HomeMy WebLinkAboutC2017-564 - 11/28/2017 - NA CITY OF CORPUS CHRISTI AMENDMENT NO. 5 CONTRACT FOR PROFESSIONAL SERVICES The City of Corpus Christi, Texas, hereinafter called "CITY," and Freese and Nichols, Inc. hereinafter called "ENGINEER," agree to the following amendment to the Contract for Professional Services for South Staples Street from Brawner Parkway to Kostoryz Road (Bond 2012) (Project No. El 2095) as authorized and administratively amended by: Original Contract January 29, 2013 Motion No. M2013-017 $731,030.00 Amendment No. 1 July 11, 2014 Administrative Approval $49,537.00 Amendment No. 2 January 23, 2015 Administrative Approval $39,154.00 Amendment No. 3 April 25, 2016 Administrative Approval $37,454.00 Amendment No. 4 October 13, 2016 Administrative Approval $49,883.00 EXHIBIT A, SECTION 1. SCOPE OF SERVICES, PART A. BASIC SERVICES shall be modified as shown below. 2. Design Phase: "ENGINEER" will provide additional design services needed and more fully described in "Exhibit A". 3. Bid Phase: "ENGINEER" will provide bid phase services and more fully described in "Exhibit A". EXHIBIT A, SECTION 1. SCOPE OF SERVICES, PART B. ADDITIONAL SERVICES shall be modified as shown below. 10. Traffic Control: "ENGINEER" will provide traffic control plan and more fully described in "Exhibit A". EXHIBIT A, SECTION 3. FEES, PART B. SUMMARY OF FEES shall be modified by the attached Summary of Fees as shown in the attached Exhibit A for an additional fee not to exceed $42,769 for a total restated fee not to exceed $949,827. All other terms and conditions of the January 29, 2013 contract between the "CITY" and "ENGINEER" and of any amendments to that contract which are not specifically addressed herein shall remain in full force and effect. CITY OF CORPUS CHRISTI FREES AND NICHOLS, INC. '' "/?f/,7 _ 11/1/17 Margie C. Rose, Date Ron Guzman, P.E. Date City Manager Vice President/Principal 800 N. Shoreline Blvd., Suite 1600N Corpus Christi, Texas 78401 N7fSs 117 /� (361) 561-6500 Office ar Van Vleck, D to (361) 561-6501 Fax Assistant City Ma age I rg@freese.com II1 � 1 j� W . .td„, A7 vile e H. Gra , P. E., Date Ex—utive Dire ••r of 'ublic Works 2017-564 AMEND. NO. 5 11/28/17 Page 1 of 2 1\E12095 SOUTH STAPLES FROM BRAWNER TO KOSTORYZ BOND ISSUE 2012\CONSULTANT CONTRACT FREESE Freese and Nichols Inc. 12095 FREESE NICHOLS DOCX INDEXED de,e2t,21 Jeff H. Edmonds, P.E. D to Director of Engineering Services P ROV D AS TO LEGAL FORM 11/7/17 Legal Department Date ATTEST c A-fig, Reb cca Huerta, City Secretary South Staples Street from Brawner Parkway to Kostoryz Rd (Project No. El 2095) Freese and Nichols Amendment No. 5, $42,769 Not to Exceed $949,827 Fund Name Accounting Account Activity No. Account Amount Unit No. Category Street 2016 CO Bond 2012 3552-051 550950 E12095-01-3552-EXP 50950 $14,345.09 Storm Water 2015 Bond 4531-043 550950 E12095-01-4531-EXP 50950 3,563.02 Water 2013 Bond 2012 4094-041 550950 _ El2095-01-4094-EXP 50950 908.68 Wastewater 2013 Bond 2012 4253-042 550950 E12095-01-4253-EXP 50950 7,875.98 Gas 2015 Bond 4561-022 550950 E12095-01-4561-EXP 50950 16,076.23 Total $42,769.00 AMEND. NO. 5 Page 2 of 2 K.\ENGINEERING DATAEXCHANGEWELMAP STREET,E12095 SOUTH STAPLES FROM BRAWNER TO KOSTORYZ BOND ISSUE 20121CONSULTANT CONTRACT FREESE NICHOLSIAMENDMENT NO SWMENDMENT NO 5 E12095 FREESE NICHOLS DOCK FREESE Innovative approaches filINICHOLS Practical results Outstanding service 800 N.Shoreline Blvd.,Suite 1600N • Corpus Christi,Texas 78401 • 361-561-6500 • fax 361-561-6501 www.freese.com September 8, 2017 Mr.Jeff Edmonds, P.E. Director of Engineering Services City of Corpus Christi P. 0. Box 9277 Corpus Christi,Texas 78469-9277 Re: South Staples Street from Brawner Parkway to Kostoryz Road (Bond 2012) City Project No. E12095-Amendment#5 Dear Mr. Edmonds, At the request of your staff, Freese and Nichols, Inc. is pleased to submit our contract amendment#5 for South Staples Street from Brawner Parkway to Kostoryz Road. This amendment includes additional design effort for the following items: 1. Additional design of a 12"wastewater force main a. Item includes plan and profile design and replacement of approximately 500 linear feet of 12" C900 PVC wastewater force main. The City Utility Department requested that the wastewater force main be relocated to avoid having the force main located beneath the new curb and gutter of the redesigned roadway. 2. Additional design effort for the 6" high pressure gas line and 6"distribution gas line within the project limits. a. This item includes detailed design PS&E of approximately 4,900 linear feet of 6" high pressure gas line and approximately 800 liner feet of 6" polyethylene gas distribution line. These lines were initially planned to be replaced by City forces. As part of the project redesign, the City has requested that the contractor construct these lines as part of a new additive alternate bid. FNI will participate in three (3) additional meetings with the City and Gas Department to coordinate the construction of these lines. 3. Revised traffic control plan (TCP) and construction sequencing a. Item includes additional redesign and phasing of the traffic control plan sequencing and detailed traffic control design changes. The changes to the TCP were requested by the City to facilitate the City/contractor construction of the 6" high pressure gas line and 6" distribution gas line within the project limits and to minimize impacts to Ray High School. The TCP was redesigned and reconfigured to accommodate the gas line construction. The 6" high pressure line must be constructed in a continuous operation as there are no isolation valves within the project limits. AMEND. NO. 5 EXHIBIT "A" Page 1 of 2 4. Add Bid Phase Services. Amendment#4 previously deleted the Bid Phase Services. a. As part of the project redesign,Amendment#4 deleted the amount for bid phase services. This amendment proposes to add bid phase services back into the contract. Bid phase services will include the: i. Participate in the pre-bid conference and provide a meeting agenda for critical construction activities and elements impacted the project. ii. Assist the City in solicitation of bids by identification of prospective bidders,and review of bids by solicited interests. iii. Review all pre-bid questions and submissions concerning the bid documents and prepare,in the City's format,for the Engineering Services'approval,any addenda or other revisions necessary to inform contractors of approved changes prior to bidding. iv. Attend bid opening,analyze bids,evaluate, prepare bid tabulation,and make recommendation concerning award of the contract. v. In the event the lowest responsible bidder's bid exceeds the project budget as revised by the Engineering Services in accordance with the A/E's design phase estimate required above,the Engineer will,at its expense,confer with City staff and make such revisions to the bid documents as the City staff deems necessary to re-advertise that particular portion of the Project for bids. Freese and Nichols, Inc.respectfully requests a contract amendment in the amount of$42,769.00 to address the aforementioned items. Please feel free to contact me at 361.561.6500 should you have any questions regarding this matter. Respectfully, Ron Guz an, P.E. Principal/Vice President Enclosures AMEND. NO. 5 EXHIBIT"A" Page 2 of 2 Basic Services Fees Preliminary Phase Design Phase Bid Phase 1 2 3 4 Construction Administration Phase Subtotal Basic Services Fees Add tional Services Fees (Allowance) Permitting ROW Acquisition Survey Topographic Survey Environmental Issues Public Meetings Additional Public Outreach Subsurface Utility Investigation Construction Observation Services 1 2 3 4 5A 5B 6 7 8 Warranty Phase Signalization Improvements Traffic Control Subtotal Additional Services Fees Autho 9 10 Total Authorized Fee South Staples Street from Brawner Parkway to Kostoryz Road (Bond 2012) Project No. E12095 SUMMARY OF FEES Original Contract Street Wastewater Storm Water Water Gas MIS Total $32,813.10 $3,611.71 $16 734.62 $4,267.85 $325.17 $313.56 $58,066.00 142,612.59 15,697.23 72,732.17 18,548.97 1,413.26 1,362.78 252,367.00 6,986.33 768.98 3,563.02 908.68 69.23 66.76 12,363.00 35,140.74 3,867.91 17,921.72 4,570.60 348.24 335.80 62,185.00 217,552.76 23,945.82 110,951.52 28,296.10 2,155.89 2,078.90 384,981.00 14,131.46 1,555.44 7,207.02 1,838.01 140.04 135.04 25,007.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 39,366.56 4,333.04 20,076.88 5,120.23 390.11 376.18 69,663.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14,056.86 1,547.23 7,168.98 1,828.31 139.30 134.33 24,875.00 20,871.97 2 297.36 10,644.67 2,714.72 206.84 199.45 36,935.00 39,205.51 4,315.31 19,994.74 5,099.28 388.52 374.64 69,378.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,107.48 342.04 1,584.81 404.18 30.79 29.69 5,499.00 33,239.75 3,658.67 16,952.21 4,323.34 329.40 317.63 58,821.00 31,572.70 3,475.18 16,102.02 4,106.52 312.88 301.70 55,871.00 195,552.29 21,524.25 99,731.32 25,434.60 1,937.87 1,868.66 346,049.00 $413,105.05 $45,470.07 $210,682.85 $53,730.71 $4,093.77 $3,947.56 $731,030.00 01/29/13 Motion No. M2013 017 South Staples Street from Brawner Parkway to Kcstoryz Road (Bond 2012) Project No. E12095 SUMMARY OF FEES Basic Services Fees 1 Preliminary Phase Design Phase Bid Phase 2 3 4 Construction Administration Phase Subtotal Basic Services Fees Md tonal Services Fees (Allowance) Permitting ROW Acquisition Survey Topographic Survey Environmental Issues Public Meetings Additional Public Outreach Subsurface Utility Investigation 1 2 3 4 5A 5B 6 7 Construction Observation Services Warranty Phase Signalization Improvements Traffic Control Subtotal Additional Services Fees Auth 8 9 10 Total Authorized Fee Amendment No 1 Amd. No. 2 Amd. No. 3 Amd. No. 4 Street Storm Water Total Street Street Street $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 0.00 0.00 0.00 39,154.00 37,454.00 140,783.00 0.00 0.00 0.00 0.00 0.00 (12,363.00) 0.00 0.00 0.00 0.00 0.00 (62,185.00) 0.00 0.00 0.00 39,154.00 37,454.00 66,235.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 (1,465.00) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 (9,388.00) 0.00 0.00 0.00 0.00 0.00 0.00 7,432.00 42,105.00 49,537.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 (5499.00) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,432.00 42,105.00 49,537.00 0.00 0.00 (16,352.00) $7,432.00 $42,105.00 $49,537.00 $39,154.00 $37,454.00 $49,883.00 07/11/14 Admin. Approval 01/23/15 Ad. Approval 04/25/16 Ad. Approval 10/13/16 Ad. Approval ,,to X m (13=6 mWC 0 o Z AppO N South Staples Street from Brawner Parkway to Kostoryz Road (Bond 2012) Project No. E12095 SUMMARY OF FEES Basic Services Fees 1 Preliminary Phase Design Phase Bid Phase 2 3 4 Construction Administration Phase Subtotal Basic Services Fees Add tional Services Fees (Allowance) Permitting ROW Acquisition Survey Topographic Survey Environmental Issues Public Meetings Additional Public Outreach Subsurface Utility Investigation 1 2 3 4 5A 5B 6 7 Construction Observation Services 8 Warranty Phase Signalization Improvements Traffic Control Subtotal Additional Services Fees Authc 9 10 Total Authorized Fee Amd. No. 5 Street Wastewater Storm Water Water Gas Total $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 0.00 7,107.00 0.00 0.00 16,007.00 23,114.00 7,053.09 768.98 3,563.02 908.68 69.23 12,36100 0.00 0.00 0.00 0.00 0.00 0.00 7,053.09 7,875.98 3,563.02 908.68 16,076.23 35,477.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 7,292.00 0.00 0.00 0.00 0.00 7,292.00 7,292.00 0.00 0.00 0.00 0.00 7,292.00 $14,345.09 $7,875.98 $3,563.02 $908.68 $16,076.23 $42,769.00 Administrative Approval South Staples Street from Brawner Parkway to Kostoryz Road (Bond 2012) Project No. E12095 SUMMARY OF FEES Total Street Wastewater Storm Water Water Gas MIS Total Basic Services Fees 1 Preliminary Phase $32,813.10 $3,611.71 $16,734.62 $4,267.85 $325.17 $313.56 $58,066.00 2 Design Phase 360,003.59 22,804.23 72,732.17 18,548.97 17,420.26 1,362.78 492,872.00 3 Bid Phase 1,676.42 1,537.96 7,126.04 1,817.36 138.46 66.76 12,363.00 4 Construction Administration Phase (27,044.26) 3,867.91 17,921.72 4,570.60 348.24 335.80 0.00 Subtotal Basic Services Fees 367,448.85 31,821.80 114,514.54 29,204.78 18,232.12 2,078.90 563,301.00 Additional Services Fees (Allowance) 1 Permitting 14,131.46 1,555.44 7,207.02 1,838.01 140.04 135.04 25,007.00 2 ROW Acquisition Survey 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3 Topographic Survey 37,901.56 4,333.04 20,076.88 5,120.23 390.11 376.18 68,198.00 4 Environmental Issues 0.00 0.00 0.00 0.00 0.00 0.00 0.00 5A Public Meetings 4,668.86 1,547.23 7,168.98 1,828.31 139.30 134.33 15,487.00 5B Additional Public Outreach 20,871.97 2,297.36 10,644.67 2,714.72 206.84 199.45 36,935.00 6 Subsurface Utility Investigation 46,637.51 4,315.31 62,099.74 5,099.28 388.52 374.64 118,915.00 7 Construction Observation Services 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8 Warranty Phase (2,391.52) 342.04 1,584.81 404.18 30.79 29.69 0.00 9 Signalization Improvements 33,239.75 3,658.67 16,952.21 4,323.34 329.40 317.63 58,821.00 10 Traffic Control 38,864.70 3,475.18 16,102.02 4,106.52 312.88 301.70 63,163.00 Subtotal Additional Services Fees Autho 193,924.29 21,524.25 141,836.32 25,434.60 1,937.87 1,868.66 386,526.00 Total Authorized Fee $561,373.14 $53,346.05 $256,350.87 $54,639.39 $20,170.00 $3,947.56 $949,827.00