HomeMy WebLinkAboutC2019-108 - 3/20/2019 - NA TASK ORDER NO. 42
This Task Order pertains to a Master Services Agreement for Professional Services by and between City of Corpus
Christi, Texas (City) and LNV, Inc. (Consultant) dated August 16, 2016 (Agreement). Consultant shall perform
services on the project described below as provided in this Task Order and in the Agreement. This Task Order
shall not be binding until it has been properly signed by both parties. Upon execution, this Task Order shall
supplement the Agreement as it pertains to the project described below.
PROJECT NAME/NUMBER: Water and Wastewater Treatment On-Call Support, E16264
1. PROJECT DESCRIPTION—This project provides the Utility Department with on-call services to assist with
any technical,operational, maintenance,diagnostic and design concerns for the City's O.N.Stevens Water
Treatment Plant and six wastewater treatment plants.
2. SCOPE OF SERVICES —ONSWTP Effluent Filter Piping Assessment, more fully described in Exhibit A.
3. COMPENSATION —The total amount not to exceed for Task Order No. 42 only is $7,076.00.
This Task Order is approved, and Consultant may proceed. All other terms and conditions of the Agreement
remain in full force and effect.
CITY OF C• 11P RIST LNV, INC.
1" 2# F 3/14 Jtq
•eff H. Edmonds, P.E. •ate .�orDa . Leyendecker, P.E. Date
Director of Engineering Services President
801 Navigation, Suite 300
Corpus Christi, TX 78408
(361) 883-1984 Office
loganb@Invinc.com
Fund Name Accounting Unit Account No. Activity No. Amount
Water Operating Fund 4010-31010-062 530000 E16264-01-4010-EXP $7,076.00
C2019-108
3/20/19
LNV Inc. Task Order No. 42
Page 1 of 1
S1ANNFfl
Professional Services Contract
City of Corpus Christi
Water/Wastewater Treatment On-Call Support
City Project No. E16264
Task Authorization No. 42 — ONSWTP Effluent Filter Piping
Assessment
March 14, 2019
UMV
EXHIBIT A
Page 1 of 4
SCOPE OF WORK
Water and Wastewater Treatment On-Call Support
Project No. E16264
Task Authorization No. 42— ONSWTP Effluent Filter Piping Assessment
PURPOSE
The ON Stevens WTP uses sand and anthracite filters in both Plant 1 and Plant 2. Filtered Water
from Filters in both the North and South Buildings flows through a 20-inch pipe from each filter
unit to a closed filtered water flume. Corrosion has been recently observed at locations where the
20-inch pipe passes through concrete to convey water to the filtered water flume. The condition
of 20-inch pipes inside the flume cannot be observed, which is also suspected to be corroded.
The purpose of this task authorization is to provide assistance to the City by performing an
assessment of these 20-inch pipes. Under this task authorization, visual and ultrasonic testing
(to be performed by HOT Inspection Services, Inc.) of pipes will be performed to define the
condition of pipe walls. In this phase of the task, power tool cleaning and minimal destructive
testing may be necessary. A total of 4 pipes will be evaluated representing approximately 20% of
the 22 pipes present, two (2) from each Filter location (North and South). A report (produced by
HOT Inspection Services, Inc.) will be issued to the City detailing the results of testing and
recommending for remedial measures needed in order to resolve the issues.
Based on the findings of the assessment, the City will make decisions regarding the future course
of action and a separate task authorization may be issued for the implementation of selected
remedial measures.
SCOPE OF WORK
ADDITIONAL SERVICES:
ITEM 9—General Engineering
Task 0001 —ONS WTP Effluent Filter Piping Inspection
The Engineer will perform the following:
i. Review record information for filter piping
ii. Coordinate and conduct one(1) site visit for visual inspection
iii. Coordinate and conduct one (1) site visit for ultrasonic testing for a total of 4 pipes,2
in each filter building
iv. Prepare/submit report to the City that will provide the following information:
• Findings of visual assessment and ultrasonic testing
• Remedial measures
Note: The report to be provided will be prepared by HOT Inspection Services, Inc. with Quality
Assurance/Quality Control (QA/QC)review and coordination with the City by LNV.
1 of 3
EXHIBIT A
Page 2 of 4
DELIVERABLES
A report produced by HOT Inspection Services, Inc. will be issued to the City detailing the
results of testing and recommendation for remedial measures needed in order to resolve the
issues.
SCHEDULE
The Engineer's services shall be performed in a timely manner consistent with sound
professional practices. The Engineer will complete the work according to the following
schedule:
Activity Completion Date
Contract Execution -Notice to Proceed (NTP) TBD
Task 0001 — ONS WTP Effluent Filter Piping
Inspection
- Review Record Information 1 week after NTP
- Visual Inspection Site Visit 1 weeks after NTP
- Ultrasonic Testing 3 weeks after NTP
- Final Report 4 weeks after NTP
The time limits set forth in the schedule shall include allowances for reasonable and expected
review time by the City and approval by authorities having jurisdiction over this project, and
shall not be allowed as cause for delay or adjustments to the schedule. Delays caused by review
times by the City exceeding those anticipated by the Engineer's schedule are cause for
adjustments in the schedule. Any adjustments made to the agreed upon schedule shall be made
in writing and accepted by both parties.
The Engineer shall begin work immediately upon receipt of the executed Task Authorization
and/or Notice to Proceed (written or emailed).
FEE
The services for all tasks listed under this task authorization will be provided on a Time and
Materials (T&M) basis. The anticipated amount for this task authorization is $7,076.00, as
shown in ATTACHMENT A. The Engineer will not incur cost in excess of this not-to-exceed
amount without prior written authorization from the City.
2 of 3
EXHIBIT A
Page 3 of 4
TASK AUTHORIZATION MANAGER
The Task Authorization Manager will be the primary contact person during the performance of
this work. All correspondence or inquiries should be addressed to the Task Authorization
Manager. This work task will be coordinated by:
Alex Barabanov, P.E.
Senior Project Manager
City of Corpus Christi
Office: 361-826-1873
Email: AlexBa@cctexas.com