
services for Amendment No. 3. The scope of services for Amendment No. 3 included the following
tasks:
• High Service No. 2 Pump Discharge Control Valve Replacement
• High Service No. 2 Motor Protection Relay (MPR) Replacement
• Clearwell No. 1 Repairs
• Existing Alternative Power Building Retrofit and Windstorm Certification
Amendment No.4
On May 15, 2017, LNV received formal Notice to Proceed (NTP) for Amendment No. 4 to provide
additional Basic Services (Design and Construction Administration) and Topographic Survey
Additional Services for a fee not-to-exceed $20,300.00 for a total restated fee not-to-exceed
$2,457,084.16. The scope of services for Amendment No. 4 included assessment and proposed
solution to address erosion issues around existing Clearwell No. 2 and potential weak unstable soils
along the drainage ditch south of High Service Pump Building No. 3, which were encountered during
construction. The proposed solution was incorporated into plans and specifications issued to the
Contractor to be included into their work scope for the High Service Pump Building No. 3 project.
Page 2 of 5
801 NAVIGATION I SUITE 300 I CORPUS CHRISTI,TEXAS 78408
OFFICE 361.883.1984 I FAX 361.883.1986 I WWW.LNVINC.COM
EXHIBIT A
Page 2 of 5
Amendment No. 5
On January 9, 2018, LNV received formal Notice to Proceed (NTP) for Amendment No. 5 to provide
additional Basic Services (Design) and Additional Services (Start-up, Warranty Phase, SCADA &
Equipment O&M Documentation) for a fee not-to-exceed $39,700.00 for a total restated fee not-to-
exceed $2,496,784.16. The purpose for Amendment No. 5 was to upgrade the existing and
designed control system network architecture to improve reliability and reduce complexity of the
existing High Service No. 2 (HS#2) and new High Service No. 3 (HS#3) systems.
PURPOSE OF AMENDMENT NO. 6
The City staff has requested professional services to provide software programming that will test
and verify the RTAC communication to all associated devices and will verify communication points
with the Facility DCS System. The programming service is exclusive to the RTAC (Real Time
Automation Controller— 1 Unit Total) and the associated Managed Ethernet Switches (3 Units Total)
which function as PCR#2 and PCR#3 Power Protection Network Communication devices. This
equipment serves as the interposing communication between the Motor Protection Relays (22 Units
Total) as well as the Feeder Protection Relays (8 Units Total) located in PCR#2 and PCR#3 and the
existing ONSWTP Facility SCADA system. The RTAC unit will be configured to poll for facility
defined data from the PCR#2 and PCR#3 SEL-710 & SEL-751A relays. It should be noted that this
work was originally in the Contractors scope and it was determined during construction that the
Contractor's integrator did not have the capabilities to perform the programming necessary to satisfy
the contract requirements. As a result, the scope of work as specified herein has been taken out of
the Contractors contract at a deducted cost that equals the amount of this amendment.
SCOPE OF WORK
ADDITIONAL SERVICES
TASK 24: RTAC Programming
This task is to include the following action items:
Provide software programming services in accordance to Contract Specification 40 90 02 (Section
2.2(A), Paragraph 4) and Contract Construction Drawing Sheets No.'s 238 (F4) and 239 (F5). The
programming service is exclusive to the RTAC (Real Time Automation Controller— 1 Unit Total) and
the associated Managed Ethernet Switches (3 Units Total) which function as PCR#2 and PCR#3
Power Protection Network Communication devices. This equipment serves as the interposing
communication between the Motor Protection Relays (22 Units Total) as well as the Feeder
Protection Relays (8 Units Total) located in PCR#2 and PCR#3 and the existing ONSWTP Facility
SCADA System. The RTAC unit will be configured to poll for facility defined data from the PCR#2
and PCR#3 SEL-710 & SEL-751A relays. The professional services provided for this task will test
and verify the RTAC communication to all associated devices and will verify communication points
with the Facility DCS System.
Page 3 of 5
801 NAVIGATION I SUITE 300 I CORPUS CHRISTI,TEXAS 78408
OFFICE 361.883.1984 I FAX 361.883.1986 { WWW.LNVINC.COM
EXHIBIT A
Page 3 of 5
SCHEDULE
All work under Amendment No. 6 of this contract shall be completed by the Engineer in accordance
with the schedule provided below.
Activity Completion Date
Additional Services
TBD; 4 to 6 Weeks After Relay Upgrade and
24. RTAC Programming Hardware Installation is Completed by the
Contractor
FEES
A. Fees for Basic Services. The City will pay fixed fee for providing for all "Basic Services"
except for the Construction Administration Phase authorized as shown in "ATTACHMENT 1".
The services for the Construction Administration Phase will be provided on a Time and
Material (T&M) basis as the project is moved towards completion. The fees for Basic
Services will not exceed those identified and will be full and total compensation for all
services outlined in this amendment.
B. Fees for Authorized Additional Services. The City will pay the ENGINEER the not-to-
exceed fee shown in "ATTACHMENT 1" for services specified in this amendment. The fee
will be full and total compensation for services and for all expenses incurred in performing
these services.
C. Summary of fees.
Refer to ATTACHMENT 1.
If you have any questions or if you would like to discuss in more detail, please feel free to call me at
361-883-1984.
Sincerely,
24112 ‘ 11/1 .---(57//7/18
Logan W. Burton, P.E.
Principal/Vice President
LNV, Inc.
TBPE Firm No. F-366
Page 4 of 5
801 NAVIGATION I SUITE 300 I CORPUS CHRISTI,TEXAS 78408
OFFICE 361.883.1984 I FAX 361.883.1986 WWW.LNVINC.COM
EXHIBIT A
Page 4 of 5
ORIGINAL AMD.NO.1 AMD.NO.2 AMD.NO.3 AMD.NO.4 AMD.NO.5 AMD.NO.6 TOTAL
CONTRACT _
pASIC SERVICES
1. Preliminary Phase $ 47,500.00 $ 381,371.00 $ - $ - $ - $ - $ - $ 428,871.00
2. Design Phase $ - $ 963,767.00 $ 88,304.86 $ 12,420.00 $ 26,870.00 $ - $ 1,091,361.86
3. Bid Phase $ - $ 35,219.00 $ - $ - $ - $ - $ 35,219.00
4. Construction Administration Phase $ - $ 277,453.00 $ 19,000.00 $ 4,880.00 $ - $ • $ 301,333.00 •
SUBTOTAL BASIC SERVICES(AUTHORIZED) $ 47,500.00 $ 1,657,810.00 $ - _ $ 107,304.86 _$ 17,300.00 $ 26,870.00 $ - $ 1,856,784.86
ADDITIONAL SERVICES(ALLOWANCE)
1. Permit&Agency Coordination $ - $ 24,026.00 $ - $ - $ $ - $ - $ 24,026.00 •
2. Topographic Survey $ - $ 58,346.00 $ - $ - $ 3,000.00 $ - $ - $ 61,346.00
3. Environmental Issues $ - $ 31,088.00 $ - $ - $ - $ • $ - $ 31,088.00
4. Construction Observation Services $ - TBD $ • $ - $ - $ - $ - $ -
5. Start-Up Services $ - $ 77,927.00 $ - $ 3,200.00 $ - $ 5,380.00 $ - $ 86,507.00
6. Warranty Phase $ - $ 53,906.00 $ - $ 4,950.00 $ - $ 3,950.00 $ - $ 62,806.00
7. SCADA&Equipment O&M Documentation $ - $ 51,175.00 $ - $ 2,000.00 $ - $ 3,500.00 $ - $ 56,675.00
8.Public Involvement(N/A) $ - N/A , $ - $ - $ - $ - $ - $
9.Electronic Operations O&M Manual $ - TBD $ - $ - $ - $ - $ - $ -
10.Conformed Contract Documents $ - TBD $ - $ - $ - $ - $ - $ -
11.Existing Facilities Condition Assessment $ - TBD $ - $ - $ - $ - $ - $
12.Windstorm Certification $ - $ 19,800.00 $ - $ 21,680.00 $ - $ - $ - $ 41,480.00
13.Peer Review Coordination&Response $ - $ 153,393.00 $ - $ (138,053.70) $ - $ • $ - $ 15,339.30
14.High Srvc.Pumping Sys.Energy Audit&Conservation Evaluation $ - TBD $ - $ - $ - $ - $ - $ -
15.Physical Laboratory Scale Hydraulic Modeling Study $ - TBD $ - $ - _ $ - $ - $ - $
16.Disinfection CT Evaluation $ - TBD $ - $ - $ - $ - $ - $ -
17.Plant Process and Hydraulic Evaluation $ - TBD $ - $ - $ - $ - $ - $ -
18.Electrical Studies $ - $ 51,150.00 $ - $ - $ - $ - $ - $ 51,150.00
19.Control Logic&Application Development Support $ - $ 28,416.00 $ • $ - $ - $ - $ - $ 28,416.00
20.Control System Integration Coordination $ - $ 28,416.00 $ - $ - $ - $ - $ - $ 28,416.00
21.Project Manual $ - $ 23,650.00 $ $ $ - $ • $ - $ 23,650.00
22.Program Management&Projects Coordination $ - $ 99,000.00 $ - $ • $ • $ - $ - $ 99,000.00
23.Geotechnical.Subsurface Investigation $ - $ - $ 28,600.00 $ 1500.00 $ - $ - $ $ 30,100.00
24.RTAC Programming $ 23,718.75 $ 23,718.75
SUBTOTAL ADDITIONAL SERVICES(AUTHORIZED) $ - $ 700,293.00 $ 28,600.00 $ 1104,723.704 $ 3,000.00 $ 12,830.00 $ 23,718.75 $ 663,718.05
TOTAL AUTHORIZED FEE $ 47,500.00 $ 2,358,103.00 $ 28,600.00 $ 2,581.16 $ 20,300.00 $ 39,700.00 $ 23,718.75 $ 2,520,502.91