HomeMy WebLinkAboutM1988-0093 - 04/26/1988Motions - 4/26/88
1. Accepting the Allison Wastewater Treatment Plant Improvements completed by
Basic Constructors, Inc., authorizing Change Order No. 9 which provides for
a contract time extension of 122 days, an additional payment of $13,350 to
the contractors for delays; authorizing final payment to the contractor
except for $3,000 to be retained until pending items of work are completed;
and approving an amendment to the contract with Urban Engineering for
additional compensation of $58,811.
M88-0093