AMENDMENT NO. 1 to the
CONTRACT FOR PROFESSIONAL SERVICES
The City of Corpus Christi, Texas, a Texas home-rule municipal corporation ("City") and Urban Engineering
("Consultant"), agree to the following amendments to the Contract for Professional Services for Kinney& Power
Street Pump Station Improvements (Project No. E16320):
Original Contract September 11, 2018 Motion No. M2018-159 $162,527.00
Exhibit A, Scope of Services shall be amended as set forth in the attached Amendment No.1, Exhibit A.
Exhibit A, Fees shall be amended based on the modified scope of services in the attached Amendment No. 1,
Exhibit A for a fee not to exceed $0.00, for a total restated fee not to exceed $162,527.00.
All other terms and conditions of the September 11,2018 Contract for Professional Services between the City and
Consultant, and of any amendments to that contract,which are not specifically addressed herein shall remain in full
force and effect.
CITY OF CORPUS C 4-r011" URBAN ENGINEERING
' 3 Z41 l7 Mar 28, 2019
do(ker 28,2019
Jeff H. dmonds, P.E. D to James L. Urban, P.E. Date
Director of Engineering Services Principal
2725 Swantner
Corpus Christi, TX 78404
(361) 884-3101 Office
(361) 854-6001 Fax
jimu@urbaneng.com
markm@urbaneng.cam
APPROVED AS TO LEGAL FORM
� )® 2019.03.28 15:26:56
-05'00'
Assistant City Attorney Date
ATTEST
C'u twt?, 3/a/17
Re cca Huerta Date
City Secretary
K:\ENGINEERING DATAEXCHANGE\CLARISSAJ\SEAWALL-TYPE A1E16320-KINNEY ST AND POWER ST PUMP STATION\URBAN-AMENDMENT NO.1\AMENDMENT NO.1 DOC
02019-190
3/29/19
Urban Engineering
SCANNFD
L1 URBAN
ENGINEERING Job No. 36688.B700
March 20, 2019
VIA EMAIL
Mrs. Sarah West, P.E.
Engineering Services
City of Corpus Christi
P. 0. Box 9277
Corpus Christi, Texas 78469
Subject: Kinney& Power St. Pump Station Improvements
City Project No. E16320
Dear Sarah:
As a part of the subject project our team scope included review and assessment of the
2016 XPSWMM 1 D/2D model previously developed by HDR for the downtown drainage system.
This model is to be used to evaluate present requirements and capacity of the downtown system
and to determine the feasibility of interim solutions to maximize the capacities of the existing
drainage system. As we have discussed, during our review of the model we determined several
issues that we believe need to be addressed. These issues and/or proposed updating of the
model are outside the scope of the original project. The intent of revisions to the XPSWMM model
is to get as accurate a model as possible and updating it will directly impact the understanding of
the conditions within downtown Corpus Christi and the development of drainage improvements.
We believe that the proposed improvements to the model are very important, even
critical, to providing an accurate model for the task we have been given. The proposed critical
model revisions are listed in the following:
1. Pump Station configuration issues
2. 1D model not properly connected to the 2D model in several areas in the downtown area
and where the Water St. horseshoe trunkline is not connected to laterals. These areas are
allowing water to enter the bay when the local storm sewer should flow into the downtown
system toward the Power St. Pump Station.
3. Salt Flats 1D model not properly connected to 2D near the bay. This does not allow the
Resaca area to properly drain at the beginning and at the end of the storm event.
4. Stranded water areas that directly affect the pump station behavior need to be address by
adding 1 D/2D connections at trunklines.
5. XPSWMM catchment flows incorrectly being applied outside the levee area near Salt
Flats.
The existing AE contract has an Additional Service to review possible impacts of the new
Harbor Bridge Relocation Project on the downtown drainage system. Based on the information
provided to date, the effects of the Harbor Bridge relocation project on the downtown system
appear to be relatively minor. The$16,225 allocated for the Harbor Bridge updates, could be more
effectively used to support the modeling update noted above. We propose to provide the
necessary revisions and updating of the XPSWMM model for a fee of $16,225 and request the
(361)854-3101 2725 SWANTNER DR.• CORPUS CHRISTI,TEXAS 78404 FAX(361)854-6001
www.urbaneng.corn
TBPE Firm#145
TBPLS Firm#10032400 EXHIBIT A
Page 1 of 3
Sarah West, P.E.
March 20, 2019
Page 2
City prepare a no cost AE amendment to our original contract. An updated Fee Summary is
provided in the following:
Updated Fee Summary
Basic Services: Contract Amd No. 1 Total Contract
1. Workshop/Meetings/Proj.
Management(T&M Allowance) $30,776 $0 $30,776
2. Pump Station Site Visits $7,270 $0 $7,270
3. Initial Assessment of Conditions&
Recs $39,883 $0 $39,883
4. Power St. Pump Station Evaluation $19,356 $0 $19,356
5. Kinney St. Pump Station Evaluation $19,356 $0 $19,356
6. Deliverables& Expenses $29,661 $0 $29,661
7. Model Updating/Revisions $0 $16,225 $16,225
Subtotal Basic Services $146,302 $16,225 $162,527
Additional Services Fees:
1. Harbor Bridge Relocation Drainage
Impact Evaluation (authorization
required) $16,225 -$16,225 $0
Sub-Total Additional Services $16,225 -$16,225 $0
Summary of Fees:
Basic Services Fees $146,302 $16,225 $162,527
Additional Services Fees $16,225 -$16,225 $0
Total of Fees $162,527 $0 $162,527
Updating the model has an impact on the project schedule. An updated schedule is
provided in the following:
Updated Project Schedule
Activity
March 8,2019 Notice To Proceed(NTP)
Complete Task 1: Initial Assessment&Kickoff Meeting
June 27, 2019 Task 1: Prel Technical Memo Workshop
Complete Task 2: Pump Station Site Visits
April 12,2019 Task 3: Initial Assessment of Current Conditions
May 24,2019 Task 4: Power St. Pump Station Evaluation
May 24,2019 Task 5: Kinney St. Pump Station Evaluation
August 15,2019 Task 6: Presentation of Final Project Deliverables
April 5,2019 Task 7: Modeling Updating/Revisions
EXHIBIT A
Page 2 of 3
•
Sarah West, P.E.
March 20, 2019
Page 2
Please review and let me know if any questions. If acceptable, please have an AE fee
amendment agreement processed.
Sincerely,
URBAN ENGINEERING
Mark Maroney, P. E.
MM/
EXHIBIT A
Page 3 of 3
E16320 Urban Amd 1
Final Audit Report 2019-03-28
Created: 2019-03-28
By: Elsa Kroeger(elsak@urbaneng.com)
Status: Signed
Transaction ID: CBJCHBCAABAASu9MmtwhBTG4NOxFKZ-8o9_Lg08njOY1
"E16320 Urban Amd 1 " History
t Document uploaded by Elsa Kroeger(elsak@urbaneng.com)from Acrobat
2019-03-28-4:20:29 PM GMT-IP address:24.173.56.98
C'-. Document emailed to jim urban (jimu@urbaneng.com)for signature
2019-03-28-4:20:50 PM GMT
t Document viewed by jim urban (jimu@urbaneng.com)
2019-03-28-4:22:58 PM GMT-IP address: 107.77.219.63
CY° Document e-signed by jim urban (jimu@urbaneng.com)
Signature Date:2019-03-28-4:23:34 PM GMT-Time Source:server-IP address: 107.77.219.63