HomeMy WebLinkAboutC2019-044 - 2/11/2019 - NA CITY OF CORPUS CHRISTI
AMENDMENT NO. 1
CONTRACT FOR PROFESSIONAL SERVICES
The City of Corpus Christi,Texas, a Texas home-rule municipal corporation ("City")and Freese and Nichols,Inc.
("Consultant"), agree to the following amendments to the Contract for Professional Services for Everhart Road
from SPID to Holly Road (Project No. 18014A):
Original Contract June 12, 2018 Resolution No. 031445 $823,700.00
In the Original Contract, Exhibit "A", Section I. Scope of Services shall be amended as set forth in the attached
Amendment No. 1, Exhibit"A".
In the Original Contract,Article III Compensation shall be amended based on the modified scope of services in the
attached Amendment No. 1, Exhibit"A"for a fee not to exceed $49,969.00, for a total restated fee not to exceed
$873,669.00.
All other terms and conditions of the June 12, 2018 Contract for Professional Services between the City and
Consultant,and of any amendments to that contract,which are not specifically addressed herein shall remain in full
force and effect.
CITY OF CORPU HRISTI FREESE AND NICHOLS, INC.
'x'11' °( (, "
.,/,-,/./.1„, ./ �.// 2/6/2019
Keith Selma Bat- Ron Guzman, P.E. Date
Interim City Manager PrincipalNice President
800 N. Shoreline Blvd., Suite 1600N
14/e /. 9.4* Corpus Christi, TX 78401
2/0/1 (361) 561-6500
Mark Van Vleck, rg@freese.com
Assistant City -na•er
`)V elk (c
Val- H. Gra , P. uat-
Exe - ive Dire. . :,illif
,
001
1 /
Jeff . Edmonds, P. E., +a -
Director of Engineering Services
AppRCv"n AS Tn LEGAL FORM
��/( jj 2019.02.0616:38:51
-06'00'
Assistant City Attorney Date
s i
id - ,. _ Lt i
C2019-044 /l 3/19
2/11/19 Date
Freese and Nichols Inc.
ANNED
Project No. 18014A
Accounting Unit 4096-041
Account 550950
Activity 18014-A-4096-EXP
Account Category 50950
Fund Name Water 2015 CIP
Innovative approaches
rilfREESE zNICHOLS Practical results
4 Outstacndinggservice
800 N.Shoreline Blvd.,Suite 1600N • Corpus Christi,Texas 78401 • 361-561-6500 • fax 361-561-6501 www.freese.com
January 28, 2019
Mr.Jeff Edmonds, P.E.
Director of Engineering Services
City of Corpus Christi
P.O. Box 9277
Corpus Christi,TX 78469
RE: Everhart Road—Holly Road to South Padre Island Drive -Amendment No. 1
City Project No. 18014A
Dear Mr. Edmonds,
Freese and Nichols, Inc. (FNI) is pleased to submit an amendment to our professional services contract to
provide additional design phase services for the Everhart Road—Holly Road to South Padre Island Drive, City
Project 18014A for your consideration. This amendment includes design services to replace an existing 36"
water transmission line throughout the project limit. This amendment will include the following services:
Design Phase
1. Prepare design plans, specifications, and estimates (PS&E)for a 36"water transmission line on
Everhart Road to replace an existing 36"water transmission line installed in 1961. Prepare design to
replace two existing 36"valves and water vaults at the intersections of SPID and Holly Road. Include
necessary tie-in details to the City existing water system. Prepare necessary design modifications to
other utility lines including water,wastewater, stormwater and gas on Everhart Road to
accommodate the new 36"water transmission line. Incorporate the design of the 36"water
transmission line into the pre-final (100%) plans(unsealed and unstamped)for City's final review.
Participate in three (3)additional meetings with the City for design of the 36"water line
improvements.
Project Assumptions:
a. City will conduct all applicable testing of the existing 36"water line. City has determined that it is
acceptable to shut down the existing 36" line and replace the line in the same alignment.
b. City will provide all water modeling of the existing and proposed water system.
Fee Summary
Basic Services Fees
1. Design Phase $49,969.00
Total Authorized Fee $49,969.00
AMEND. NO. 1
Exhibit "A"
Page 1 of 2
Freese and Nichols, Inc. respectfully requests a lump sum fee in the amount of$49,969.00 to perform
these services.
Please feel free to contact me at 361.561.6500 should you have any questions regarding this matter.
Sincerely,
72 (2)
Ron Guzman, P.E.
Vice President/Principal
Enclosures
AMEND. NO. 1
Exhibit"A"
Page 2 of 2
Everhart Road from SPID to Holly Road
Project No. 18014A
Summary of Fees
Original Contract Amendment No. 1 Total
Basic Services
1 Preliminary Phase $106,851.00 $0.00 $106,851.00
2 Design Phase 387,114.00 49,969.00 437,083.00
3 Bid Phase 17,770.00 0.00 17,770.00
4 Construction Administration Phase 50,000.00 0.00 50,000.00
(Time and Materials)
Subtotal Basic Services 561,735.00 49,969.00 611,704.00
Additional Services
1 Permit Preparation 12,527.00 0.00 12,527.00
2 Topographic Survey 53,763.00 0.00 53,763.00
3 ROW Acquistion Survey 17,315.00 0.00 17,315.00
4 Environmental Issues TBD 0.00 0.00
5 Public Meetings 15,874.00 0.00 15,874.00
6 Construction Observation Services TBD 0.00 0.00
7 Traffic Control 98,507.00 0.00 98,507.00
8 Signalization Improvements 57,096.00 0.00 57,096.00
9 Warranty Phase 6,883.00 0.00 6,883.00
Subtotal Additional Services 261,965.00 0.00 261,965.00
Total Authorized Fee $823,700.00 $49,969.00 $873,669.00