HomeMy WebLinkAboutC2019-427 - 7/12/2019 - NA CITY OF CORPUS CHRISTI
CONTRACT FOR PROFESSIONAL SERVICES
AMENDMENT NO. 1
The City of Corpus Christi, Texas, a Texas home-rule municipal corporation ("City") and WKMC Architects, Inc.
("Consultant"), agree to the following amendment to the Contract for Professional'Services for PROJECT:
19020A CITY WAREHOUSE CONSTRUCT OFFICE SPACE
Original Contract May 2, 2019 Administrative Approval $24,058.00
In the Original Contract, Exhibit A,Scope of Services shall be amended as set forth in the attached Amendment No.1,
Exhibit A.
In the Original Contract, Exhibit A, Fees shall be amended based on the modified scope of services in the attached
Amendment No.1, Exhibit A for a fee not to exceed$2,837.00,for a total restated fee not to exceed $26,895.00.
All other terms and conditions of May 2.2019 Contract for Professional Services between the City and Consultant,
and of any amendments to that contract,which are not specifically addressed herein shall remain in full force and
effect.
CITY OF CORPUS Cs. ' TI WKMC ARCHITECTS, INC.
William S.McCord,AIA.ONgYUSdmneW SlkdcNbA.m
m,
�ars.In`",CN,N.sem
S.
4 /2 / I
Roasoii:l am approving Nn Eoa+menl
___ Oolo;2019.C6.28 I521:15e5W'
Jeff H. Edmonds, P.E. at William S. McCord Date
Director of Engineering Services President
909 S. Tancahua Street
Corpus Christi, TX 78404
(361) 887-6696 Office
APPROVED AS TO LEGAL FORM wmccord@wkmcarchitects.com
' /4`/\-- .. .
� 2019.06.27
/ 09:47:13 -05'00'
Assistant City Attorney Date
Amendment No.1
Contract for Professional Services
Page 1 of 2
PM:JJICFA:GH
K:lEngineering Projects Data Management%19020A City Warehouse Construct Office Space13.AE Agreement,Contracts 8 FMAC Task OrderslAmendmentslAMD 1
SCANNED
1/1,4t
\AI ktilECITECTC,
June 17, 2019
City of Corpus Christi
Engineering Services
ATTN: Joe Johnson, FMAC Program Manager
1201 Leopard Street
Corpus Christi, Texas 78401
RE: Fee/Scope Proposal Amendment for Professional Services for
City of Corpus Christi
William S.McCord,AIA City Warehouse- Construct Office Space, Project No. 19020A
Bill T.Wilson,II,FAIA
Thank you for the opportunity to provide an amendment to our proposal for professional
Robert Conolly,AIA A/E services for the City Warehouse, Construct Office Space Project. Based on
Naomi Corley,RID discussions with Engineering Services, we understand that the project will require three-
Jodi Smith Goings,RID part specifications to be included in the Final Construction Document Set issued June 21,
Jennifer Hilliard,AIA
2019._
Herbert Morrison,Ill,AIA
Connie Rivera,AIA
Frank Trimble,Ill,AIA Due to the fast-track nature of this project, an abbreviated design schedule and limited
services were initially proposed and included "product specifications and schedules to
be included in construction drawings".
The additional work to produce three-part specifications is broken down as follows:
Man-Hour Rate Total Estimated Estimated Man-Hour
Man-Hours Costs
Architect/Project Manager $113 7 $791
Sr. Engineer, PE $155 12 $1,860
Fee Breakdown
Architectural $791
MEP Engineering $1,860
Consultant 10%Mark-Up $186
AMENDMENT TO CONTRACT TOTAL $2,837
TOTAL REVISED FEE: $26,895
909 S.Tancahua St. Corpus Christi,Texas 78404 v 361.887.6696 f 361.887.6697 WKMCarchitecis.com
Exhibit A
Page 1 of 2
Accounting Unit: 5010-40000-185
Account: 530210
Activity: 19020-A-5010-EXP
Account Category: 30210
Fund Name: Stores
Amount: $2,837.00
Amendment No.1
Contract for Professional Services
Page 2 of 2
PM:JJ/CFA:GH
K:\Engineering Projects Data Management\19020A City Warehouse Construct Office Space\3.AE Agreement,Contracts&FMAC Task OrderstAmendmentstAMD 1
•
•
I City of Corpus Christi, City Warehouse Construct Office Space Fee Amendment
June 17, 2019
r
Page 2 of 2
Modified Project Schedule
Activity Proposed Schedule
100% Pre-Final Documents submitted for review (WKMC) June 21, 2019
City comments returned (City) June 28, 2019
Caller Times Deadline (City) July 3, 2019
Sealed CDs submitted to City (WKMC) July 8, 2019
Advertisement No. 1 (City) July 8, 2019
Advertisement No. 2 (City) July 15, 2019
Pre-Bid Meeting (City and WKMC) July 16, 2019
Bid Opening (City and WKMC) July 24, 2019
A/E Recommendation (WKMC) July 26, 2019
Sincerely,
Jodi Smith Goings, RID
Program/ Project Manager
Exhibit A
Page 2 of 2
City Warehouse Construct Office Space
CITY PROJECT NO. 19020A
SUMMARY OF FEES
Original Amendment No. Total Contract
Basic Services: Contract
Preliminary Phase $3,312.00 $3,312.00
Design Phase $10,423.00 $2,837.00 $13,260.00
Bid Phase $2,933.00 $2,933.00
Construction Admin Phase $4,693.00 $4,693.00
Subtotal Basic Services $21,361.00 $2,837.00 $24,198.00
Additional Services:
Permit Prepartion $0.00
TDLR Review, Registration, and Inspection $1,402.00 $1,402.00
ROW Acquisition Survey $0.00
Asbestos Survey& Report $1,295.00 $1,295.00
Public Meetings $0.00
Construction Observation $0.00
Traffic Control $0.00
Signalization Improvements $0.00
Warranty Phase $0.00
Construction Inspection (T&M) $0.00
Platting Survey $0.00
•
O&M Manuals $0.00 .
SCADA $0.00
Subtotal Additional Services $2,697.00 $0.00 $2,697.00
Summary of Fees:
Basic Services Fees $21,361.00 $2,837.00 $24,198.00
Additional Services Fees $2,697.00 $0.00 $2,697.00
Total Authorized Fees $24,058.00 $2,837.00 $26,895.00
Admin Approval Admin Approval
5/2/2019 Pending