HomeMy WebLinkAboutC2018-454 - 9/11/2018 - NA CITY OF CORPUS CHRISTI
AMENDMENT NO.4
CONTRACT FOR PROFESSIONAL SERVICES
The City of Corpus Christi, Texas, a Texas home-rule municipal corporation ("City") and Urban Engineering
("Consultant"), agree to the following amendments to the Contract for Professional Services for Park Road 22
Bridge (Project No. 6281):
Original Contract October 11, 2011 Motion No. M2011-223 $1,072,714.00
Amendment No. 1 May 14, 2013 Administrative Approval $49,805.00
Amendment No. 2 June 2, 2014 Administrative Approval $0.00
Amendment No. 3 January 23, 2015 Administrative Approval $49,270.00
In the Original Contract, Exhibit"A", Section I. Scope of Services shall be amended as set forth in the attached
Amendment No. 4, Exhibit"A".
In the Original Contract, Section III. Fees shall be amended based on the modified scope of services in the attached
Amendment No. 4, Exhibit "A" for a fee not to exceed $12,000.00, for a total restated fee not to exceed
$1,183,789.00.
All other terms and conditions of the October 11, 2011 Contract for Professional Services between the City and
Consultant,and of any amendments to that contract,which are not specifically addressed herein shall remain in full
force and effect.
CITY U H ISTI U- = ENGINEERIN=
- , 9A
7. 2ei8
J H. Edmonds, P. E. Date Authorized Representa i'- Date
Director of Engineering Services 2725 Swantner Drive
820 Buffalo Street
Corpus Christi, TX 78404
APPROVED AS TO LEGAL FORM (361)854-3101 Office
94) 2018.09.10 14:05:13 chipu@urbaneng.com
-05'00'
Assistant City Attorney Date
ATTEST
G ci-z, l! 311E
Ci Secretary Date
Accounting Unit 3541-051
Account 550950
Activity 170062-01-3541-EXP
Account Category 550950
Fund Name Street 2005 GO
2018-454
9/11/18
Urban Engineering
SCANNED
U RBAN
ENGINEERING Job No. 42481.00.00
August 31, 2018
Mr. Jeff Edmunds, P.E. Sent Via Email
Director of Engineering Services
City of Corpus Christi
P.O. Box 9277
Corpus Christi, Texas 78469
Subject: Park Road 22 Bridge (Project No. 6281)—Contract Amendment No. 4
Dear Mr. Edmunds:
We are proposing Amendment No. 4 to our contract to address additional work.
Per our discussion earlier this week, it is our understanding that the city intends to re-bid PR
22 Bridge Project. However, prior to bidding the city would like for us to explore the possibility of
reducing or eliminating the retaining walls by changing to sloped embankment where possible.
The bulkheading and fill activity on the property east of PR 22 at the project location may
have changed conditions that lead to a jurisdictional determination by the USACE. The original
determination considered the roadside ditches to be jurisdictional due to a tidal influence. Since
the property to the east has been dredged and bulk headed, that may no longer be the case. In
the event that the ditches may no longer need to be mitigated for, this could mean a significant
savings to the project that would not have a significant impact on the environmental document
and schedule.
We propose to work with Raba Kistner Environmental to prepare exhibits and initiate an
informal dialogue with the Corps to determine if the change in conditions would likely change the
existing jurisdictional determination and the steps that would be necessary to do so, including a
timeline to accomplish a revised determination. We would also meet with TXDOT to determine
the impact this would have on the Environmental Assessment.
Urban Engineering will deliver a letter report outlining our discussions with the Corps and
TXDOT. The report will also include an estimate of the walls that could be reduced and the
potential savings. We propose to provide these services on a Time & Materials basis not to
Exceed $12,000.
Sincerely,
URBAN ENGINEERING
-- /
- _ -
Rhodes"Chip" Urban, P.E., R.P.L.S.
RCU/
Cc: File
(361)854-3101 2725 SWANTNER DR. • CORPUS CHRISTI,TEXAS 78404 FAX(361)854-6001
www.urbaneng.com AMEND. NO. 4
TBPE Firm#145 EXHIBIT "A"
TBPLS Firm#10032400 Page 1 of 1
Park Road 22 Bridge
Project No. 6281
Summary of Fees
ORIGINAL AMEND. NO. 1 AMEND. NO. 2 AMEND. NO. 3 AMEND. NO.4 TOTAL
CONTRACT
Fee for Basic Services
1 Preliminary Phase $131,250.00 $25,000.00 $0.00 $0.00 $0.00 $156,250.00
2 Design Phase 364,000.00 86,700.00 63,200.00 17,950.00 12,000.00 543,85$.00
3 Bid Phase 7,250.00 1,800.00 0.00 0.00 0.00 9,050.00
4 Construction Phase 52,500.00 17,500.00 0.00 0.00 0.00 70,000.00
Subtotal Basic Services Fees 555,000.00 131,000.00 63,200.00 17,950.00 12,000.00 779,150.00
Fee for Additional Services(Allowance)
1 Permit Preparation (as applicable)
U. S. Army Corps of Engineers 180,000.00 (92,120.00) 7,100.00 4,200.00 0.00 99,180.00
NPDES Permit/Amendments 3,000.00 0.00 0.00 0.00 0.00 3,000.00
TXDOT Categorical Exclusion 101,534.00 2,725.00 5,650.00 33,820.00 0.00 143,729.00
Public Meetings for CE(2 Meetings) 20,000.00 0.00 0.00 0.00 0.00 20,000.00
Public Hearing for CE 10,850.00 0.00 0.00 11,350.00 0.00 22,200.00
Texas Department of License and Regulation 2,500.00 0.00 0.00 0.00 0.00 2,500.00
Coast Guard Permit Section 9 19,830.00 0.00 0.00 0.00 0.00 19,830.00
Total Permitting 337,714.00 (89,395.00) 12,750.00 49,370.00 0.00 310,439.00
2 Public Meetings 5,000.00 0.00 0.00 0.00 0.00 5,000.00
3 Topographic Survey(AUTHORIZED) 50,000.00 8,200.00 0.00 0.00 0.00 58,200.00
4 Subsurface Utility Investigation (AUTHORIZED) 16,500.00 0.00 0.00 0.00 0.00 16,500.00
5 Construction Observation Services 94,000.00 0.00 (75,950.00) (18,050.00) 0.00 0.00
6 Environmental Issues 8,000.00 0.00 0.00 0.00 0.00 8,000.00
7 Start-up Services(Lift Station) 3,000.00 0.00 0.00 0.00 0.00 3,000.00
8 Warranty Phase 3,500.00 0.00 0.00 0.00 0.00 3,500.00
Subtotal Additional Services Fees 517,714.00 (81,195.00) (63,200.00) 31,320.00 0.00 404,639.00
Total Authorized Fee $1,072,714.00 $49,805.00 $0.00 $49,270.00 $12,000.00 $1,183,789.00
M2011-223 Admin Approval Admin Approval Admin Approval Admin Approval .
10/11/11 05/14/13 06/02/14 01/23/15