CITY OF CORPUS CHRISTI
AMENDMENT NO. 1
CONTRACT FOR PROFESSIONAL SERVICES
The City of Corpus Christi, Texas, a Texas home-rule municipal corporation("City")and LNV, Inc.("Consultant"),
agree to the following amendments to the Contract for Professional Services for Elevated Water Storage Tanks
Citywide (Alternative Capacity Requirement Implementation)(Prolect No. E16290):
Original Contract September 27, 2016 Motion No. M2016-126 , $672,034
In the Original Contract, Exhibit A, Section I. Scope of Services shall be amended as set forth in the attached
Amendment No.1, Exhibit A.
In the Original Contract,Section III. Fees shall be amended based on the modified scope of services in the attached
Amendment No. 1, Exhibit A for a fee not to exceed $18,500, for a total restated fee not to exceed $690,534.
All other terms and conditions of the September 27,2016 Contract for Professional Services between the City and
Consultant,and of any amendments to that contract,which are not specifically addressed herein shall remain in full
force and effect.
CITY 1 C• 'P •� RIS 1010.1•1
,//
'rte►: :___�
Val- -" H. Gray, '.E. or tI Date Dan , Rar�!e:'--cker, P.E. Date
Exec', ive Directo .f Pu•lic ork 17 President
801 Navigation, Suite 300
Corpus Christi, TX 78408
APPROVED AS TO LEGAL FORM (361)883-1984 Office
Aimee Alcorn Reed
06,0w, (361)883-1986 Fax
amyl 2017.03.2917:53:52-05'00' loganb@Invinc.com
Assistant City Attorney Date
ATTEST
ek). eiktt
City Secretary Date
Project Number E16290
Accounting Unit 4093-041
Account 550950
Activity E16290-01-4093EXP
Account Category 50950
Fund Name Water 2013 RVBD
2017-127
4/11/17 TER E16290 ELEVATED WATER STORAGE TANK PHASE 364 AMENDMENT NO 15CONTRACT DOC RFV 1011 15
LNV Inc. INDEXED
. : •
. .
LNV
Solutions Today with a
engineers architects f contractors Vision for Tomorrow
March 15, 2017
Mr. Jeff Edmonds, P.E.
Director of Capital Programs
City of Corpus Christi
P.O. Box 9277
Corpus Christi, Texas 78469-9277
RE: AMENDMENT NO. 1 TO PROFESSIONAL SERVICES CONTRACT
Elevated Water Storage Tanks -Citywide(ACR Implementation)
City Project E16290
Mr. Edmonds:
In response to the City's request, we are proposing Amendment No. 1 in the amount of $18,500 to
provide additional services for the Elevated Water Storage Tanks - Citywide (ACR Implementation)
project(E16290)for a total re-stated project fee of$690,534.
PROJECT BACKGROUND
On October 13, 2016, LNV received formal Notice to Proceed (NTP) letters for the Elevated Water
Storage Tanks - Citywide (ACR Implementation) project (E16290), which will provide the City with a
2.5 million gallon (MG) elevated storage tank (EST) at Starry Road and a 1.25 MG EST at Nueces
Bay Blvd., as outlined in the Alternative Capacity Requirement (ACR) Implementation Plan. This
project also includes the demolition of the four (4) existing ESTs in the City's Pressure Zone 1,
which have been identified as Morgan EST, Gollihar EST, Alameda EST, and Flour Bluff EST. The
original contract amount for the Basic and Additional Services associated with this project is
$672,034.
PURPOSE OF AMENDMENT NO. 1
The purpose of Amendment No. 1 is to provide assistance to the City by performing a modeling
evaluation of the manner in which the Flour Bluff area receives water from the mainland. Currently,
the following three (3)water lines are capable of providing water to the Flour Bluff area of the City:
• 8" line that runs north of South Padre Island Drive
• 30" line that runs along Holly Rd.
• 42" line that runs along Yorktown Blvd. (currently out of service)
Page 1 of 3 AMEND. NO. 1
801 NAVIGATION I SUITE 300 I CORPUS CHRISTI,TEXAS 78408 EXHIBIT A
OFFICE 361 883.1984 I FAX 361.883.1986 I WWW LNVINC.COM PAGE 1 OF 4
•
. r •
As a result of the current status of these lines to Flour Bluff, recent water quality challenges, and the
imminent installation of new ESTs under the original contract, the City has requested the use of
water modeling to achieve the following three(3)objectives:
1. Provide redundancy with respect to water delivery to the Flour Bluff area
2. Improve water quality in the Flour Bluff area
3. Determine the appropriate location for the Starry EST
SCOPE OF WORK
BASIC SERVICES(NIA)
ADDITIONAL SERVICES:
14.Water Modeling
An additional budget allowance of$18,500 has been requested under Amendment No. 1 to
provide water modeling support to the City to achieve its stated objectives. To perform this
service, the current City of Corpus Christi Hydraulic Model will be used, along with the pipe
and valve configuration data provided by the City. With this information and the current
model,the following scenarios will be evaluated:
• The delivery of water from the mainland with varying combinations of existing water
lines to Flour Bluff
• The delivery of water from the mainland with additional scenarios to include the
reduction of the existing 42" water transmission main by sliplining (maximum of two
(2) line sizes to be modeled)
NOTE: The proposed future EST configuration will be used for this analysis and will be
limited to a total of eight (8) scenarios. Each scenario will be evaluated for its impacts to
water system pressures and overall water quality.
At the conclusion of this water modeling effort, The ENGINEER will provide the City with a
DRAFT modeling report that describes the impacts of the various scenarios on the water
quality and system pressures throughout the City to aid the City staff in its decision-making
regarding changes to the water system. Upon receipt of comments from the City, the
ENGINEER will update and submit one (1) hard copy and one (1) electronic copy of the
FINAL modeling report for the City's use.
Page 2 of 3 AMEND. NO. 1
801 NAVIGATION I SUITE 300 I CORPUS CHRISTI,TEXAS 78408 EXHIBIT A
OFFICE 361.883.1984 I FAX 361.883 1986 I WWW.INVINC.COM PAGE 2 OF 4
SCHEDULE
All work under Amendment No. 1 of this contract shall be completed by the Engineer in accordance
with the schedule provided below.
Activity Completion Date
Basic Services (N/A)
Additional Services
14. Water Modeling
• DRAFT Modeling Report 14 days after NTP
• FINAL Modeling Report 21 days after NTP
FEES
A. Fees for Basic Services. Not applicable
B. Fees for Authorized Additional Services. The City will pay the ENGINEER the not-to-
exceed fee shown in "ATTACHMENT 1" for services specified in this amendment. The fee
will be full and total compensation for services and for all expenses incurred in performing
these services.
C. Summary of fees.
Refer to ATTACHMENT 1.
If you have any questions or if you would like to discuss in more detail, please feel free to call me at
361-883-1984.
Sincerely,
Logan Burton, P.E.
PrincipalNice President
LNV, Inc.
TBPE Firm No. F-366
Page 3 of 3 AMEND. NO. 1
801 NAVIGATION I SUITE 300 I CORPUS CHRISTI,TEXAS 78408 EXHIBIT A
OFFICE 361.883.1984 I FAX 361 883.1986 I WWW,LNVINC.COM PAGE 3 OF 4
ATTACHMENT 1 -SUMMARY FEE TABLE
TASK ORIGINAL CONTRACT AMENDMENT 1 TOTAL
BASIC SERVICES
1. Preliminary Phase $136,795 $0 $136,795
2. Design Phase $286,925 $0 $286,925
3. Bid Phase $11,378 $0 $11,378
4. Construction Administration Phase $118,992 $0 $118,992
Subtotal Basic Services $554,090 $0 $554,090
ADDITIONAL SERVICES(ALLOWANCE)
1. Permit Preparation $7,280 $0 $7,280
2. ROW Acquisition Survey $14,340 $0 $14,340
3. Topographic Survey and Parcel Descriptions $14,270 $0 $14,270
4. Environmental Issues $27,692 $0 $27,692
5. Public Involvement $0 $0 $0
6. Subsurface Utility Investigation $0 $0 $0
7. Construction Observation Services $0 $0 $0
8. Warranty Phase $6,983 $0 $6,983
9. Start-Up Services $13,096 $0 $13,096
10. Provide SCADA Documentation $5,880 $0 $5,880
11. Project Manual $0 $0 $0
12. O&M Manuals and Training $6,595 $0 $6,595
13. Process Automation System Development $21,808 $0 $21,808
14. Water Modeling $0 $18,500 $18,500
Subtotal Additional Services $117,944 $18,500 $136,444
TOTAL FEE $672,034 $18,500 $690,534
Council Approved on
9/27/2016 by Motion
No.M2016-126
AMENDMENT 1
ATTACHMENT 1
AMEND. NO. 1
EXHIBIT A
PAGE 4 OF 4