HomeMy WebLinkAboutC2017-349 - 6/9/2017 - NA TASK ORDER NO. 8
This Task Order pertains to a Master Services Agreement for Professional Services by and between City of Corpus
Christi, Texas (City) and LNV, Inc. (Consultant) dated August 16, 2016 (Agreement). Consultant shall perform
services on the project described below as provided in this Task Order and in the Agreement. This Task Order
shall not be binding until it has been properly signed by both parties. Upon execution, this Task Order shall
supplement the Agreement as it pertains to the project described below.
PROJECT NAME/NUMBER: Water and Wastewater Treatment On-Call Support, E16264
1. PROJECT DESCRIPTION–This project provides the Utility Department with on-call services to assist with
any technical,operational, maintenance,diagnostic and design concerns for the City's O.N.Stevens Water
Treatment Plant and six wastewater treatment plants.
2. SCOPE OF SERVICES–Planning Level Assessment of O.N.Stevens Water Treatment Plant Chlorine Gas
System
3. COMPENSATION –The total amount not to exceed for Task Order No 8 only is $61,380.
This Task Order is approved and Consultant may proceed All other terms and conditions of the Agreement
remain in full force and effect.
CITY OF fp •HRIS LNV, INC'
Air
'eforA.
�- a 7
, �7
J ff H. Edmonds, P.E at Dan S.—�r�'�r, P.E. Date
Director of Engineering Services President
801 Navigation, Suite 300
Corpus Christi, TX 78408
(361) 883-1984 Office
loganb@Invinc.com
Fund Name Accounting Unit Account No. Activity No. Amount
Water 2015 CIP 4096-062 550950 E16264-01-4096 EXP $61,380
2017-349
6/09/17
LNV Inc.
INDEXED
City Project No. E16264
Professional Services Contract
City of Corpus Christi
Water/Wastewater Treatment On-Call Support
Task Authorization No. 8 - Planning-level Assessment of
ONSWTP Chlorine Gas System
May 12, 2017
LNV
Task Order No. 8
Exhibit A
Page 1 of 6
Op,US c,,
LNVJh
SCOPE OF WORK
Project No. E16264
Water and Wastewater Treatment On-Call Support
Task Authorization No. 8- Planning-level Assessment of ONSWTP Chlorine Gas System
PURPOSE
The City of Corpus Christi operates one(1) water treatment plant, O.N. Stevens Water Treatment Plant
(ONSWTP), which has a rated capacity of 161.5 million gallons per day (MGD). Conventional water
treatment processes are employed to provide treated water to its residents, including coagulation,
flocculation, sedimentation, filtration, and disinfection. Currently, disinfection at ONSWTP is provided
by a chlorine gas system,along with I-ton chlorine cylinders that serve as a partial back-up.The chlorine
gas system converts liquid chlorine into gaseous chlorine and conveys it to various locations throughout
ONSWTP using carrier water.
The purpose of this task authorization is to provide assistance to the City staff by performing a planning-
level assessment of the existing chlorine gas system. This assessment would include a basic inventory of
the existing gas system, including components in the current gas measurement building, along with an
evaluation of the immediate needs for the gas system to ensure reliability and safety. Along with this
assessment, this task authorization also allows for the development of a long-term strategy to meet
anticipated future disinfection needs at ONSWTP by comparing various alternative disinfection strategies.
SCOPE OF WORK
ADDITIONAL SERVICES:
ITEM 2—Permitting and Regulatory
The Engineer will perform the following:
1. Compare the regulatory requirements for the implementation of existing chlorine
gas system improvements and the installation of new facilities and equipment.
2. Summarize the regulatory requirements tier the following alternative disinfection
technologies, which will be evaluated in the development of the long-term
disinfection strategy
• Gas Chlorine
• On-site chlorine generation
• Bulk sodium hypochlorite
• 1-ton chlorine cylinders(for back-up)
• Any combination of the previously-mentioned methods
Task Order No. 8
Exhibit A
Page 2 of 6
opus C•4
LNV •
ITEM 9—General Engineering
The Engineer will perform the following:
1. Conduct multiple site visits to develop a basic inventory of the components of the existing
chlorine gas system, along with vendor information, capacities, and their estimated
remaining useful service life
2. Determine the immediate needs of the existing chlorine gas system to address reliability,
redundancy,capacity,performance,and safety concerns by performing the following:
• Investigation of a back-up chlorine gas system to provide redundancy
• Evaluation of minor modifications to the existing gas measurement building to
address reliability or safety concerns
• Evaluation of bulk chlorine storage handling and facilities,including the rail
car delivery system
• Evaluation of existing chlorine gas equipment
3. Develop a long-term disinfection strategy for ONSWTP to meet anticipated future needs,
which would include the following:
• Determination of the disinfection requirements for the existing capacity of 161.5
MGD and anticipated future build-out capacity of ONSWTP, which is currently
estimated at 200 MGD
• Planning level evaluation of various disinfection technologies, including non-
economic advantages/disadvantages, estimated life-cycle costs, and regulatory
considerations
• Evaluation of potential, feasible back-up disinfection strategies for the existing
capacity of 161.5 MGD and future build-out capacity to provide redundancy, such
as a combination of on-site generation and the use of I-ton cylinders
• Selection workshop with City staff to review findings and choose long-term
disinfection strategy
• Development of an preliminary plan and schedule for the implementation of the
long-term disinfection strategy, including a phased approach to achieving effective
disinfection at future build-out capacity
4. Prepare a memorandum that provides the findings of the planning level assessment,
including a determination of the immediate needs of the gas system, and the long-term
disinfection strategy
5. Provide cost estimates, along with the preliminary plan and schedule, for the immediate
needs for the gas system and the long-term disinfection strategy that were identified
DELIVERABLES
The Engineer will prepare a DRAFT memorandum for the City's review and comment. Upon receipt of
comments, the Engineer will incorporate the comments and submit one (I) hard copy and one (I)
electronic copy of the FINAL memorandum.
Task Order No. 8
Exhibit A
Page 3 of 6
•
��US -'
4.
,0 P:
CNV • 4
+(34
SCHEDULE
The Engineer's services shall be performed in a timely manner consistent with sound professional
practices. The Engineer will complete the work according to the following schedule:
Activity Completion Date
Contract Execution-Notice to Proceed(NTP) TBD
Item 9-General Engineering
• DRAFT Memorandum 10 weeks after NTP
• FINAL Memorandum 12 weeks after NTP
The time limits set forth in the schedule shall include allowances for reasonable and expected review time
by the City and approval by authorities having jurisdiction over this project, and shall not be allowed as
cause for delay or adjustments to the schedule. Delays caused by review times by the City exceeding
those anticipated by the Engineer's schedule are cause for adjustments in the schedule. Any adjustments
made to the agreed upon schedule shall be made in writing and accepted by both parties.
The Engineer shall begin work immediately upon receipt of the executed Task Authorization and/or
Notice to Proceed(written or emailed).
FEE
The services will be provided on a Time and Materials (T&M) basis as the project is moved towards
completion.The anticipated amount for this task authorization is $61,380, as shown in ATTACHMENT
A. If the level of effort exceeds this estimate,a separate task authorization will be requested.
3 Task Order No. 8
Exhibit A
Page 4 of 6
. •
LNVv
TASK AUTHORIZATION MANAGER
The Task Authorization Manager will be the primary contact person during the performance of this work.
All correspondence or inquiries should be addressed to the Task Authorization Manager. This work task
will be coordinated by:
Daniel Grimsbo, P.E. A.I.C.P.
Interim Assistant Director of Utilities Department
City of Corpus Christi
Office: 361-826-1874
Fax: 361-826-1889
Email: DanGAcetexas.com
APPROVAL
The undersigned has reviewed and approved this Task Authorization and recommends LNV, Inc. to
perform the work as presented:
Re • nended by:
Oni,// /"ISLiC(Printed Name)
(Date)
4 Task Order No. 8
Exhibit A
Page 5 of 6
8 8 8 8 S
I
+I , 'o
d
O Fi N 0 : N
8 - co
O co
s z < '
a c $ 5
o
E. k m
�^ .� N W N N L L Q)
8 O IX Cn
m
Y •.• Q
a (n
c b CO
.- N I-
8
58r
CT
- 1 4 °
b .0 b •^
4. :.,.
. a. N N tN
fig_ _ s
H R = r: R m ^S
N
03 N N
o g
Q C Q = W b
4.. 0 W =-- g N
C 8
Cu O C
Q • O ;4_ .,, d N N
Y t
an
03 C Y 8 8-
1— R3 Inz „ e
yN
2 b
w g s g
x • ' x
S
$
a ~
F8
n m
o m o IT 2 mi«
13 .13
c. o = A m 0 .O
v u Cm in
¢ c z e
a m V 'm
AW
C c� W
✓ O C 7 O m 7
C - o, C C d
• C
Q . C
> 4- E tNNo fl E
E: c'; {� a `u
J O a i_ O a.-
N O. N 01
EXHIBIT B
TASK ORDER SUMMARY
MASTER SERVICE AGREEMENT
WATER AND WASTEWATER ON-CALL SUPPORT
PROJECT NO. E16264
TASK NOT TO
ORDER EXCEED
DESCRIPTION AMOUNT AMOUNT
Original Contract(June 2,2016) $35,000
Amendment No. 1 Master Service Agreement(August 16,2016) $600,000
Maximum Contract Amount $635,000
TASK ORDERS:
Task Order No. 1 $14,914
Greenwood Wastewater Treatment Plant Generator Sizing
Task Order No. 2 $14,575
Whitecap Wastewater Treatment Plant South Clarifier Scum System Rehab
Task Order No. 3 $24,350
Electrical Support for ONSWTP Intermediate Sludge Removal Phase 1
Task Order No.4 $167,588
Water System Operations Monitoring and Support
Task Order No. 5 $33,524
Public Communication on City-Wide Water Quality
Task Order No. 58 $10,996
Public Communication on City-Wide Water Quality
Task Order No. 6 $21,373
Monthly Water Qualify Mtgs and Alt ONSWTP Residuals Mgmt Evaluation
Task Order No. 7 $45,792
Implementation and Administration of General Engineering Services
Task Order No.S $61,380
Planning Level Assessment of ONSWTP Chlorine Gas System
Task Order No. 9 $7,052
ONSWTP Facilities Optimization Plan Update
Task Order No. 10 $13,332
Distribution System Control Strategy
Task Order No. 11 $7,090
Foundation Design&Windstorm Inspection/Certification for FRP Bldg at ONSWTP
Task Order Total $421,966
Amount Remaining on Contract $213,034