HomeMy WebLinkAboutC2018-470 - 9/21/2018 - NA CITY OF CORPUS CHRISTI
AMENDMENT NO. 1
CONTRACT FOR PROFESSIONAL SERVICES
The City of Corpus Christi, Texas, a Texas home-rule municipal corporation("City")and LNV,Inc.("Consultant"),
agree to the following amendments to the Contract for Professional Services for Holly Road from Paul Jones to
Rodd Field Road BOND 2018 (Project No. 18021A):
Original Contract June 12, 2018 Resolution No. 031445 $792,940.00
In the Original Contract, Exhibit "A", Section I. Scope of Services shall be amended as set forth in the attached
Amendment No. 1, Exhibit"A".
In the Original Contract,Section III. Fees shall be amended based on the modified scope of services in the attached
Amendment No. 1, Exhibit "A" for a fee not to exceed $36,600.00, for a total restated fee not to exceed
$829,540.00.
All other terms and conditions of the June 12, 2018 Contract for Professional Services between the City and
Consultant,and of any amendments to that contract,which are not specifically addressed herein shall remain in full
force and effect.
CITY OF CORPUS CH STI LNV I4 N
,..
////�/� 21 r8 ��� �-�. ,' V, 09/10/18
Mark Van Vlec c� -��-�-"
D e D- •- er, P.E. Date
Assistant City M.na!er President
at , e
ill ' ,/ s Corpus801NChvigaristiion, TSuitX 78408300
C. (361)883-1984 Office
V.7 e H. Gr- , P. =. sate danl@Invinc.com
Ex: utive 9' : o o P is Works pf
0C}' yl /g"
eff H. Edmonds, P. E. Date
Director of Engineering Services
APPROVED AS TO LEGAL FORM
0 2018.09.10 14:07:53
-05'00'
Assistant City Attorney Date
raeoe,.....4„12.44r."
gic-_7/1 8
City Secretary Date
Accounting Unit 3551-051
e,...ru i„+ nogn
2018-470
9/21/18
LNV Inc.
SCANNED
•
LNV
Solutions Today with a
engineers architects contractors Vision for Tomorrow
August 23, 2018
Mr. Jeff Edmonds, P.E.
Director of Engineering Services
City of Corpus Christi
P.O. Box 9277
Corpus Christi, Texas 78469-9277
RE: AMENDMENT NO. 1 TO PROFESSIONAL SERVICES CONTRACT
Holly Road— Rodd Field to Ennis Joslin (Bond 2018)
City Project 18021A
Mr. Edmonds:
The City has requested that LNV make the following changes and revisions to the scope of
improvements on the Holly Road (18021A) Project:
1. Reduce the Project Limits to only include improvements from Rodd Field Road to Ennis
Joslin Road with no Additive Alternate for Ennis Joslin Road to Paul Jones Avenue;
2. Add the replacement of the existing 30" water transmission main from Rodd Field Road to
Ennis Joslin Road; and
3. Revise the design road profile such that no roadside ditches are required, and drainage is
accomplished through underground storm sewer only.
In response to this, we are proposing Amendment No. 1 in the amount of $36,600 to provide
additionally-required engineering services to accomplish the changes.
PROJECT BACKGROUND
On June 20, 2018, LNV received a formal Notice to Proceed (NTP) on the Holly Road—Rodd Field
to Ennis Joslin (Bond 2018) Project (18021A), which will provide for the reconstruction of Holly
Road from Rodd Field Road to Ennis Joslin Road with an Additive Alternate for the continued
reconstruction from Ennis Joslin Road to Paul Jones Avenue. On July 24, 2018, LNV submitted the
DRAFT Engineering Letter Report on schedule. The Original Contract amount for the Basic and
Additional Services associated with this project was $792,940.
Page 1 of 4
801 NAVIGATION I SUITE 300 I CORPUS CHRISTI,TEXAS 78408 AMEND. NO. 1
OFFICE 361.883.1984 I FAX 361.883.1986 I WWW.LNVINC.COM EXHIBIT "A"
Page 1 of 5
Holly Road Project LNV, Inc. August 23,2018
(18021A) Contract Amendment No. 1
PURPOSE OF AMENDMENT NO. 1
The purpose of Amendment No. 1 is to provide additionally-required engineering services
necessary to perform the Project revisions and added scope of improvements. The work covered
by Amendment No. 1 includes completion of the Preliminary Phase, as described below, and
additional design efforts for the replacement of the existing 30" water transmission main and
lowering of the road profile. The lowered road profile will require the design of retaining walls, ditch
fill, and extended driveway and intersecting street connections.
SCOPE OF WORK
BASIC SERVICES:
1. Preliminary Phase: The DRAFT Engineering Letter Report (ELR) submitted on July 24, 2018
will be revised to reflect the revisions to the Project Scope of Improvements and to address City
comments received on the DRAFT ELR. A Response-to-Comments letter will be prepared and
submitted with the FINAL ELR per the amended schedule below. This work will be performed
with no increase to the Preliminary Phase fee.
2. Design Phase: Additional design efforts covered by this Amendment include: design of
retaining walls, design of extended driveway and intersecting road connections, design of utility
adjustments for conflicts with existing utilities, and design of a new 30"water transmission main,
including: water modeling to determine allowable downtime, night-time connections to the
existing main, pre-connection water system requirements, sequence of water construction, and
removal or abandonment of the existing 30" main.
3. Bid Phase: No change.
4. Construction Administration Phase: No change.
ADDITIONAL SERVICES:
Changes to the Additional Services related to this Amendment include:
Item 5. Design Water System Improvements: Authorization of this Original Contract task for the
design of water distribution improvements. This task does not include design efforts
related to replacement of the existing 30"water transmission main.
Item 9. Stormwater Pollution Prevention Plan: Removal of this task item and reallocating its fee to
the Design Phase.
Item 10. Traffic Signal Design — Rodd Field Road: Removal of this task item and reallocating its
fee to the Design Phase.
Page 2 of 4
801 NAVIGATION I SUITE 300 I CORPUS CHRISTI,TEXAS 78408 AMEND. NO. 1
OFFICE 361.883.1984 I FAX 361.883.1986 I WWW.LNVINC.COM EXHIBIT"A"
Page 2 of 5
Holly Road Project LNV, Inc. August 23,2018
(18021A) Contract Amendment No. 1
SCHEDULE
Pending receipt of approval and Notice to Proceed with this amendment, LNV will perform the
remaining work on the Project per the revised schedule below. Revisions to the Original Contract
Schedule are shown in RED.
Date Activity
(8-31-18) Submit Response to ELR
Comments & Final ELR
6 Weeks after Final ELR Submittal 60% Design Submittal
(10-12-18)
2 Weeks City Review
2 Weeks after Receipt of City 100% Design Submittal
Comments (11-09-18)
2 Weeks City Review
2 Weeks after Receipt of City Final Submittal
Comments (12-07-18)
(1-8-19) Advertise for Bids
(1-15-19) Pre-Bid Conference
(1-23-19) Receive Bids
(2-20-19) Contract Award
(3-6-19) Begin Construction
Approximately 28 Months (July Complete Construction
2021)
FEES
A. Fees for Basic Services. The City will pay the NE a fixed fee for providing for all "Basic
Services" authorized as per the table shown in ATTACHMENT 1. The fees for Basic
Services will not exceed those identified and will be full and total compensation for all
services outlined herein and in Original Contract Sections I.A.1-4, and for all expenses
incurred in performing these services. The fee for this project is subject to the
availability of funds. The Engineer may be directed to suspend work pending receipt
and appropriation of funds. For services provided, NE will submit monthly statements for
services rendered. The statement will be based upon NE's estimate (and with City's
concurrence) of the proportion of the total services actually completed at the time of billing.
City will make prompt monthly payments in response to A/E's monthly statements.
B. Fees for Authorized Additional Services. For services authorized by the Executive
Director of Public Works under Original Contract Section I.B. "Additional Services", as
modified herein, the City will pay the NE a not-to-exceed fee as per the table shown in
ATTACHMENT 1.
Page 3 of 4
801 NAVIGATION I SUITE 300 I CORPUS CHRISTI,TEXAS 78408 AMEND. NO. 1
OFFICE 361.883.1984 I FAX 361.883.1986 I WWW.LNVINC.COM EXHIBIT "A"
Page 3 of 5
•
•
Holly Road Project LNV Inc August 23, 2018
(18021A) Contract Amendment No 1
C. Summary of fees.
Refer to ATTACHMENT 1
If you have any questions, or if you would like to discuss in more detail, please feel free to call me
at 361-883-1984.
Sincerely,
Dan S. Le •ecker, P.E.
President/CEO
LNV, Inc.
TBPE Firm No. F-366
Cc:LNV File
Attachment
DSJ/dsl
Page 4 of 4
801 NAVIGATION SUITE 300 I CORPUS CHRISTI,TEXAS 78408
OFFICE 361 883.1984 FAX 361 8831986 WWW LNVINC COM
AMEND. NO. 1
EXHIBIT "A"
Page 4 of 5
ATTACHMENT 1 - SUMMARY FEE TABLE
Project: Holly Road (18021A)
TASK ORIGINAL CONTRACT AMENDMENT 1 TOTAL
BASIC SERVICES
1. Preliminary Phase _ $105,000 $0 $105,000
2. Design Phase $448,000 $71,100 $519,100
3. Bid Phase $15,000 $0 $15,000
4. Construction Administration Phase $49,900 $0 $49,900
Subtotal Basic Services $617,900 $71,100 $689,000
ADDITIONAL SERVICES(ALLOWANCE)
1. Permit: TDLR * $1,940 $0 $1,940
2. ROW Survey* $3,800 $0 $3,800
3. Topographic Survey* $19,700 $0 $19,700
4. Hazardous Materials $3,300 $0 $3,300
5. Design Water System Improvements * $60,000 $0 $60,000
6. Design Wastewater System Upgrades TBD $0
7. Public Involvement(2 Meetings) * $13,000 $0 $13,000
8. Detailed Traffic Control Plans $12,000 $0 $12,000
9. Stormwater Pollution Prevention Plan $5,500 ($5,500) $0
10. Traffic Signal Design -Rodd Field Road $29,000 ($29,000) $0
11. Street Light Design * $22,100 $0 $22,100
12. Warranty Phase $4,700 $0 $4,700
Subtotal Additional Services $175,040 ($34,500) $140,540
TOTAL FEE $792,940 $36,600 $829,540
(` Additional Services authorized with the Original Council Approved on
Contract or this Amendment.) 6/12/2018 by Res. No.
031445
AMENDMENT 1
ATTACHMENT 1
AMEND. NO. 1
EXHIBIT "A"
Page 5 of 5