AMENDMENT NO. 2
CONTRACT FOR PROFESSIONAL SERVICES
The City of Corpus Christi, Texas, hereinafter called "CITY," and Martinez, Guy & Mavbik, Inc.,
hereinafter called "ENGINEER," agree to the following amendment to the Contract for Professional
Services for Community Park Development and Improvements — Bill Witt Park (Bond 20121
(Project No. E14002, Parent Project E121151 as authorized and administratively amended by:
Original Contract April 23, 2013 Motion No. M2013-073 $156,780.00
Amendment No. 1 December 17, 2015 Administrative Approval $25,000.00
In the Original Contract, Exhibit A, Scope of Services shall be amended as set forth in the attached
Amendment No. 2, Exhibit A.
In the Original Contract, Exhibit A, Fees shall be amended based on the modified scope of services in
the attached Amendment No. 2, Exhibit A for a fee not to exceed $6,560.00, for a total restated fee not
to exceed$188,340.00.
All other terms and conditions of April 23, 2013 Contract for Professional Services between the City
and Consultant, and of any amendments to that contract, which are not specifically addressed herein
shall remain in full force and effect.
C •F $ ' - C TI M' -TINEZ GUY& A BIK, INC
3(.. •
V:lerie H. Gr-y, P.E. Date icardo Martinez, r ' ma e
E e tive Direlstor Fo Public •rks President
6000 S. Staples S . a 207
RECOMMENDS Corpus Christi, TX 78413
q / (361) 814-3070 Office
7 I rmartinez@mgm-inc.com
Becky Perrin Date
Interim Director of Parks and Recreation
APPROVED AS TO LEGAL FORM
2019.03.25 10:30:58
-05'00'
Assistant City Attorney Date
TES
ity Secretary
Amendment No.2
Contract for Professional Services
C2019-189 Page 1 of 2
3/29/19
Martinez, Guy & Maybik Inc.
SCANNF
Accounting Unit: 3293-141
Account: 550950
Activity: E14002-01-3293-EXP
Account Category: 50950
Fund Name: PK&RC2013GOBD12
Amount: $6,560.00
Amendment No.2
Contract for Professional Services
Page 2 of 2
•
MARTINEZ, GUY
& MAYBIK, INC.
February 28, 2019 ENGINEERS&SURVEYORS
Ms.Sarah West P.E. 6000 S.Staples,Suite 207
CorpusChristi,
City of Corpus Christi-Major Projects Engineer Texas78413
Offficee33661..8814.3070
1201 Leopard Street
Corpus Christi,Texas 78469 Offices in Houston&Corpus Christi
RE: Community Park Development & Improvements Bill Witt Park(Bond 2012), Project No.
E14002—Contract Amendment No. 2 Proposal
Dear Ms. West:
MGM Inc. was informed by the City's construction department on 12/28/2018 in regards to the
installation of the new grates at parking lot #2 (adjacent to the existing kickball field). Upon
MGM Inc.'s field visit it was noted that the edge of parking lot #2 was shifted closer to the
drainage swale, and was also built up to a higher elevation that was not per the design
elevations of the construction plans. As a result the alterations to parking lot#2 have created a
construction issue with the drainage design and will now require the installation of concrete
retaining walls at the grate inlet areas to retain the steep edges of the built up parking lot in
lieu of sloping the grade into the proposed swale as shown in the original construction plans.
Since parking lot #2 has changed in dimensions and vertical elevation MGM Inc. will now need
to survey the full length of the drainage area at parking lot #2. MGM Inc. will also be providing
engineering services and new construction plans for the required concrete retaining walls.
COMPENSATION
MGM proposes to perform continued construction phase services for the aforementioned
project for a total fixed fee of SIX THOUSAND FIVE HUNDRED AND SIXTY DOLLARS AND ZERO
CENTS ($6,560.00).
1. Surveying Services $ 2,260.00
2. Engineering Services $ 950.00
3. Provide Revised Plans & Retaining Wall Plans/Details $ 2,550.00
4. Additional Project Management Services and
Construction Administration Services $ 800.00
February 28, 2019 1
Community Park Development& Improvements Bill Witt Park(Bond 2012), Project No. E14002
City of Corpus Christi
Exhibit A
Page 1 of 3
Said fee shall be paid as follows:monthly payments based on the progress of services
rendered.
Any Additional Services performed hourly by MGM and as authorized by the Client, would be
charged according to the following rates: Project Management/Engineering at $135/hour;
Windstorm Engineer at $130/hour; and Administration Assistance at $55/hour.
Summary of Fees
Basic Services Fees Original Amendment Amendment
Contract No. 1 No. 2
1. Preliminary Phase $22,840.00 $0.00 $0.00
2. Design Phase $69,800.00 $30,370.00 $5,760.00
3. Bid Phase $6,620.00 $0.00 $0.00
4. Construction Administration Phase $15,680.00 $0.00 $800.00
Subtotal Basic Services Fees $114,940.00 $30,370.00 $6,560.00
Additional Services Fees
1. Permit Preparation To Be $0.00 $0.00
Determined
2. ROW Acquisition Survey None $0.00 $0.00
Anticipated
3. Topographic Survey $27,680.00 $0.00 $0.00
4. Environmental Issues $1,920.00 ($1,920.00) $0.00
5. Public Involvement $4,600.00 ($3,450.00) $0.00
6. Subsurface Utility Investigation $5,240.00 $0.00 $0.00
7. Construction Observation Services To Be $0.00 $0.00
Determined
8. Start-up Services Not Applicable $0.00 $0.00
9. Warranty Phase $2,400.00 $0.00 $0.00
Sub-Total Additional Services Fees Authorized $41,840.00 ($5,370.00) $0.00
Total Authorized Fee $156,780.00 $25,000.00 $6,560.00
Approved Approved Pending
Approval from
Approved By: City
February 28, 2019 2
Community Park Development& Improvements Bill Witt Park (Bond 2012), Project No. E14002
City of Corpus Christi
Exhibit A
Page 2 of 3
Sincerely,
MARNEZ, GUY & MAYB K, INC.
Richard Martinez, E.
President
Accepted by CITY OF CORPUS CHRISTI (CLIENT)
Accepted this day of February 2019,
By:
Authorized Signature
Printed Name &Title
•
February 28, 2019 3
Community Park Development&Improvements Bill Witt Park(Bond 2012), Project No. E14002
City of Corpus Christi
Exhibit A