HomeMy WebLinkAboutC2018-524 - 8/7/2018 - NA TASK ORDER 2
This Task Order pertains to a Master Services Agreement for Professional Services by and between City of Corpus
Christi, Texas (City) and Freese and Nichols, Inc. (Consultant) dated December 19, 2017 (Motion M2017-196)
(Agreement). Consultant shall perform services on the project described below as provided in this Task Order and
in the Agreement. This Task Order shall not be binding until it has been properly signed by both parties. Upon
execution, this Task Order shall supplement the Agreement as it pertains to the project described below.
MSA PROJECT NUMBER/NAME: 18061A Preliminary Engineering Street Feasibility and Cost Estimate
Reports (Bond 2018)
TASK ORDER PROJECT NUMBER /NAME: 18061 C Preliminary Engineering Street Feasibility and Cost
Estimate Reports (Bond 2018)
1. PROJECT DESCRIPTION: 18033B North Beach Coastal Protection
2. SCOPE OF SERVICES The scope of services includes preliminary engineering street feasibility and
cost estimate reports. This task order is more fully described in Exhibit A.
3. COMPENSATION The total amount not to exceed for Task Order No. 2 only is $24,744.
This Task Order is approved and Consultant may proceed. All other terms and conditions of the Agreement
remain in full force and - ect.
C 0' o 11 H- STI FREESE AND NICHOLS, INC.
�� /
�
� /�, August 6, 2018
Je' H. Edmonds, P. E. Date I on Guzman, P. E. Date
Director of Engineering Services Principal
800 N. Shoreline Blvd., Suite 1600N
Corpus Christi, TX 78401
(361) 561-6500 Office
(361) 561-6501 Fax
rg@freese.com
Fund Name Accounting Unit Account No. Activity No. Amount
ST 2012 GO BD 08 3548-051 550950 E17083-01-3548-EXP $24,744
C2018-524
8/07/18
Freese and Nichols Inc.
SCANNED
'trait',
•
FFREESE
7?NICHOLS E stand;
800 N.Shoreline Blvd.,Suite 1600N • Corpus Christi,Texas 78401 • 361-561-6500 • fax 361-561-6501 aruw.treese.com
TASK ORDER NO.: 2
PROJECT NAME: Preliminary Engineering Street Feasibility and Cost Estimate
Reports (Bond 2018)
1. PROJECT DESCRIPTION —N. Beach Coastal Protection Project ID No. TBD
2. SCOPE OF SERVICES —
a. FNI will meet with City staff to:
• Discuss project goals
• Discuss project parameters and timelines
• Discuss funding opportunities for this project
• Receive guidance on project approach
• Receive record drawings, studies, utility base maps, surveys, or
other project information
• Discuss permitting requirements, approaches, and timelines
b. With the support of the City, FNI will obtain existing data needed to
perform the evaluation of the proposed Erosion Protection conceptual
plan. Existing data needed to support the evaluation may include, but not
be limited to: bathymetry, geology, geotech, hydrology, storm analysis,
existing beach morphology and changes, sediment transport mechanisms,
and topographic survey.
c. FNI will identify expected technical considerations for the conceptual project
plan, including: need for protective structures relative to proposed concepts,
constructability of desired features, and required future maintenance
considerations. FNI will identify potential project composition alternatives for
island material (beneficial use of fill from other projects, e.g. future dredging
for new Port projects, Harbor Bridge abutment demolition, etc.), and structural
composition, such as: reuse of roadway concrete rip rap, rubble-rock, and
manufactured shoreline protection alternatives. The technical practicality and
associated preliminary costs of implementing these considerations will be
estimated.
d. FNI will conduct basic numerical modeling for conceptual evaluation of the
water elevations, wind, waves, and currents to determine potential siting of a
coastal protective structure(s), such as: distance from beach, basic geometry,
and depth of water.
TASK ORDER NO. 2
Exhibit"A"
Page 1 of 3
e. FNI will assemble and submit a draft Conceptual Plan Evaluation Report to
include:
• Results of the technical practicality assessment
• Alternatives for protective features of the conceptual project plan
• Order of magnitude Conceptual level Opinion of Probable
Construction Costs for both reuse material and original construction
material.
• Permitting guidance
• Sequence of events table or narrative to guide the City on the
process needed to bring the project to a successful conclusion,
including identification of roadblocks or major milestones.
• Identification of post-construction maintenance considerations
• FNI will meet with City Staff in a submittal meeting
f. FNI will assemble and submit a final Conceptual Plan Evaluation Report
based on City review comments.
g. FNI will attend upato(2)meetings with Engineering and/or Utilities Staff to
facilitate project coordination
h. FNI will attend up to one (1) meeting with USACE's regulatory staff
The City staff will:
a) Assign a project manager to oversee the project
b) Provide all relevant data or guidance required to support updated
design details
c) Review and comment on the draft Conceptual Plan Evaluation
Report
d) Attend meeting with USACE—Corpus Christi Regulatory Field Office
Submittals:
1 draft report(2 hard copies and 1 electronic)
1 final report(2 hard copies and 1 electronic)
Schedule:
Date Activity Fee
Coordinate and meet with City for
guidance on Conceptual Plan $3,417.00
Within 1 week of Notice to Evaluation Report and review
Proceed preliminary data provided.
TASK ORDER NO. 2
Exhibit"A"
Page 2 of 3
Submit Preliminary Conceptual
Within 3 weeks of Notice to Plan Evaluation Report for City $15,892.75
Proceed Review and Comment
Within 12 weeks of receipt of
City comments on draft Submit final Conceptual Plan $5,434.25
submittal Evaluation Report
Total Effort $24,744.00
3. COMPENSATION Lump sum amount of$24,744.00
This Task Order is approved, and Consultant may proceed. All other terms and
conditions of the Agreement remain in full force and effect.
FREESE AND NICHOLS, INC.
(..31„,.1,.
7/19/2018
Ron Guzman, P. E. Date
Principal
800 N. Shoreline Blvd., Suite 1600N
Corpus Christi, TX 78401
(361) 561-6500 Office
(361) 561-6501 Fax
rg@freese.com
TASK ORDER NO. 2
Exhibit "A"
Page 3 of 3
EXHIBIT B
TASK ORDER SUMMARY
Master Services Agreement
Preliminary Engineering Street Feasibility and Cost Estimate Reports (Bond 2018)
Project No. 18061A
TASK NOT TO
DESCRIPTION AMOUNT EXCEED
AMOUNT
Master Services Agreement(Dec. 19,2017) $300,000.00
Amendment No. 1 to Master Services Agreement(Jul. 25, 2018) 25,000.00
Maximum Contract Amount $325,000.00
TASK ORDERS: 313,897.00
Task Order No. 1 _ 289,153.00
18004A Airline Road from SPID to McArdle Road 36,250.00
18005A Alameda Street from Chamberlain to Louisiana 39,217.00
18007A Beach Avenue from Dead End at Gulf Breeze to E 33,174.00
Causeway
18011A Castanon from Trojan to Delgado 33,147.00
18012A Downtown Management District Improvements 38,804.00
18033A North Beach Access Management Initiative 38,417.00
18041A S. Staples Street from Kostoryz to Baldwin 26,224.00
18046A Swantner Drive from Texan Trail to Indiana Avenue 43,920.00
Task Order No. 2 24,744.00
18033B North Beach Coastal Protection 24,744.00
Amount Remaining on Master Services Agreement $11,103.00
TASK ORDER NO.2
Exhibit"B"
Page 1 of 1