HomeMy WebLinkAboutC2019-027 - 1/24/2019 - NA TASK ORDER NO. 18
This Task Order pertains to a Master Services Agreement for Geotechnical and Construction Materials Testing by
and between City of Corpus Christi, Texas(City) and Tolunav-Wong Engineers, Inc., (Lab)dated January 16,
2018 by Motion No. M2018-005 (Agreement). Lab shall perform services on the project described below as
provided in this Task Order and in the Agreement. This Task Order shall not be binding until it has been properly
signed by both parties. Upon execution, this Task Order shall supplement the Agreement as it pertains to the
project described below.
MSA PROJECT NUMBER/NAME: 17101A Geotechnical and Construction Materials Testing
TASK ORDER PROJECT NUMBER/NAME: 17101S Geotechnical and Construction Materials Testing
1. PROJECT DESCRIPTION: #E17088 CCAD Industrial Security Enclave
2. SCOPE OF SERVICES—GeoTech and/or Construction Material Services to observe,test and report for the
CCAD Industrial Security Enclave project, and as more fully described in Exhibit A.
3. COMPENSATION—The total amount not to exceed for this Task Order only is$3,595.00.
This Task Order is approved, and Lab may proceed. All other terms and conditions of the Agreement remain in
full force and effect.
CITY OF CO' ' tS *RIST TOLUNAY-WONG ENGINEERS,INC.
i V/7 IL- ! 1 _ Z3 ,
Je H. Ed ,monds P.E. Don R. Rokohl, P. E. Date
Director of Engineering Services Branch Manager
826 South Padre Island Drive
Corpus Christi,TX 78416
(361)884-5050 Office
drokohl@tweinc.com
Project Number: El 7088
Accounting Unit: 1072-071
Account: 550920
Activity: E17088-01-1072-EXP
Account Category: 50920
Fund Name: ComDevelopmtGrt
Amount: $3,595.00
C2019-027
1/24/19
Tolunay-Wong Engineers Inc. Task Order#18
Testing Agreement
Page 1 of 2
2 m n
TASK ORDER FUNDING REQUEST FORM
CONTRACT MSA#AND TITLE: 17101A Geotechnical and Construction Materials Testing(TWE)
TASK ORDER PROJECT#/TITLE: 17101S Geotechnical and Construction Materials Testing(TWE)
REQUESTING DEPARTMENT: Engineering Services
FUND NAME/FUND#-ME: ACCOUNT: ACTIVITY:
1072-071 350920 E I 7088-01-1072-EXP
CONSULTANT:TOLUNAY-WONG ENGINEERING, INC.
TASK ORDER#: 18
SCOPE OF WORK:SEE PROPOSAL
TASK ORDER IS FOR PROJECT(S)LISTED BELOW:
PROJECT# FEE PROJECT NAME
E17088 53,595.00 E17088 CCAI Industrial Security Enclave Project
S3,595.00 Grand Total
LUIS VARGAS
PM PRINT NAME:
SI . fURE:
I/22/ 2019
DATE:
Task Order#18
Testing Agreement
Page 2 of 2
Tolunay-Wong 826 South Padre Island Drive
En ineers, Inc. Corpus Christi,Texas 78416
g Phone:(361)884-5050
January 16,2019
City of Corpus Christi
Engineering Services Department
P.O.Box 9277
Corpus Christi Texas 78469-9277
Attn: Mr. Luis Vargas EIT
Via e-Mail: LuisVa@CCTexas.com
Phone: (361)826-3528
Re: Construction Materials Testing Services For:
CCAD Industrial Security Enclave Project
Corpus Christi,Texas
Mr.Vargas:
Tolunay-Wong Engineers (TWE) appreciates the opportunity to submit our proposal to provide construction
materials testing and inspection services for the above referenced project. The proposed scope of services was
based on the testing schedule and the project plans downloaded from the CivCast website.
The cost estimate contained herein was developed using the scope of services from the drawings and specification
and the unit rates presented in the Master Service Agreement (Project No. 17101A) between the City of Corpus
Christi and Tolunay-Wong Engineers, Inc. We understand that the City will issue a Project Task Order upon
acceptance of this proposal in accordance with the MSA and the Task order will serve as our authorization to
proceed with our services for the project.
Tolunay-Wong Engineers has established a reputation for excellence in the materials engineering field through a
business philosophy based on quality professional services responsive to the needs of our clients. We thank you
for the opportunity to serve you with this philosophy and your consideration for this project. Please do not
hesitate to contact us, if you have any questions regarding the proposal or if additional information is needed.
Respectfully submitted,
Tolunay-Wong Engineers,Inc.
/2-1e4-4
Rene Farias Don R. Rokohl, P.E.
CMT Project Manager Branch Manager
rfarias@tweinc.com drokohk tweinc.com
RF/DRR/rf
Exhibit A
Page 1 of 4
Geotechnical Engineering*Environmental Field and Consulting Services*Construction Materials Testing*Deep Foundations Testing
•
Tolunav-Wong January 16,2019
Engineers. Inc. Proposal No.P19-0006
Page 2 of 4
INTRODUCTION
TWE understands the importance of this project to you and the special needs associated with construction of
a project of this type. Of particular importance is for the overall project team to be comprised of experienced
professionals working together toward a common objective. This objective is to obtain a quality project,
meeting the intent of the project specifications,as well as completion on schedule and within budget.
From our Corpus Christi facility located at 826 South Padre Island Drive, we will provide experienced
engineering technicians to perform the on-site testing and inspection services. Additionally, we meet the
requirements of ASTM E-329 "Standard Practice for Inspection and Testing Agencies for Concrete, Steel and
Bituminous Materials Used in Construction" regarding qualifications of the testing laboratory. Additionally,
our Corpus Christi laboratory is accredited in construction materials testing by the American Association for
Laboratory Accreditation (A2LA).
WORK PLAN
TWE's approach to providing materials testing services is to assign qualified engineering technicians, directed
by Senior Professional Engineers, experienced in their respective disciplines. Our assigned Project Manager
will provide communication, service direction, and overall project coordination. It is presumed that the
contractor will be encouraged to provide their own formalized quality control program separate and apart
from our acceptance inspection/testing program stated herein.
We anticipate providing the majority of the required testing services for this particular project on a "part-
time"basis.The anticipated services required on this project are as follows:
A. Cast In-Place Concrete Inspection/Testing
B. Hot Mix Asphalt Concrete Inspection/Testing
All reports of materials tests and inspection services provided will be issued to appropriate members of the
project team. In the event individual reports indicate potential problems or items of non-conformance to the
project specifications,you will be contacted as soon as possible.
SCOPE OF SERVICES
The specific materials monitoring services and laboratory tests anticipated for this project are as follows:.
A. Cast In-Place Concrete Monitoring/Testing
• The technician will sample the concrete in order to perform standard field tests and prepare
test cylinders in accordance with project specifications. The frequency of sampling will also be
as directed by the project specifications. Standard field tests include slump, air content and
temperature for normal weight concrete and will also include unit weight on all samples of
lightweight concrete.
• TWE will cure the test specimens and perform compressive strength tests at the age
designated by project specifications.
• The technician will visually estimate the slump of each load of concrete delivered and perform
actual slump tests and other standard field tests when test specimens are prepared, or as
necessary to evaluate concrete consistency.
• The on-site technician will monitor the concrete temperature, ambient temperature, mixing
time, and placement procedures. The technician will also sample concrete at the frequency
specified in the project specifications.
Exhibit A
Geotechnical Engineering*Environmental Field and Consulting Services*Construction Materials Testing*Deep Foundations Testing Page 2 of 4
•
1,10 Tolunay-Wong January 16,2019
Engineers. Inc. Proposal No
Page 3 of
9
• The technician will record detailed information regarding the location of the placement, date
of the placement,concrete mixture strength requirement and all other pertinent information.
B. Hot Mix Asphalt Concrete Inspection/Testing
• During lay down of hot mix asphalt concrete, the technician will obtain and record
temperature of the mixture and obtain samples for laboratory testing.
• After lay down and compaction, the asphalt will be cored to determine and record in-place
thickness,%air voids, and laboratory density. The in-place%air voids and in-place theoretical
density will be determined from the asphalt cores in the laboratory.
• The asphalt samples obtained during lay down will tested in the laboratory for extraction and
gradation,laboratory density and stability,and maximum theoretical density(rice method).
COST ESTIMATE &GENERAL NOTES
In this section of the proposal you will find our cost estimate. Additional services or tests requested and
not specifically addressed in this proposal will be invoiced per the Master Service Agreement(Project No.
17101A) between the City of Corpus Christi and Tolunay-Wong Engineers, Inc.
Based on the testing schedule, the project bid documents (plans/Specifications) provided to us at this
time,and the anticipated construction schedule,we have established what we believe is the most realistic
cost estimate for this project. Please remember that the units stated are only an estimate. Due to factors
beyond our control such as weather, unforeseen conditions, contractor expertise, contractor scheduling,
etc.,the cost of our services may vary from the estimated amount.
We estimate the cost of the construction materials testing for our proposed Scope of Services will be
$3,595.00 as detailed in the following section, although all services will be invoiced on a time and
materials basis.
A minimum 4-hour labor equivalent charge is applicable for all field testing and inspection services.
Overtime rates for field personnel are applicable for all hours worked in excess of 8 hours per day,
weekends, and holidays and are assessed at 1.5 times the standard rates. All field hours will be charged
portal to portal from our Corpus Christi laboratory. All sample pick-ups will be charged travel time from
portal to portal and will include associated vehicle charges.Administrative costs, Engineering consultation
and evaluation in connection with field and laboratory testing services will be charged at a rate of
approximately one hour for each 20 hours of field work performed.
Our prices include copies of our reports distributed through e-mail in accordance with your instructions.
Additional copies mailed at $0.50 per page. Direct expenses incurred in connection with the project will
be invoiced at cost plus 15%for handling. Travel and lodging expenses for out of town assignments will
be invoiced at cost plus 15% or$125.00 per day, whichever is greater. Our terms are net 30 days upon
receipt of invoice. Invoices will be submitted on a monthly basis.
Exhibit A
Geotechnical Engineering*Environmental Field and Consulting Services*Construction Materials Testing*Deep Foundations Testing Page 3 of 4
10 Tolunav-Wong January 16,2019
Proposal No.
Engineers, Inc. Page 4 of
9
COST ESTIMATE SUMMARY
Description Unit Quantity Rate Extension
Hot Mix Asphalt Concrete Inspection/Testing
1 Construction Materials Technician, HR. ea. 4 $55.00 $220.00
2 Asphalt Coring(minimum) ea. 1 $375.00 $375.00
3 Core Thickness ea. 1 $20.00 $20.00
4 Core Bulk Density(ASTM D 2726) ea. 1 $55.00 $55.00
5 Extraction/Gradation-Ignition Method ea. 1 $225.00 $225.00
6 Theoretical Density Rice Method ea. 1 $75.00 $75.00
7 Hveem Stability(ASTM D1560) ea. 1 $95.00 $95.00
8 Vehicle Charge ea. 1 $75.00 $75.00
9 Sample Pick-up ea. 1 $150.00 $150.00
Concrete Testing
10 Construction Materials Technician, HR. ea. 12 $55.00 $660.00
11 Compressive Strength of Concrete Cylinders ea. 10 $20.00 $200.00
12 Flexural Strength of Concrete Beams ea. 3 $50.00 $150.00
13 Vehicle Charge ea. 3 $75.00 $225.00
14 Sample Pick-up ea. 3 $150.00 $450.00
Project Management
15 Project Manager, Hr. ea. 4 $105.00 $420.00
16 Administrative Support, Hr. ea. 4 $50.00 $200.00
Total Cost Estimate $3,595.00
ASSUMPTIONS: The cost estimate is based on the following assumptions and our experience on similar projects:
1. The project bid documents and testing schedule provided by the Client and downloaded from the CivCast
website.
2. Concrete sample pick-up charges will not be assessed if retrieval of concrete test specimens occurs during
performance of other scheduled testing at the site.
3. Concrete compressive strength samples taken will consist of five (5) 4"x8" cylinders to be tested as
follows:one(1)at 7 day's compressive strength,three(3)at 28 day's compressive strength,and one(1)to
be held as a reserve.
4. Concrete flexural strength beam samples taken will consist of three to be tested as follows: one(1) at 7
days flexural strength,one(1)at 28 days flexural strength,and one(1)to be held as a reserve.