CITY OF CORPUS CHRISTI
AMENDMENT NO. 2 to the
CONTRACT FOR PROFESSIONAL SERVICES
The City of Corpus Christi;Texas, hereinafter called "CITY,"and Alan Plummer Associates. Inc.,.
hereinafter called"CONSULTANT,"agree to the following amendment to the Contract for Professional
Services for Greenwood Wastewater Treatment Plant Facility Flood Mitication (Project No:
18070A),as authorized and administratively amended-by:
Original Contract April 25, 2018 : Administrative Approval.. $49,700.00
Amendment.No. 1 November 13, 2018 Motion No. 2018-216 $339',895.00
IN THE ORIGINAL CONTRACT, EXHIBIT A,:SCOPE OF SERVICES, shall-be modified as shown in
the attached Exhibit A.
IN THE ORIGINAL CONTRACT,COMPENSATION shall be modified as shown in the attached Exhibit
A for an additional fee not to exceed $0.00 fora total restated fee not to exceed $389.595:00.
All other terms and conditions of the contract between the "CITY" and "CONSULTANT" and of any -
amendments to_that contract which are not specifically.addressed herein shall remain in full force and
effect.
CITY.OF C• PUS CHRISTI ALAN PLUMM R •SSOCIATES, INC.
. .._ i� .. • _JrS". 7. - Zd!
Je �. Edmond , P.E. Rex H.Hunt Date
Director of Engineering Services Principal •
5934 S. Staples St.:Suite 220. -
(361) 356-8412 Office
-rhunt@apaienv.com
APPROVED AS TO:FORM
94).4, 2019.05.29
10:10:00-05'00'
Legal Department Date
SCANNED
ALAN PLUMMER
ASSOCIATES, INC.
611111111ENVIRONMENTAL
ENGINEERS AND SCIENTISTS
0537-034-01
May 6, 2019
Mr. Pablo G. Martinez, P.E., C.P.M.
Project Manager
Engineering Department
Corpus Christi,TX 78414
Re: Greenwood Wastewater Treatment Plant Flood Mitigation
City Project No. 18070A
Request for Amendment 2—Survey
Dear Mr. Martinez:
Alan Plummer Associates, Inc. is requesting an amendment to the Greenwood
Wastewater Treatment Plant Facility Flood Mitigation contract to include topographic
survey which will include all of the items in the attached proposal. Control points CP2
and CP4 on the attached Control Points Survey document will be used to ensure
consistency across various projects at Greenwood WWTP.
The additional cost of this work is $20,987.50 as shown in the attached Summary of
Fees.This cost will be covered as a no-cost change by removing the Permitting portion
of the original scope.
The survey deliverable will be ready for use on the project by APAI and LAN 15-25
Business days from notice to proceed.
If you have any questions, please call me at (817) 806-1700.
Sincerely,
Jeffrey E. Caffey, P.E.
Texas No. 81896
Project Manager
JEC/scmk
1320 SOUTH UNIVERSITY DRIVE SUITE 300
FORT WORTH,TEXAS 76107
PHONE 817.806.1700
FAX 817.870.2536 www.apalonvcom TOPE Firrn No.13 EXHIBIT A
Page 1 of 5
isURBAN
lam, ENGINEERING
3/26/19
Sarah Kerr
Alan Plummer Associates, Inc.
1320 S University Drive, Suite 300
Fort Worth,TX 76107
Phone: (817)806-1700
Email: skerr@apaienv.com
Re: Proposal for Professional Surveying Services
Greenwood Wastewater Plant±64.5 Acres
Saratoga Boulevard and Greenwood,Corpus Christi,TX 78415
Ms. Kerr;
Urban Engineering is pleased to submit this proposal for providing professional surveying services
for the Greenwood Wastewater Plant±64.5 Acres project located at Saratoga Boulevard and
Greenwood,Corpus Christi,TX 78415.
Please review the Scope of Services to ensure the certainty of your requirements. If you need to
modify any items, please notify us and we will provide you with a revised proposal.
Any special certification required, additional title research or additional services can be evaluated
and an additional amount can be quoted commensurate to the level of certification or additional
work required.
We appreciate the opportunity to provide you with this proposal and look forward to working with
you on this project.
If you have any questions,please give us a call at 361-854-3101.
Sincerely,
Urban Engineering
)C.
(ANk -
James D. Carr, RPLS, CFM
2725 Swantner,Corpus Christi,Texas 784041 PHONE 361-854-31011 FAX 361-854-6001
TBPLS Firm# 100324001 TBPE Firm# 145
EXHIBIT A
Page 2 of 5
Scope of Services
TASK 1 —SUBMITTALS
1.1 Topographic Survey
• Perform a Topographic Survey of the area defined in the site plan provided.
• Establish 2 Site Benchmarks in reference to the NAVD 88 Vertical Datum.
• Locate all improvements and visible above ground utilities,together with
underground utilities as marked on the ground at the time of the survey.
Invert measurements will be taken on accessible sanitary and storm sewer
facilities.
• Locate curb cuts, edge of roadway, walks,pavement,and ditches along
with ground shots to establish drainage patterns.
• Ground shots will extend approximately 15 feet beyond the limits of the
survey and to the centerline of existing adjacent streets.
• Survey will substantially comply with the current minimum technical
requirements adopted by the Texas Board of Professional Land Surveying.
• Delivery will be a map with 1-foot contours or spot elevations,certified by
a Registered Professional Land Surveyor.
Total Fixed Fee: $18.250.00
Deliverable will be 15-25 Business Days from notice to proceed.
This proposal is based on the current rate sheet and is valid for 30 days.
IN WITNESS HEREOF,the parties hereby execute this agreement upon the terms and conditions stated below.
CLIENT: CONSULTANT:
Urban En ineering-Cor C 'sti,Texas
By: By: liv miketd1
(Signature) (Date Signed) (Signature) (Date Signed)
Name: Name: James D. Carr, RPLS, CFM
(Print) (Print)
Title: Title: Director of Surveying
-2 EXHIBIT A
Page 3 of 5
•
•
•
k
r: .,,,,
�- ems;
-$:48111A'l
'•4k� s ,
4
t•
4,0
v.,'74t7:40,-;. ' 4a. ' a \ "lI4j r
,`;. r h
> s C `-\ *fir f
EXHIBIT A
Page 4 of 5
Greenwood Wastewater Treatment Plant Facility Flood Mitigation
CITY PROJECT NO. 18070A
SUMMARY OF FEES
Original Amendment No. Amendment No. Total Contract
Basic Services: Contract 1 2
Preliminary Phase $49,700.00 $254,698.00 $304,398.00
Design Phase $0.00 '
Bid Phase $0.00
Construction Admin Phase $0.00 ,
Subtotal Basic Services $49,700.00 $254,698.00 $0.00 $304,398.00
Additional Services:
Permit Prepartion $29,760.00 -$29,760.00 $0.00
Topographic Survey $20,987.50 $20,987.50
ROW Acquisition Survey $0.00
Environmental Issues $55,437.00 $8,772.50 $64,209.50 .
Public Meetings $0.00
Construction Observation $0.00
Traffic Control $0.00
Signalization Improvements $0.00
Warranty Phase $0.00
Construction Inspection (T&M) $0.00
Platting Survey $0.00
O & M Manuals $0.00
SCADA $0.00
Subtotal Additional Services $0.00 $85,197.00 $0.00 $85,197.00 •
Summary of Fees:
d m Basic Services Fees $49,700.00 $254,698.00 $0.00 $304,398.00
o• = Additional Services Fees $0.00 $85,197.00 $0.00 $85,197.00
N W Total Authorized Fees $49,700.00 $339,895.00 $0.00 $389,595.00
o 7I Admin Approval Council Approval Admin Approval
N a 25-Apr-18 13-Nov-18 Pending
Sample form for:
Payment Request
COMPLETE PROJECT NAME AE Contract
Project No. XXXX Revised 02/01/17
Invoice No. 12345
Invoice Date 01/01/2017
Total Current Previous Total Remaining Percent
Basic Services: Contract Amd No. 1 Amd No. 2 Contract Invoice Invoice Invoice Balance Complete
Preliminary Phase $1,000.00 $0.00 $0.00 $1,000.00 $0.00 $1,000.00 $1,000.00 $0.00 100.0%
Design Phase $2,000.00 $1,000.00 $0.00 $3,000.00 $1,000.00 $500.00 $1,500.00 $1,500.00 50.0%
Bid Phase $500.00 $0.00 $250.00 $750.00 $0.00 $0.00 $0.00 $750.00 0.0%
Construction Phase $2,500.00 $0.00 $1,000.00 $3,500.00 $0.00 $0.00 $0.00 $3,500.00 0.0%
Subtotal Basic Services $6,000.00 $1,000.00 $1,250.00 $8,250.00 $1,000.00 $1,500.00 $2,500.00 $5,750.00 30.3%
Additional Services:
Permitting $2,000.00 $0.00 $0.00 $2,000.00 $500.00 $0.00 $500.00 $1,500.00 25.0%
Warranty Phase $0.00 $1,120.00 $0.00 $1,120.00 $0.00 $0.00 $0.00 $1,120.00 0.0%
Inspection $0.00 $0.00 $1,627.00 $1,627.00 $0.00 $0.00 $0.00 $1,627.00 0.0%
Platting Survey TBD TBD TBD TBD TBD TBD TBD TBD TBD
0 & M Manuals TBD TBD TBD TBD TBD TBD TBD TBD TBD
SCADA TBD TBD TBD TBD TBD TBD TBD TBD TBD
Subtotal Additional Services $2,000.00 $1,120.00 $1,627.00 $4,747.00 $500.00 $0.00 $500.00 $4,247.00 10.5%
Summary of Fees:
Basic Services Fees $6,000.00 $1,000.00 $1,250.00 $8,250.00 $1,000.00 $1,500.00 $2,500.00 $5,750.00 30.3%
Additional Services Fees $2,000.00 $1,120.00 $1,627.00 $4,747.00 $500.00 $0.00 $500.00 $4,247.00 10.5%
Total of Fees $8,000.00 $2,120.00 $2,877.00 $12,997.00 $1,500.00 $1,500.00 $3,000.00 $9,997.00 23.1%
Notes:
If needed, update this sample form based on the contract requirements.
If applicable, refer to the contract for information on what to include with time and materials (T&M).
om
v x
(p S
(D
_a -
0 CO