HomeMy WebLinkAboutC2017-118 - 3/23/2017 - NA TASK ORDER NO. 11
This Task Order pertains to a Master Services Agreement for Professional Services by and between City of Corpus
Christi, Texas (City) and LNV, Inc. (Consultant) dated August 16, 2016 (Agreement). Consultant shall perform
services on the project described below as provided in this Task Order and in the Agreement. This Task Order
shall not be binding until it has been properly signed by both parties. Upon execution, this Task Order shall
supplement the Agreement as it pertains to the project described below.
PROJECT NAME/NUMBER: Water and Wastewater Treatment On-Call Support, E16264
1. PROJECT DESCRIPTION—This project provides the Utility Department with on-call services to assist with
any technical,operational, maintenance, diagnostic and design concerns for the City's O.N.Stevens Water
Treatment Plant and six wastewater treatment plants.
2. SCOPE OF SERVICES — Foundation Design and Windstorm Inspection/Certification for Fiberglass
Reinforced Plastic Building at O.N. Stevens Water Treatment Plant
3. COMPENSATION—The total amount not to exceed for Task Order No. 11 only is $7,090.
This Task Order is approved and Consultant may proceed. All other terms and conditions of the Agreement
remain in full force and effect.
7
CITY OF CORPU H- TI LNV, INC.
/ i4 z3 / 7 � � ,401
/APPA _ / ,i 3/317
J. H dmonds, P.E. Pat; Dan S.ey;!ker, P.E. Date
Director of Engineering Services Presid-
801 Navigation, Suite 300
Corpus Christi, TX 78408
(361)883-1984 Office
loganb@Invinc.com
Fund Name Accounting Unit Account No. Activity No. Amount
Water 2013 RVBD 4098-062 550950 E16264-01-4098-EXP $7,090
2017-118
3/23/17
LNV Inc.
INDEXED
City Project No. E16264
Professional Services Contract
City of Corpus Christi
WaterNVastewater Treatment On-Call Support
Task Authorization No. 11 — Foundation Design and Windstorm
Inspection/Certification for FRP Building at ONSWTP
February 24, 2017
"INV
Task Order No. 11
Exhibit A
Page 1 of 5
LJ ,
LW �
SCOPE OF WORK
Project No. E16264
Water and Wastewater Treatment On-Call Support
Task Authorization No. 11 -Foundation Design and Windstorm Inspection/Certification
for FRP Building at ONSWTP
PURPOSE
As the City continues to make improvements at ONSWTP and throughout the distribution system, many
plant process changes are being considered, including chemical usage, organics removal, and the
disinfection methods to be employed. To assist with the decision-making regarding the various process
changes under consideration, the City plans to install a pilot plant at ONSWTP, which would be used to
evaluate additional treatment methods to enhance the removal of natural organic matter to determine the
City's ability to permanently convert from chloramines to free chlorine as the distribution system
disinfectant. This pilot study would evaluate the use of granular activated carbon (GAC) and
nanofiltration as additional treatment methods. In addition, when considering long-term water treatment
processes or operations, this pilot plant would be capable of replicating the conditions at ONSWTP and
could be used to evaluate a wide variety of future changes and scenarios.
The pilot units were originally intended to be placed in an existing building. However, a new fiberglass
reinforced plastic (FRP) building will be installed at ONSWTP to contain all of the pilot plant
components. The state of Texas requires all structures to have a windstorm certification to mitigate losses
due to hurricanes along the Texas Gulf Coast.
The purpose of this task authorization is to assist the City by providing engineering design services for the
construction of the foundation for the FRP building along with windstorm inspection and certification to
ensure compliance with existing State laws.
SCOPE OF WORK
ADDITIONAL SERVICES:
ITEM 9 —General Engineering
The Engineer will perform the following:
1. Structural Engineering Design Services:
i. Review all existing available documentation such as sealed building drawings &
calculations,Geotechnical reports and/or any additional applicable documentation
pertinent to the project.
ii. Coordinate with the building manufacturer as required to ensure that the structural
design meets the requirements of the Fiberglass Building Manufacturer's design.
iii. Review design criteria, load requirements, anchor bolt size, spacing and layout
from the building manufacturer sealed drawings to ensure that the foundation and
anchor embedment design meets the requirements of the building design.
Task Order No. 11
1 Exhibit A
Page 2 of 5
f..
iv. Perform design of the structural foundation system such that all load requirements
are met.
v. Prepare drawings to include all plans, sections, details and notes required to
adequately depict the foundation work to be performed.
vi. Prepare all required technical specifications for the foundation system.
2. Windstorm Inspection and certification services:
i. Prepare and submit the WPI-1 form in accordance with the requirements of the
Texas Department of Insurance(TDI)for Windstorm for the project work.
ii. Review all necessary submittals required for the work, including but not limited
to;reinforcing shop drawings,anchor rods,concrete mix design,backfill materials,
steel shop drawings and all other project-specific items, to ensure conformance
with the sealed project Construction Documents and for compliance with TDI.
iii. Perform required inspections and prepare the required reports during the
construction phase to visually verify all work is constructed as designed and
detailed on the sealed Construction Documents.
iv. Prepare and submit WPI-2 form to the Texas Department of Insurance upon
completion of construction for the Client to receive the WPI-8 Windstorm
Certificate issued by TDI.
NOTE:The work performed under the task authorization does not include the following:
• Topographic surveying services
• Architectural services
• Bid phase and construction administration services other than windstorm
inspections.
DELIVERABLES
The Engineer will prepare a DRAFT set of construction plans and specifications for the foundation design
of the building. Upon receipt of comments, the Engineer will incorporate the necessary changes and
submit one (1) hard copy and one (1) electronic copy of the FINAL set of construction plans and
specifications,along with the necessary windstorm certification documents.
SCHEDULE
The Engineer's services shall be performed in a timely manner consistent with sound professional
practices. The Engineer will complete the work according to the following schedule:
Activity Completion Date
Contract Execution-Notice to Proceed(NTP) TBD
Item 9—General Engineering
• Draft submittal 10 days after NTP
• Final submittal 17 days after NTP
Task Order No. 11
Exhibit A
Page 3 of 5
. . .
LNV
The time limits set forth in the schedule shall include allowances for reasonable and expected review time
by the City and approval by authorities having jurisdiction over this project, and shall not be allowed as
cause for delay or adjustments to the schedule. Delays caused by review times by the City exceeding
those anticipated by the Engineer's schedule are cause for adjustments in the schedule. Any adjustments
made to the agreed upon schedule shall be made in writing and accepted by both parties.
The Engineer shall begin work immediately upon receipt of the executed Task Authorization and/or
Notice to Proceed(written or emailed).
FEE
The services will be provided on a Time and Materials (T&M) basis as the proiect is moved towards
completion.The anticipated amount for this task authorization is $7,090,as shown in ATTACHMENT A.
If the level of effort exceeds this estimate,a separate task authorization will be requested.
TASK AUTHORIZATION MANAGER
The Task Authorization Manager will be the primary contact person during the performance of this work.
All correspondence or inquiries should be addressed to the Task Authorization Manager. This work task
will be coordinated by:
Daniel Grimsbo, P.E.A.I.C.P.
Interim Assistant Director of Utilities Department
City of Corpus Christi
Office: 361-826-1874
Fax: 361-826-1889
Email: DanG@cctexas.com
APPROVAL
The undersigned has reviewed and approved this Task Authorization and recommends LNV, Inc. to
perform the work as presented:
Reco • ended by:
A /i l Ad
04A1 t mS 6 0 (Printed Name)
`l /c2 '//7 (Date) Task Order No. 11
Exhibit A
3 Page 4 of 5
Attachment A
Task Authorization No. 11
Man-hour and Fee Analysis
ITEM
LNV Inc.
Description
Principal/VP
Project Mgr.
Project Engineer
EIT IV
Sr. CADD/GIS Tech
Clerical
Expenses
TOTALS
$ 185.00
$ 155.00
$ 125.00
$ 115.00
$ 85.00
$ 60.00
v 1Hrs
ee
Hrs.
Sub -total
Hrs.
Subtotal
Hrs.
Sub -total
, -"'
s"
"�
-""��`"
""°"""`�"
�""`
9
General Engineenng,
a
912
11
1200
20
$
2,300
24
$ 2,040
2
$
120
$ 200.00
64
$ 7,090.00
Sub -totals
0
$-
6
$
930
12
$
1,500
20'',.�s_
Task Order No. 11
Exhibit A
Page 5 of 5
• •
EXHIBIT B
TASK ORDER SUMMARY
MASTER SERVICE AGREEMENT
WATER AND WASTEWATER ON-CALL SUPPORT
PROJECT NO. E16264
NOT TO
TASK EXCEED
DESCRIPTION AMOUNT AMOUNT
Original Contract(June 2, 2016) $35,000
Amendment No. 1 Master Service Agreement(August 16,2016) $600,000
Maximum Contract Amount $635,000
TASK ORDERS:
Task Order No. 1 $14,914
Greenwood Wastewater Treatment Plant Generator Sizing
Task Order No. 2 $14,575
Whitecap Wastewater Treatment Plant South Clarifier Scum System Rehab
Task Order No. 3 $24,350
Electrical Support for ONSWTP Intermediate Sludge Removal Phase 1
Task Order No.4 $167,588
Water System Operations Monitoring and Support
Task Order No. 5 $33,524
Public Communication on City-Wide Water Quality
Task Order No. 6 $21,373
Monthly Water Quality Mtgs and Alt ONSWTP Residuals Mgmt Evaluation
Task Order No. 7 $45,792
Implementation and Administration of General Engineering Services
Task Order No.8
TBD
Task Order No.9 $7,052
ONSWTP Facilities Optimization Plan Update
Task Order No. 10 $13,332
Distribution System Control Strategy
Task Order No.11 $7,090
Foundation Design&Windstorm Inspection/Certification for FRP Bldg at ONSWTP
Amount Remaining on Master Service Agreement $285,410