HomeMy WebLinkAboutC2018-583 - 10/19/2018 - NA CITY OF CORPUS CHRISTI
CONTRACT FOR PROFESSIONAL SERVICES
AMENDMENT NO. 4
The City of Corpus Christi, Texas, a Texas home-rule municipal corporation ("City") and HDR Engineering. Inc.
("Consultant"), agree to the following amendments to the Contract for Professional Services for Corpus Christi
Aquifer Storage and Recovery Feasibility Study (Project No. E162651:
Original Contract July 26, 2016 Ordinance No. 030902 $601,980.00
Amendment No. 1 September 8, 2016 Administrative Approval 0.00
Amendment No. 2 May 12, 2017 Administrative Approval $24,820.00
Amendment No. 3 May 4, 2018 Administrative Approval $19,964.00
In the Original Contract, Exhibit A, Scope shall be amended as set forth in the attached Amendment No.3, Exhibit A.
In the Original Contract, Exhibit A, Fees shall be amended based on the modified scope of services in the attached
Amendment No. 3, Exhibit A for a fee not to exceed $26,070.00,for a total restated fee not to exceed $672,834.00.
All other terms and conditions of the July 26, 2016 Contract for Professional Services between the City and
Consultant, and of any amendments to that contract,which are not specifically addressed herein shall remain in full
force and effect.
CITY OF CORP CHRISTI HDR ENGINEERING, INC.
11 I Nip. ,�fill‘ tO I' Ggj ✓t'.?'2= — 10/11/18
qd .r Van VI:ck Date Mark Borenstein, P.E. Date
U A stant City ,an.ger Vice President
4401 West Gate Boulevard, Suite 400
Austin, Texas 78745
(512) 912-5100 Office
kristi.shaw@hdrinc.com
RECOMMENDED 1
Ali di, 1 ; (0(1° l
Val" . Gray, P.E. Date
Exe e Direct., •f "ublic Warks
iI
f 4 604) /9 OLr 18
Jeff H. '.1.F onds, P.E. Date
Director of Engineering Services
4
APPROVED
ED AS TO LEGAL FORM
2018.10.12 14:46:28
' � -05'00'
Assistant City Attorney Date
K.1ENGINEERING DATAEXCHANGEICLARISSAJIWATER\E 16265-CORPUS CHRISTI AQUIFER STORAGE AND RECOVERY FEASIBILITY STUDYIHDR AMENDMENT NO 41AMENDMENT NO 4 DOC
C2018-_583
10/19/18
HDR Engineering Inc.
SCANNED
ATTEST Accounting Unit 4481-041
Account 550950
Activity E16265-01-4481-EXP
1°/�./, Account Category 50950
��� Fund Name RWSppIyDvChciCIP
City Secretary Date
K:\ENGINEERING DATAEXCHANGE\CLARISSAJ\WATER\E16265-CORPUS CHRISTI AQUIFER STORAGE AND RECOVERY FEASIBILITY STUDY\HDR AMENDMENT NO.4\AMENDMENT NO.4.DOC
•
•
September 26, 2018
Mr. Alex Barabanov, P.E.
Senior Project Manager
Engineering Services
City of Corpus Christi
P.O. Box 9277
Corpus Christi,Texas 78469-9277
RE: Amendment No.4 to Professional Services Agreement for Corpus Christi Aquifer
Storage and Recovery Feasibility Study(Project No. E16265)
Dear Mr. Barabanov:
In August 2016,HDR Engineering, Inc (HDR) entered into an agreement with the City of
Corpus Christi to provide Professional Services for the Corpus Christi Aquifer Storage and
Recovery(ASR) Feasibility Study. Project funding was authorized and allocated by City
Council on July 26, 2016, which included HDR's professional services, well drilling and
construction services, and provisions for additional requested services and contingencies
beyond those identified in the original scope, not to exceed the City's total appropriation'
for the project. HDR's original contract and amendment amounts are shown in
Attachment 1. The details of the City's contract and amendments with Felder Water Well
LC for drilling and construction services are not addressed in this letter.
The additional services requested of HDR by City Staff included in this Amendment No 4
are as follows:
• Item 1-Coordination,review, and follow-up necessary to gather drilling-related
submittals from Felder Water Well LLC pursuant with driller agreement with the
City(March 22 to August 2, 2018); and
• Item 2- Retesting of Greenwood WWTP samples from Greenwood WWTP for
bacteriological, radionuclide, and metals (As and U) analysis for verification
purposes, as authorized by email on July 6, 2018.
I Approved by City Council on July 26,2016 by Ordinance No.030902,which included but is not limited to
acceptance of TWDB grant in amount up to$433,388 and appropriating funding from the Raw Water Supply
Development Fund No.4041 to combine with previously assigned Water Supply Operating Fund for a total
project budget of$1,857,708 which included contingency for additional efforts that may arise during the
three-year study.
hdrinc.com
4401 West Gate Blvd.,Suite 400,Austin,TX 78745
T 512.912 5100 F 512-912.5158 Texas Registered Engineering Firm F-754
EXHIBIT A
Page 1 of 4
•
Mr Alex Barabanov,P.E.
September 26,2018
Page 2
ITEM 1-
The City's agreement with the driller specified substantial completion within 133 days of
notice to proceed, or February 16, 2018. The drilling activities were substantially
completed on March 8, 2018,or 138 days (20 weeks) after notice to proceed. Additional
HDR support associated with these changes related to field schedule were reflected in
HDR's Amendment No. 3.
The driller's contract documents and agreement with the City included submittals (Section
33 21 31 Part 1.3) to be provided by the driller. At City staff request, HDR began
coordinating with Felder Water Well LLC after drilling was complete to obtain submittals
required by driller. From March 22 to August 2, 2018, HDR coordinated with Felder
Water Well LLC by email/phone and provided follow-up of outstanding items still needed
pursuant to City agreement at an average frequency of twice per week. HDR reviewed
materials sent by driller and requested clarification, when needed,on items that were
different from HDR field records or inconsistent with prior records provided by the driller.
On August 2, 2018,it was deemed that the driller had satisfied the submittal requirement
specified in their agreement with the City.
ITEM 2-
HDR was requested to assist in the re-sampling of Greenwood WWTP effluent. Services
included laboratory coordination related to analysis of samples for bacteriological,
radionuclide, and metals (As and U), coordination with City staff on sample collection
procedures, review of water quality data,comparison to previous results, and summarizing
in Geochemical Technical Memo.
Attached for your consideration is Amendment No. 4, for costs incurred on activities
beyond our original scope of work as summarized in Attachment 1. A detailed breakdown
of hours and costs for each of the two items associated with this amendment is included in
Attachment 2. Please prepare an amendment to the subject contract for$26,070. Should
you need additional information,please contact me at 512-912-5118 at your convenience.
Sincerely,
HDR Engineering, Inc.
Kristine S.Shaw,P.E.
Project Manager
EXHIBIT A
Page 2 of 4
Attachment 1
Corpus Christi Aquifer Storage and Recovery Feasibility Project
City Project No.E16265
Amd Amd Amd Amd Total
Basic Services: Contract No. 1 No.2 No.3 No.4 Contract
Task 1-Formulate Program $44,286 SO SO $44,286
Task 2-Exploratory Test Drilling Program $276,055 0 $24,820 $19,964 $22,011 $342,850
Task 3-Geochemical Analysis $65,906 0 SO $4,059 669,965
Task 4-Field Scale Groundwater Model 5116,753 0 SO $116,753
Task 5-ASR Operating Policies $29,553 0 SO 629,553
Task 6-TWDB Coord,Deliv&Meeting 369,427 0 $0 169,427
Subtotal Basic Services $601,990 SO $24,820 $19,964 $26,070 6672,834
Additional Services:
Subtotal Additional Services $0 $0 $0 $0 $0 $0
Summary of Fees
Basic Services Fees $601,980 $0 $24,820 $19,964 $26,070 6672,834
Additional Services Fees 0 0 0 0 0 0
Total of Fees $601,980 SO $24,820 $19,964 $26,070 $672,834
EXHIBIT A
Page 3 of 4
•
Attachment 2
Amendment#4 Details Amount Hours
Item 1-Driller Submittal(itemization below) $22,011 101
*March 22-April 28 $6,526 30
*April 29-May 26 $7,189 33
*May 27-June 30 $5,530 25
*July 1-August 2 $2,766 13
Item 2-Greenwood WWTP re-test $4,059 20
Total Amendment#4 $26,070 121
EXHIBIT A
Page 4 of 4