HomeMy WebLinkAboutC2019-456 - 7/16/2019 - Approved 00 52 23 AGREEMENT
This Agreement, for the Project awarded on July 16, 2019, is between the City of Corpus Christi (Owner)
and
Berry Contracting LP dba Bay, Ltd (Contractor).
Owner and Contractor agree as follows:
ARTICLE 1—WORK
1.01 Contractor shall complete all Work as specified or indicated in the Contract Documents. The Work
is generally described as:
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014)
Project No. E13090
ARTICLE 2—DESIGNER AND OWNER'S AUTHORIZED REPRESENTATIVE
2.01 The Project has been designed by:
UA Engineering,Inc.
Jeff Coym, PE
5353 South Staples Street,Suite 425
Corpus Christi,Texas 78411
UASouthcc@lja.com
The Owner's Authorized Representative for this Project is:
Kent Power, P.E.—Acting Construction Management Engineer
City of Corpus Christi—Engineering Services
4917 Holly Rd, Bldg#5
Corpus Christi,TX 78411
ARTICLE 3—CONTRACT TIMES
3.01 Contract Times
A. The Work is required to be substantially completed within 550 days after the date when the
Contract Times commence to run as provided in the Notice to Proceed and is to be completed
and ready for final payment in accordance with Paragraph 17.16 of the General Conditions
within 580 days after the date when the Contract Times commence to run.
B. Milestones,and the dates for completion of each,are as defined in SECTION 0135 00 SPECIAL
PROCEDURES.
3.02 Liquidated Damages
A. Owner and Contractor recognize that time limits for specified Milestones, Substantial
Completion, and completion and readiness for Final Payment as stated in the Contract
Documents are of the essence of the Contract. Owner and Contractor recognize that the
Agreement 00 52 23-1
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
SCANNED
CONTRACT DOCUMENTS
FOR CONSTRUCTION OF
Morgan Ave . From Staples Street
To Ocean Drive ( Bond 2014)
PROJECT NUMBER E13090
City of
Corpus
Christi
,...:......................
� JEFFREY C.COYM...,�
LJA Engineering, Inc. �i�a�, 101983 : oo
TBPE F-1386/TBPLS 10104001CENS;� \��r
5350 SOUTH STAPLES STREET, SUITE 425 ���S/ AL°
CORPUS CHRISTI,TEXAS 78411
PHONE: 361.991.8550
EMAIL: LJASouthcc(a)lia.com
WVMN.LJA.COM
Record Drawing Number STR893
00 01 00 TABLE OF CONTENTS
Division/
Title
Section
Division 00 Procurement and Contracting Requirements
00 00 00 Cover
00 01 00 Table of Contents(Rev.11-14-2018)
00 21 13 Invitation to Bid and Instructions to Bidders (Rev 10-11-2018)
00 30 00 Bid Acknowledgment Form (Rev 10-11-2018)
00 30 01 Bid Form (Rev 10-11-2018)
00 30 02 Compliance to State Law on Nonresident Bidders (Rev 10-11-2018)
00 30 05 Disclosure of Interest(Revo1-2016)
00 30 06 Non-Collusion Certification (Rev 10-11-2018)
00 45 16 Statement of Experience (Rev 10-11-2018)
00 52 23 Agreement(Rev 10-11-2018)
00 61 13 Performance Bond (Rev 10-11-2018)
00 61 16 Payment Bond (Rev 10-11-2018)
00 72 00 General Conditions (Rev 11-13-2018)
00 73 00 Supplementary Conditions(Rev 10-11-2018)
Division 01 General Requirements
01 11 00 Summary of Work(Rev 10-11-2018)
01 23 10 Alternates and Allowances(Rev 10-11-2018)
01 29 01 Measurement and Basis for Payment(Rev 10-11-2018)
01 33 01 Submittal Register(Rev 10-11-2018)
01 35 00 Special Procedures (Rev10-11-2018)
01 50 00 Temporary Facilities and Controls (Rev 10-11-2018)
01 57 00 Temporary Controls(Rev 10-11-2018)
Part S Standard Specifications
Division 02 Sitework
020100 Survey Monuments (Rev 10-30-14)
021020 Site Clearing and Stripping (Rev 10-30-14)
021040 Site Grading(Rev 10-30-14)
Table of Contents 000100- 1
[Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090] Rev 11/2018
Division/
Title
Section
Division 02 Sitework
021080 Removing Old Structures (Rev 10-30-14)
022020 Excavation and Backfill For Utilities (Rev03-25-15)
022021 Control of Ground Water(Rev 10-30-14)
022022 Trench Safety For Excavations (Rev 10-30-14)
022040 Street Excavation (Rev 10-30-14)
022080 Embankment(Rev 10-30-14)
022100 Select Material (Rev 10-30-14)
022420 Silt Fence (Rev 10-30-14)
025205 Pavement Repair, Curb, Gutter, Sidewalk& Driveway Replacement(Rev 10-30-14)
025223 Crushed Limestone Flexible Base (Rev03-25-15)
025404 Asphalts, Oils and Emulsions (Rev 10-30-14)
025412 Prime Coat(Asphaltic Materials Only) (Rev 10-30-14)
025424 Hot Mix Asphaltic Concrete Pavement (Class A)
025608 Inlets(Rev 03-25-15)
025610 Concrete Curb and Gutter(Rev03-25-15)
025612 Concrete Sidewalks and Driveways (Rev03-25-15)
025614 Concrete Curb Ramps(Rev03-25-15)
025802 Temporary Traffic Controls During Construction (Rev 10-30-14)
025805 Work Zone Pavement Markings (Rev 10-30-14)
025807 Pavement Markings (Paint and Thermoplastic) (Rev 10-30-14)
025813 Preformed Thermoplastic, Striping, Words & Emblems(Rev03-25-15)
025816 Raised Pavement Markers (Rev 10-30-14)
025818 Reference Specification—TxDOT DMS-4200 Pavement Markers (Reflectorized)
025828 Reference Specification — TxDOT DMS-6130 Bituminous Adhesive For Pavement
Marker
026201 Waterline Riser Assemblies(Rev 10-30-14)
026202 Hydrostatic Testing of Pressure Systems (Rev 10-30-14)
026206 Ductile Iron Pipe & Fittings(Rev 10-30-14)
026210 PVC Pipe — AWWA C900/C905 Pressure Pipe For Municipal Water Mains and
Wastewater Force Mains(Rev03-25-15)
026214 Grouting Abandoned Utility Lines(Rev 10-30-14)
Table of Contents 000100- 2
[Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090] Rev 11/2018
Division/
Title
Section
Division 02 Sitework
026402 Waterlines(Rev03-25-15)
026404 Water Service Lines (Rev 03-25-15)
026409 Tapping Sleeves &Tapping Valves(Rev03-25-15)
026411 Gate Valves For Waterlines(Rev03-25-15)
026416 Fire Hydrants(Rev03-25-15)
027202 Manholes (Rev03-25-15)
027203 Vacuum Testing of Wastewater Manholes and Structures(Rev 10-30-14)
027205 Fiberglass Manholes (Rev3-25-15)
027402 Reinforced Concrete Pipe Culverts (Rev03-25-15)
027404 Concrete Box Culverts (Rev 10-30-14)
027606 Wastewater Service Lines(Rev 10-30-14)
028020 Seeding(Rev 03-25-15)
028040 Sodding(Rev 03-25-15)
028200 Mail Box Relocation (Rev 10-30-14)
028300 Fence Relocation (Rev 10-30-14)
028320 Chain Link Fence(Rev 10-30-14)
Division 03 Concrete
030020 Portland Cement Concrete(Rev 10-30-14)
032020 Reinforcing Steel (Rev 10-30-14)
037040 Epoxy Compounds (S-44)
038000 Concrete Structures(Rev03-25-15)
Division 05 Metals
055420 Frames, Grates, Rings & Covers (Rev03-25-15)
Appendix Title
Subsurface Investigation, Laboratory Testing Program and Provision of Pavement
1 Recommendations For The Proposed Morgan Ave. — Ocean Drive To Staples Street
(Bond 2014), Rock Engineering &Testing, April 1, 2014
2 Subsurface Utility Engineering Report Along Morgan Avenue (From Staples Street To
Ocean Drive), RVE, Inc., May—June 2014.
END OF SECTION
Table of Contents 000100-3
[Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090] Rev 11/2018
00 21 13 INVITATION TO BID AND INSTRUCTIONS TO BIDDERS
ARTICLE 1—DEFINED TERMS
1.01 Terms used in this Invitation to Bid and Instructions to Bidders have the meanings indicated in the
General Conditions and Supplementary Conditions.
ARTICLE 2—GENERAL NOTICE
2.01 The City of Corpus Christi, Texas (Owner) is requesting Bids for the construction of the following
Project:
Morgan Ave. From Staples Street To Ocean Drive (Bond 2014)
Prosect No. E13090.
A. This project includes the reconstruction of approximately 2,190 LF of Morgan Avenue
from Staples Street to Ocean Drive with new HMAC (Base Bid 1) or Concrete (Base Bid 2)
pavement and new concrete curb and gutter, concrete sidewalk. Also included are
improvements and upgrades to the Storm Water, Water, and Wastewater infrastructure.
Bidders may submit bids on either Base Bid 1 or Base Bid 2 or both.
Additive / Alternate No. 1 includes the purchase and delivery of Traffic Signal materials
only estimated to construct a new signal at the Staples Street and Morgan Avenue
intersection. No additional Contract time will be allotted for any Additive/Alternate.
Additive / Alternate No. 2 includes the purchase and delivery of Traffic Signal materials
only estimated to construct a new signal at the Santa Fe Street and Morgan Avenue
intersection. No additional Contract time will be allotted for any Additive/Alternate.
Additive / Alternate No. 3 includes the purchase and delivery of Traffic Signal materials
only estimated to construct a new signal at the 3rd Street and Morgan Avenue
intersection. No additional Contract time will be allotted for any Additive/Alternate.
2.02 The Engineer's Opinion of Probable Construction Cost for the Project is$5,524,000 for Base Bid 1
HMAC . The Project is to be substantially complete and ready for operation within 550 days. The
Project is to be complete and eligible for Final Payment 30 days after the date for Substantial
Completion.
2.03 Advertisement and bidding information for the Project can be found at the following website:
www.CivCastUSA.com
2.02 Contract Documents may be downloaded or viewed free of charge at this website. This website
will be updated periodically with Addenda, lists of interested parties, reports,or other information
relevant to submitting a Bid for the Project.
Invitation to Bid and Instructions to Bidders 002113- 1
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
ARTICLE 3— DELIVERY AND OPENING OF BIDS
3.01 Bids must be received no later than 2:00 P.M. on Wednesday, May 1, 2019 to be accepted. Bids
received after this time will not be accepted. It is the sole responsibility of the Bidder to deliver
the Bid, electronic or hard copy, by the specified deadline.
3.02 Complete and submit the Bid Form,the Bid Bond and the Bid Acknowledgement Form along with
all required documents identified in the Bid Acknowledgement Form.
3.03 Electronic Bids may be submitted to the CivCast website at www.civcastusa.com. Bid Security as
detailed in Article 8 of this Section must be submitted in accordance with paragraph 3.04.
3.04 If submitting a hard copy bid or bid security, please address envelopes or packages:
City of Corpus Christi
City Secretary's Office
City Hall Building, 1st Floor
1201 Leopard Street
Corpus Christi, Texas 78401
Attention: City Secretary
Bid Morgan Ave. From Staples Street To Ocean Drive (Bond 2014), Project No. E13090
All envelopes and packages (including FEDEX envelopes) must clearly identify, on the OUTSIDE of
the package, the project name and number and that bid documents are enclosed.
3.05 Bids will be publicly opened and read aloud at the date and time shown in paragraph 3.01, at the
following location:
City of Corpus Christi
City Hall Building, 3rd Floor
Engineering SmartBoard Conference Room
1201 Leopard Street
Corpus Christi, Texas 78401
3.06 The Owner will read aloud the names of the Bidders and the apparent Bid amounts shown on the
Bid Summary for all Bids received in time to be considered.
ARTICLE 4—PRE-BID CONFERENCE
4.01 A non-mandatory pre-bid conference for the Project will be held on 2:00 P.M. on Tuesday,April
23, 2019 at the following location:
City Hall Building, 3rd Floor
Engineering SmartBoard Conference Room
1201 Leopard Street
Corpus Christi,Texas 78401
Bids will not be accepted from Bidders who do not attend the conference. It is the Bidders'
responsibility to sign in at the pre-bid conference to verify their participation.
Invitation to Bid and Instructions to Bidders 002113- 2
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
ARTICLE 5—COPIES OF CONTRACT DOCUMENTS
5.01 Obtain a complete set of the Contract Documents as indicated in SECTION 00 52 23 AGREEMENT.
5.02 Use complete sets of Contract Documents in preparing Bids; Bidder assumes sole responsibility
for errors or misinterpretations resulting from the use of incomplete sets of Contract Documents.
5.03 OPT makes copies of Contract Documents available for the sole purpose of obtaining Bids for
completion of the Project and does not confer a license or grant permission or authorization for
any other use.
ARTICLE 6—EXAMINATION OF CONTRACT DOCUMENTS
6.01 Before submitting a Bid:
A. Examine and carefully study the Contract Documents, including any Addenda and related
supplemental data.
B. Become familiar with all federal, state, and local Laws and Regulations that may affect cost,
progress, or the completion of Work.
C. Carefully study and correlate the information available to the Bidder with the Contract
Documents, Addenda, and the related supplemental data.
D. Notify the OAR of all conflicts, errors, ambiguities, or discrepancies that the Bidder discovers in
the Contract Documents, Addenda, and the related supplemental data.
E. Determine that the Contract Documents, Addenda, and the related supplemental data are
generally sufficient to indicate and convey understanding of all terms and conditions for
completion of Work.
6.02 The submission of a Bid will constitute an incontrovertible representation by the Bidder that the
Bidder has complied with every requirement of this Article 5, that without exception the Bid is
premised upon completion of Work required by the Contract Documents, Addenda, and the
related supplemental data,that the Bidder has given the OAR written notice of all conflicts,errors,
ambiguities, and discrepancies that the Bidder has discovered in the Contract Documents,
Addenda, and the related supplemental data and the written resolutions provided by the OAR are
acceptable to the Bidder, and that the Contract Documents, Addenda, and the related
supplemental data are generally sufficient to indicate and convey understanding of all terms and
conditions for completion of Work.
ARTICLE 7—INTERPRETATIONS AND ALTERNATE BIDS
7.01 Submit all questions about the meaning or intent of the Contract Documents, Addenda, and the
related supplemental data using the Owner's Bidding Website at www.civcastusa.com.
Responses to questions submitted will be posted on the website by the Owner for the benefit of
all Bidders. Responses will be posted for questions submitted by 5:00 p.m. seven (7) days prior
to the date of the bid opening. Inquiries made after this period may not be addressed.
7.02 Submit any offer of alternate terms and conditions, or offer of Work not in strict compliance with
the Contract Documents to the OAR no later than 14 days prior to the date for opening of Bids.
OAR and Designer will issue Addenda as appropriate if any of the proposed changes to the
Invitation to Bid and Instructions to Bidders 002113-3
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
Contract Documents are accepted. A Bid submitted with clarifications or taking exceptions to the
Contract Documents, except as modified by Addenda, may be considered non-responsive.
7.03 Addenda may be issued to clarify, correct, or change the Contract Documents, Addenda or the
related supplemental data as deemed advisable by the Owner or Designer. Modifications to the
Contract Documents prior to the award of contract can only be made by Addenda.
Only answers in Addenda authorized by the Owner will be binding. Oral and other interpretations
or clarifications will be without legal effect.
ARTICLE 8—BID SECURITY
8.01 Bidders must submit an acceptable Bid Security with their Bid as a guarantee that the Bidder will
enter into a contract for the Project with the Owner within 10 days of Notice of Award of the
Contract. The security must be payable to the City of Corpus Christi, Texas in the amount of 5
percent (5%) of the greatest amount bid.
8.02 Bid Security may be in the form of a Bid Bond or a cashier's check, certified check, money order,
or bank draft from a chartered financial institution authorized to operate in the State of Texas.
Bidders submitting bids electronically through the CivCast System at www.CivCastUSA.com shall
scan and upload a copy of the Bid Security as an attachment to their bid. The original Bid Bond,
cashier's check,certified check, money order or bank draft must be enclosed in a sealed envelope,
plainly identified on the outside as containing bid documents,the bidder's name and thejob name
and number and delivered as required in Article 3 of this Section.
8.03 Bid Bond Requirements:
1. A Bid Bond must guarantee, without qualification or condition, that the Owner will be
paid a sum equal to 5 percent (5%)of the greatest amount bid if, within 10 calendar days
of Notice of Award of the Contract, the Bidder/Principal:
a. fails to enter into a contract for the Project with the Owner; or
b. fails to provide the required Performance and Payment Bonds.
2. A Bid Bond may not limit the sum payable to the Owner to be the difference between the
Bidder/Principal's bid and the next highest bidder.
3. The Bid Bond must reference the Project by name as identified in Article 2.
4. Bidders may provide their surety's standard bid bond form if revised to meet these Bid
Bond Requirements.
8.04 Failure to provide an acceptable Bid Security will constitute a non-responsive Bid which will not
be considered.
8.05 Failure to provide the required Performance and Payment Bonds will result in forfeiture of the Bid
Security to the City as liquidated damages.
8.06 Owner may annul the Notice of Award and the Bid Security of the Bidder will be forfeited if the
apparent Selected Bidder fails to execute and deliver the Agreement or Amendments to the
Agreement.
Invitation to Bid and Instructions to Bidders 002113-4
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
The Bid Security of other Bidders whom the Owner believes to have a reasonable chance of
receiving the award may be retained by the Owner until the earlier of 7 days after the Effective
Date of the Contract or 90 days after the date Bids are opened.
8.07 Bid Securities are to remain in effect until the Contract is executed. The Bid Securities of all but
the three lowest responsible Bidders will be returned within 14 days of the opening of Bids. Bid
Securities become void and will be released by the Owner when the Contract is awarded or all
Bids are rejected.
ARTICLE 9—PREPARATION OF BID
9.01 The Bid Form is included with the Contract Documents and has been made available at the
Owner's Bidding Website. Complete all blanks on the Bid Form by typing or printing in ink.
Indicate Bid prices for each Bid item or alternate shown in accordance with SECTION 01 29 01
MEASUREMENT AND BASIS FOR PAYMENT.
9.02 Execute the Bid Acknowledgement Form as indicated in the document and include evidence of
authority to sign.
9.03 Acknowledge receipt of all Addenda by filling in the number and date of each Addendum. Provide
a signature as indicated to verify that the Addenda were received. A Bid that does not
acknowledge the receipt of all Addenda may be considered non-responsive.
9.04 Provide the name, address, email, and telephone number of the individual to be contacted for
any communications regarding the Bid in the Bid Acknowledgement Form.
9.05 Provide evidence of the Bidder's authority and qualification to do business in the State of Texas
or covenant to obtain such qualification prior to award of the Contract.
ARTICLE 10—CONFIDENTIALITY OF BID INFORMATION
10.01 In accordance with Texas Government Code 552.110, trade secrets and confidential information
in Bids are not open for public inspection. Bids will be opened in a manner that avoids disclosure
of confidential information to competing Bidders and keeps the Bids from the public during
considerations. All Bids are open for public inspection after the Contract is awarded, but trade
secrets and confidential information in Bids are not typically open for public inspection. The
Owner will protect this information to the extent allowed by Laws and Regulations. Clearly
indicate which specific documents are considered to be trade secrets or confidential information
by stamping or watermarking all such documents with the word "confidential" prominently on
each page or sheet or on the cover of bound documents. Place "confidential" stamps or
watermarks so that they do not obscure any of the required information on the document, either
in the original or in a way that would obscure any of the required information in a photocopy of
the document. Photocopies of"confidential" documents will be made only for the convenience
of the selection committee and will be destroyed after the Effective Date of the Contract. Original
confidential documents will be returned to the Bidder after the Effective Date of the Contract if
the Bidder indicates that the information is to be returned with the Bid, and arrangements for its
return are provided by the Bidder.
Invitation to Bid and Instructions to Bidders 002113-5
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
ARTICLE 11—MODIFICATION OR WITHDRAWAL OF BID
11.01 A Bid may be withdrawn by a Bidder, provided an authorized individual of the Bidder submits a
written request to withdraw the Bid prior to the time set for opening the Bids.
11.02 A Bidder may withdraw its Bid within 24 hours after Bids are opened if the Bidder files a signed
written notice with the Owner and promptly, but no later than 3 days, thereafter demonstrates
to the reasonable satisfaction of the Owner that there was a material and substantial mistake in
the preparation of its Bid. The Bid Security will be returned if it is clearly demonstrated to the
Owner that there was a material and substantial mistake in its Bid. A Bidder that requests to
withdraw its Bid under these conditions may be disqualified from responding to a reissued
invitation to Bid for the Work to be furnished under these Contract Documents.
ARTICLE 12—BIDS REMAIN SUBJECT TO ACCEPTANCE
12.01 All Bids will remain subject to acceptance for 90 days, but the Owner may, at its sole discretion,
release any Bid and return the Bid Security prior to the end of this period.
ARTICLE 13—STATEMENT OF EXPERIENCE
13.01 Bidders must submit the information required in SECTION 00 45 16 STATEMENT OF EXPERIENCE
with the date Bid to demonstrate that the Bidder meets the minimum requirements to complete
the Work.
ARTICLE 14—EVALUATION OF BIDS
14.01 The Owner will consider the amount bid, the Bidder's responsibilities, the Bidder's safety record,
the Bidder's indebtedness to Owner, the Bidder's capacity to perform the work and/or whether
the Bidder has met the minimum specific project experience requirements.
14.02 Owner may conduct such investigations as it deems necessary to establish the responsibility of
the Bidder and any Subcontractors, individuals, or entities proposed to furnish parts of the Work
in accordance with the Contract Documents.
14.03 Submission of a Bid indicates the Bidder's acceptance of the evaluation technique and
methodology as well as the Bidder's recognition that some subjective judgments must be made
by the Owner during the evaluation. Each Bidder agrees to waive any claim it has or may have
against the OPT and their respective employees, arising out of or in connection with the
administration, evaluation, or recommendation of any Bid.
ARTICLE 15—AWARD OF CONTRACT
15.01 The Bidder selected for award of the Contract will be the lowest responsible Bidder that submits
a responsive bid. Owner will,at its discretion,award the contract to the lowest responsible bidder
for the base bid, plus any combination of Add or Deduct Alternates.
15.02 Owner reserves the right to reject any and all Bids, including without limitation, non-conforming,
non-responsive or conditional Bids. The Owner reserves the right to adopt the most
advantageous interpretation of the Bids submitted in the case of ambiguity or lack of clearness in
stating Bid prices and/or waive any or all formalities.
Invitation to Bid and Instructions to Bidders 002113-6
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
15.03 More than one Bid for the same Work from an individual or entity under the same or different
names will not be considered. Reasonable grounds for believing that any Bidder has an interest
in more than one Bid for the Work shall be cause for disqualification of that Bidder and the
rejection of all Bids in which that Bidder has an interest.
ARTICLE 16—MINORITY/ MBE/ DBE PARTICIPATION POLICY
16.01 Selected Contractor is required to comply with the Owner's Minority/ MBE / DBE Participation
Policy as indicated in SECTION 00 72 00 GENERAL CONDITIONS.
16.02 Minority participation goal for this Project has been established to be 45%.
16.03 Minority Business Enterprise participation goal for this Project has been established to be 15%.
ARTICLE 17—BONDS AND INSURANCE
17.01 Article 6 of the General Conditions and Article 6 of the Supplementary Conditions set forth the
Owner's requirements as to bonds and insurance. When the Selected Bidder delivers the
executed Agreement to the Owner, it must be accompanied by the required bonds and evidence
of insurance.
17.02 Provide Performance and Payment Bonds for this Project that fully comply with the provisions of
Texas Government Code Chapter 2253. Administration of Bonds will conform to Texas
Government Code Chapter 2253 and the provisions of these Contract Documents.
ARTICLE 18—SIGNING OF AGREEMENT
18.01 The City Engineer or Director of Engineering Services will submit recommendation for award to
the City Council for those project awards requiring City Council action. The Selected Bidder will
be required to deliver the required Bonds and insurance certificates and endorsements along with
the executed Contract to the Owner within 10 days. The Contract will be signed by the City
Manager or his/her designee after award and the Bidder's submission of required documentation
and signed counterparts. The Contract will not be binding upon Owner until it has been executed
by both parties. Owner will process the Contract expeditiously. However,Owner will not be liable
for any delays prior to the award or execution of Contract.
ARTICLE 19—SALES AND USE TAXES
19.01 The Owner generally qualifies as a tax exempt agency as defined by the statutes of the State of
Texas and is usually not subject to any City or State sales or use taxes, however certain items such
as rented equipment may be taxable even though Owner is a tax-exempt agency. Assume
responsibility for including any applicable sales taxes in the Contract Price and assume
responsibility for complying with all applicable statutes and rulings of the State of Texas
Comptroller.
19.02 It is the Owner's intent to have this Contract qualify as a "separated contract."
Invitation to Bid and Instructions to Bidders 002113-7
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
ARTICLE 20—WAGE RATES
20.01 This Contract is subject to Texas Government Code Chapter 2258 concerning payment of
prevailing wage rates. Requirements for paying the prevailing wage rates are discussed in
SECTION 00 72 00 GENERAL CONDITIONS. Bidders must pay not less than the minimum wage
shown on this list and comply with all statutes and rulings of the State of Texas Comptroller.
ARTICLE 21—BIDDER'S CERTIFICATION OF NO LOBBYING
21.01 In submitting its Bid, Bidder certifies that it has not lobbied the City or its officials, managers,
employees,consultants,or contractors in such a manner as to influence or to attempt to influence
the bidding or contract award process.
In the event it reasonably appears that the Bidder influenced or attempted to influence the
bidding or award process, the City may, in its discretion, reject the Bid.
ARTICLE 22—CONFLICT OF INTEREST
22.01 Bidder agrees to comply with Chapter 176 of the Texas Local Government Code and file Form CIQ
with the City of Corpus Christi City Secretary's Office, if required. For more information on Form
CIQ and to determine if you need to file a Form CIQ, please review the information on the City
Secretary's website at http://www.cctexas.com/government/city-secretary/conflict-
disclosure/index.
ARTICLE 23—CERTIFICATE OF INTERESTED PARTIES
23.01 Bidder agrees to comply with Texas Government Code section 2252.908 and complete Form 1295
Certificate of Interested Parties as part of this contract, if required. For more information, please
review the information on the Texas Ethics Commission website at
https://www.ethics.state.tx.us.
ARTICLE 24-REJECTION OF BID
24.01 The following will be cause to reject a Bid:
A. Bids which are not signed by an individual empowered to bind the Bidder.
B. Bids which do not have an acceptable Bid Security, with Power of Attorney, submitted as
required by Article 8.
C. More than one Bid for same Work from an individual, firm, partnership or corporation.
D. Evidence of collusion among Bidders.
E. Sworn testimony or discovery in pending litigation with Owner which discloses misconduct
or willful refusal by bidder to comply with subject contract or instructions of Owner.
F. Failure to have an authorized agent of the Bidder attend the mandatory Pre-Bid Conference,
if applicable.
G. Bids received from a Bidder who has been debarred or suspended by Owner.
H. Bids received from a Bidder when Bidder or principals are currently debarred or suspended
by Federal, State or City governmental agencies.
Invitation to Bid and Instructions to Bidders 002113-8
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
I. Bids received from a Bidder identified on a list prepared and maintained by the Texas
Comptroller under Chapter 2252 of the Texas Government Code.
24.02 The following may be cause to reject a Bid or cause to deem a Bid non-responsive or irregular.
The City reserves the right to waive any irregularities and any or all formalities:
A. Poor performance in execution of work under a previous City of Corpus Christi contract.
B. Failure to achieve reasonable progress on an existing City of Corpus Christi contract.
Evidence of Bidder's recurring failure to complete an item of work within a timeframe
acceptable to the City or in accordance with a City-accepted schedule is evidence of Bidder's
failure to achieve reasonable progress under this subsection.
C. Default on previous contracts or failure to execute Contract after award.
D. Evidence of failure to pay Subcontractors, Suppliers or employees in accordance with
Contract requirements.
E. Bids containing omissions, alterations of form, additions, qualifications or conditions not
called for by Owner, or incomplete Bids may be rejected. In any case of ambiguity or lack of
clarity in the Bid, OWNER reserves right to determine most advantageous Bid or to reject the
Bid.
F. Failure to acknowledge receipt of Addenda.
G. Failure to submit post-Bid information specified in Section 00 45 16 STATEMENT OF
EXPERIENCE within the allotted time(s).
H. Failure to timely execute Contract after award.
I. Previous environmental violations resulting in fines or citations by a governmental entity(i.e.
U.S. Environmental Protection Agency, Texas Commission on Environmental Quality, etc.).
J. Bidder's Safety Experience.
K. Failure of Bidder to demonstrate, through submission of the Statement of Experience, the
experience required as specified in Section 00 45 16 STATEMENT OF EXPERIENCE, if that
Section is included in the bidding documents.
L. Evidence of Bidder's lack of sufficient resources, workforce, equipment or supervision, if
required by inclusion of appropriate requirements in Section 00 45 16 STATEMENT OF
EXPERIENCE.
M. Evidence of poor performance on previous Projects as documented in Owner's project
performance evaluations.
N. Unbalanced Unit Price Bid: "Unbalanced Bid" means a Bid, which includes a Bid that is based
on unit prices which are significantly less than cost for some Bid items and significantly more
than cost for others. This may be evidenced by submission of unit price Bid items where the
cost are significantly higher/lower than the cost of the same Bid items submitted by other
Bidders on the project.
O. Evidence of Bidder's lack of capacity to perform the Work. Evidence of capacity to perform
the Work will include a factual review of (i) all remaining work or incomplete work items
under any existing city or non-city contract; (ii) resources, workforce, equipment and
supervision/supervisory staff; (iii) past performance to timely complete the same or similar
work in a good and workmanlike manner utilizing same or similar remaining resources or
Invitation to Bid and Instructions to Bidders 002113-9
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
under the same or similar conditions. Evidence of incomplete work items under any existing
City-awarded IDIQ or other contract for similar work may constitute a lack of capacity to
perform the Work.
END OF SECTION
Invitation to Bid and Instructions to Bidders 002113- 10
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
00 73 00 SUPPLEMENTARY CONDITIONS
These Supplementary Conditions amend or supplement SECTION 00 72 00 GENERAL CONDITIONS and
other provisions of the Contract Documents. All provisions not amended or supplemented in these
Supplementary Conditions remain in effect.
The terms used in these Supplementary Conditions have the meanings stated in the General Conditions.
Additional terms used in these Supplementary Conditions have the meanings stated below.
ARTICLE 1—DEFINITIONS AND TERMINOLOGY
SC-1.01 DEFINED TERMS
A. Delete the last sentence in Paragraph 1.01.A.26 and replace with the following:
"Designers are Licensed Professional Engineers, Registered Architects, or Registered
Landscape Architects qualified to practice their profession in the State of Texas."
City of Corpus Christi
UA Engineeing, Inc.
B.
ARTICLE 4—COMMENCEMENT AND PROGRESS OF THE WORK
SC-4.04 DELAYS IN CONTRACTOR'S PROGRESS
A. The allocation for delays in the Contractor's progress for rain days as set forth in General
Conditions Paragraph 4.04.D are to be determined as follows:
1. Include rain days in developing the schedule for construction. Schedule construction so
that the Work will be completed within the Contract Times assuming that these rain
days will occur. Incorporate residual impacts following rain days such as limited access
to and within the Site, inability to work due to wet or muddy Site conditions, delays in
delivery of equipment and materials, and other impacts related to rain days when
developing the schedule for construction. Include all costs associated with these rain
days and residual impacts in the Contract Price.
Supplementary Conditions 007300- 1
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
2. A rain day is defined as any day in which the amount of rain measured by the National
Weather Services at the Power Street Stormwater Pump Station is 0.50 inch or greater.
Records indicate the following average number of rain days for each month:
Month Day Month Days
January 3 July 3
February 3 August 4
March 2 September 7
April 3 October 4
May 4 November 3
June 4 December 3
3. A total of 50 rain days have been set for this Project. An extension of time due to rain
days will be considered only after 43 rain days have been exceeded in a calendar year
and the OAR has determined that a detrimental impact to the construction schedule
resulted from the excessive rainfall. Rain days are to be incorporated into the schedule
and unused rain days will be considered float time which may be consumed by the
Owner or Contractor in delay claims.
ARTICLE 5 — AVAILABILITY OF LANDS; SUBSURFACE CONDITIONS AND PHYSICAL CONDITIONS;
HAZARDOUS ENVIRONMENTAL CONDITIONS
SC-5.03 SUBSURFACE AND PHYSICAL CONDITIONS
A. This Supplementary Condition identifies documents referenced in General Conditions
Paragraph 5.03.A which describe subsurface and physical conditions.
Geotechnical Reports include the following:
1. Subsurface Investigation, Laboratory Testing Program and Provision of Pavement
Recommendations For The Proposed Morgan Ave. From Staples Street To Ocean Drive
(Bond 2014), Rock Engineering &Testing Laboratory, Inc.—April 1, 2014.
a. Subsurface Utility Engineering Report Morgan Avenue (From Staples Street To
Ocean Drive), RVE, Inc., May—June 2014
1) All information presented with regard to material type and general location.
SC-5.06 HAZARDOUS ENVIRONMENTAL CONDITIONS AT SITE
A. . "NONE"
B. This Supplementary Condition identifies documents referenced in General Conditions
Paragraph 5.06 which describe Hazardous Environmental Conditions that have been identified at
or adjacent to the Site. No reports of explorations or tests for Hazardous Environmental
Conditions at or contiguous to the Site are known to Owner.
ARTICLE 6—BONDS AND INSURANCE
SC-6.03 REQUIRED MINIMUM INSURANCE COVERAGE
Supplementary Conditions 007300- 2
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
INSURANCE REQUIREMENTS
CONTRACTOR'S INSURANCE AMOUNTS
Provide the insurance coverage for at least the following amounts unless greater amounts are required
by Laws and Regulations:
Type of Insurance Minimum Insurance Coverage
Commercial General Liability including
1. Commercial Form
2. Premises—Completed Operations
3. Explosions and Collapse Hazard
4. Underground Hazard
5. Products/Completed Operations Hazard $1,000,000 Per Occurrence
6. Contractual Liability $2,000,000 Aggregate
7. Broad Form Property Damage
8. Independent Contractors
9. Personal &Advertising Injury
Business Automobile Liability-Owned, Non-
$1,000,000 Combined Single Limit
Owned, Rented and Leased
Workers' Compensation Statutory
Employer's Liability $500,000/500,000/500,000
Excess Liability/Umbrella Liability
$1,000,000 Per Occurrence
Required if Contract Price>$5,000,000
Contractor's Pollution Liability / $1,000,000 Per Claim
Environmental Impairment Coverage
Not limited to sudden and accidental X Required ❑ Not Required
discharge. To include long-term
environmental impact for the disposal of
pollutants/contaminants.
Required if excavation>3 ft
Builder's Risk(All Perils including Collapse) Equal to Full Replacement Cost of
Structure and Contents
Required for vertical structures and bridges ❑ Required X Not Required
Installation Floater Equal to Contract Price
Required if installing city-owned equipment X Required ❑ Not Required
ARTICLE 7—CONTRACTOR'S RESPONSIBILITIES
Supplementary Conditions 007300-3
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
SC-7.02 LABOR; WORKING HOURS
B. Perform Work at the Site during regular working hours except as otherwise required for the
safety or protection of person or the Work or property at the Site or adjacent to the Site and
except as otherwise stated in the Contract Documents. Regular working hours are between
8:00 a.m. and 7:00 p.m. unless other times are specifically authorized in writing by OAR.
SC-7.04 CONCERNING SUBCONTRACTORS, SUPPLIERS,AND OTHERS
A. Add the following sentence to the end of Paragraph 7.04.A:
"The Contractor must perform at least 50 percent of the Work, measured as a percentage of
the Contract Price, using its own employees."
ARTICLE 14—PREVAILING WAGE RATE REQUIREMENTS
SC-14.04 PREVAILING WAGE RATES
A. The minimum rates for various labor classifications as established by the Owner are shown
below:
Wage
Determination Construction Type Project Type
(WD) No
TX-21 Heavy Heavy Construction Projects (including Sewer
and Water Line Construction and Drainage
Projects)
TX-29 Highway Highway Construction Projects (excluding
tunnels, building structures in rest area projects
& railroad construction; bascule, suspension &
spandrel arch bridges designed for commercial
navigation, bridges involving marine
construction; and other major bridges).
ARTICLE 19—PROJECT MANAGEMENT AND COORDINATION
Supplementary Conditions 007300-4
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
SC-19.21 COOPERATION WITH PUBLIC AGENCIES
C. For the Contractor's convenience, the following telephone numbers are listed:
Public Agencies/Contacts Phone Number
City Engineer 361-826-3500
UA Engineering, linc. 361.991.8550
Jeff Coym, PE 361.991.8550
Traffic Engineering 361-826-3547
Police Department 361-882-2600
Water/Wastewater/Stormwater 361-826-1800
(361-826-1818 after hours)
Gas Department 361-885-6900
(361-885-6942 after hours)
Parks & Recreation Department 361-826-3461
Street Department 361-826-1875
City Street Div. for Traffic Signals 361-826-1610
Solid Waste & Brush 361-826-1973
IT Department(City Fiber) 361-826-1956
AEP 1-877-373-4858
AT&T 361-881-2511
(1-800-824-4424 after hours)
Grande Communications 1-866-247-2633
Spectrum Communications 1-800-892-4357
Crown Castle Communications
1-888-632-0931
(Network Operations Center)
Centuryl-ink 361-208-0730
W i ndstrea m 1-800-600-5050
Regional Transportation Authority 361-289-2712
Port of Corpus Christi Authority Engr. 361-882-5633
Tx DOT Area Office 361-808-2500
Corpus Christi ISD 361-695-7200
ARTICLE 25—SHOP DRAWINGS
SC-25.03 CONTRACTOR'S RESPONSIBILITIES
A. Provide Shop Drawings for the following items:
Specification Section Shop Drawing Description
01 33 01 Submittal Register
Supplementary Conditions 007300-5
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
Specification Section Shop Drawing Description
ARTICLE 26—RECORD DATA
SC-26.03 CONTRACTOR'S RESPONSIBILITIES
A. Submit Record Data for the following items:
Specification Section Record Data Description
01 33 01 Submittal Register
END OF SECTION
Supplementary Conditions 007300-6
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
General Decision Number: TX190021 01/04/2019 TX21
Superseded General Decision Number: TX20180031
State: Texas
Construction Type: Heavy
Counties: Nueces and San Patricio Counties in Texas.
HEAVY CONSTRUCTION PROJECTS (including Sewer and Water Line
Construction and Drainage Projects)
Note: Under Executive Order (EO) 13658, an hourly minimum wage
of$10.60 for calendar year 2019 applies to all contracts
subject to the Davis-Bacon Act for which the contract is awarded
(and any solicitation was issued) on or after January 1, 2015.
If this contract is covered by the EO, the contractor must pay
all workers in any classification listed on this wage
determination at least$10.60 per hour(or the applicable
wage rate listed on this wage determination, if it is higher)
for all hours spent performing on the contract in calendar
year 2019. If this contract is covered by the EO and a
classification considered necessary for performance of work on
the contract does not appear on this wage determination, the
contractor must pay workers in that classification at least
the wage rate determined through the conformance process set
forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,
if it is higher than the conformed wage rate). The EO minimum
wage rate will be adjusted annually. Please note that
this EO applies to the above-mentioned types of contracts
entered into by the federal government that are subject
to the Davis-Bacon Act itself, but it does not apply
to contracts subject only to the Davis-Bacon Related Acts,
including those set forth at 29 CFR 5.1(a)(2)-(60). Additional
information on contractor requirements and worker protections
under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date
0 01/04/2019
* SUTX1987-001 12/01/1987
Rates Fringes
CARPENTER(Excluding Form
Setting).........................$ 9.05
Concrete Finisher................$ 7.56
ELECTRICIAN......................$ 13.37 2.58
Laborers:
Common......................$ 7.25
Utility.....................$ 7.68
Power equipment operators:
Backhoe.....................$ 9.21
Motor Grader................$ 8.72
----------------------------------------------------------------
WELDERS - Receive rate prescribed for craft performing
operation to which welding is incidental.
----------------------------------------------------------------
Note: Executive Order(EO) 13706, Establishing Paid Sick Leave
for Federal Contractors applies to all contracts subject to the
Davis-Bacon Act for which the contract is awarded (and any
solicitation was issued) on or after January 1, 2017. If this
contract is covered by the EO, the contractor must provide
employees with 1 hour of paid sick leave for every 30 hours
they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their
own illness, injury or other health-related needs, including
preventive care; to assist a family member (or person who is
like family to the employee)who is ill, injured, or has other
health-related needs, including preventive care; or for reasons
resulting from, or to assist a family member(or person who is
like family to the employee)who is a victim of, domestic
violence, sexual assault, or stalking. Additional information
on contractor requirements and worker protections under the EO
is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within
the scope of the classifications listed may be added after
award only as provided in the labor standards contract clauses
(29CFR 5.5 (a) (1) (ii)).
----------------------------------------------------------------
The body of each wage determination lists the classification
and wage rates that have been found to be prevailing for the
cited type(s) of construction in the area covered by the wage
determination. The classifications are listed in alphabetical
order of"identifiers" that indicate whether the particular
rate is a union rate (current union negotiated rate for local),
a survey rate (weighted average rate) or a union average rate
(weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed
in dotted lines beginning with characters other than "SU" or
"UAVG" denotes that the union classification and rate were
prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of
the union which prevailed in the survey for this
classification, which in this example would be Plumbers. 0198
indicates the local union number or district council number
where applicable, i.e., Plumbers Local 0198. The next number,
005 in the example, is an internal number used in processing
the wage determination. 07/01/2014 is the effective date of the
most current negotiated rate, which in this example is July 1,
2014.
Union prevailing wage rates are updated to reflect all rate
changes in the collective bargaining agreement(CBA) governing
this classification and rate.
Survey Rate Identifiers
Classifications listed under the "SU" identifier indicate that
no one rate prevailed for this classification in the survey and
the published rate is derived by computing a weighted average
rate based on all the rates reported in the survey for that
classification. As this weighted average rate includes all
rates reported in the survey, it may include both union and
non-union rates. Example: SULA2012-007 5/13/2014. SU indicates
the rates are survey rates based on a weighted average
calculation of rates and are not majority rates. LA indicates
the State of Louisiana. 2012 is the year of survey on which
these classifications and rates are based. The next number, 007
in the example, is an internal number used in producing the
wage determination. 5/13/2014 indicates the survey completion
date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a
new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate
that no single majority rate prevailed for those
classifications; however, 100% of the data reported for the
classifications was union data. EXAMPLE: UAVG-OH-0010
08/29/2014. UAVG indicates that the rate is a weighted union
average rate. OH indicates the state. The next number, 0010 in
the example, is an internal number used in producing the wage
determination. 08/29/2014 indicates the survey completion date
for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of
each year, to reflect a weighted average of the current
negotiated/CBA rate of the union locals from which the rate is
based.
----------------------------------------------------------------
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can
be:
• an existing published wage determination
• a survey underlying a wage determination
• a Wage and Hour Division letter setting forth a position on
a wage determination matter
• a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests
for summaries of surveys, should be with the Wage and Hour
Regional Office for the area in which the survey was conducted
because those Regional Offices have responsibility for the
Davis-Bacon survey program. If the response from this initial
contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal
process described here, initial contact should be with the
Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
2.)If the answer to the question in 1.) is yes, then an
interested party (those affected by the action) can request
review and reconsideration from the Wage and Hour Administrator
(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the
interested party's position and by any information (wage
payment data,project description, area practice material,
etc.)that the requestor considers relevant to the issue.
3.)If the decision of the Administrator is not favorable, an
interested party may appeal directly to the Administrative
Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
----------------------------------------------------------------
END OF GENERAL DECISION
General Decision Number: TX190029 01/04/2019 TX29
Superseded General Decision Number: TX20180040
State: Texas
Construction Type: Highway
Counties: Aransas, Calhoun, Goliad, Nueces and San Patricio
Counties in Texas.
HIGHWAY CONSTRUCTION PROJECTS (excluding tunnels, building
structures in rest area projects &railroad construction;
bascule, suspension & spandrel arch bridges designed for
commercial navigation, bridges involving marine construction;
and other major bridges).
Note: Under Executive Order (EO) 13658, an hourly minimum wage
of$10.60 for calendar year 2019 applies to all contracts
subject to the Davis-Bacon Act for which the contract is awarded
(and any solicitation was issued) on or after January 1, 2015.
If this contract is covered by the EO, the contractor must pay
all workers in any classification listed on this wage
determination at least$10.60 per hour(or the applicable
wage rate listed on this wage determination, if it is higher)
for all hours spent performing on the contract in calendar
year 2019. If this contract is covered by the EO and a
classification considered necessary for performance of work on
the contract does not appear on this wage determination, the
contractor must pay workers in that classification at least
the wage rate determined through the conformance process set
forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,
if it is higher than the conformed wage rate). The EO minimum
wage rate will be adjusted annually. Please note that
this EO applies to the above-mentioned types of contracts
entered into by the federal government that are subject
to the Davis-Bacon Act itself, but it does not apply
to contracts subject only to the Davis-Bacon Related Acts,
including those set forth at 29 CFR 5.1(a)(2)-(60). Additional
information on contractor requirements and worker protections
under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date
0 01/04/2019
* SUTX2011-010 08/08/2011
Rates Fringes
CEMENT MASON/CONCRETE
FINISHER(Paving & Structures)...$ 12.64
FORM BUILDER/FORM SETTER
Paving & Curb...............$ 10.69
Structures..................$ 13.61
LABORER
Asphalt Raker...............$ 11.67
Flagger.....................$ 8.81
Laborer, Common.............$ 10.25
Laborer, Utility............$ 11.23
Pipelayer...................$ 11.17
Work Zone Barricade
Servicer....................$ 11.51
PAINTER(Structures).............$ 21.29
POWER EQUIPMENT OPERATOR:
Asphalt Distributor.........$ 14.25
Asphalt Paving Machine......$ 13.44
Mechanic....................$ 17.00
Motor Grader, Fine Grade....$ 17.74
Motor Grader, Rough.........$ 16.85
TRUCK DRIVER
Lowboy-Float................$ 16.62
Single Axle.................$ 11.61
----------------------------------------------------------------
WELDERS - Receive rate prescribed for craft performing
operation to which welding is incidental.
----------------------------------------------------------------
Note: Executive Order(EO) 13706, Establishing Paid Sick Leave
for Federal Contractors applies to all contracts subject to the
Davis-Bacon Act for which the contract is awarded (and any
solicitation was issued) on or after January 1, 2017. If this
contract is covered by the EO, the contractor must provide
employees with 1 hour of paid sick leave for every 30 hours
they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their
own illness, injury or other health-related needs, including
preventive care; to assist a family member (or person who is
like family to the employee)who is ill, injured, or has other
health-related needs, including preventive care; or for reasons
resulting from, or to assist a family member(or person who is
like family to the employee)who is a victim of, domestic
violence, sexual assault, or stalking. Additional information
on contractor requirements and worker protections under the EO
is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within
the scope of the classifications listed may be added after
award only as provided in the labor standards contract clauses
(29CFR 5.5 (a) (1) (ii)).
----------------------------------------------------------------
The body of each wage determination lists the classification
and wage rates that have been found to be prevailing for the
cited type(s) of construction in the area covered by the wage
determination. The classifications are listed in alphabetical
order of"identifiers" that indicate whether the particular
rate is a union rate (current union negotiated rate for local),
a survey rate (weighted average rate) or a union average rate
(weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed
in dotted lines beginning with characters other than "SU" or
"UAVG" denotes that the union classification and rate were
prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of
the union which prevailed in the survey for this
classification, which in this example would be Plumbers. 0198
indicates the local union number or district council number
where applicable, i.e., Plumbers Local 0198. The next number,
005 in the example, is an internal number used in processing
the wage determination. 07/01/2014 is the effective date of the
most current negotiated rate, which in this example is July 1,
2014.
Union prevailing wage rates are updated to reflect all rate
changes in the collective bargaining agreement(CBA) governing
this classification and rate.
Survey Rate Identifiers
Classifications listed under the "SU" identifier indicate that
no one rate prevailed for this classification in the survey and
the published rate is derived by computing a weighted average
rate based on all the rates reported in the survey for that
classification. As this weighted average rate includes all
rates reported in the survey, it may include both union and
non-union rates. Example: SULA2012-007 5/13/2014. SU indicates
the rates are survey rates based on a weighted average
calculation of rates and are not majority rates. LA indicates
the State of Louisiana. 2012 is the year of survey on which
these classifications and rates are based. The next number, 007
in the example, is an internal number used in producing the
wage determination. 5/13/2014 indicates the survey completion
date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a
new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate
that no single majority rate prevailed for those
classifications; however, 100% of the data reported for the
classifications was union data. EXAMPLE: UAVG-OH-0010
08/29/2014. UAVG indicates that the rate is a weighted union
average rate. OH indicates the state. The next number, 0010 in
the example, is an internal number used in producing the wage
determination. 08/29/2014 indicates the survey completion date
for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of
each year, to reflect a weighted average of the current
negotiated/CBA rate of the union locals from which the rate is
based.
----------------------------------------------------------------
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can
be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on
a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests
for summaries of surveys, should be with the Wage and Hour
Regional Office for the area in which the survey was conducted
because those Regional Offices have responsibility for the
Davis-Bacon survey program. If the response from this initial
contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal
process described here, initial contact should be with the
Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
2.)If the answer to the question in 1.) is yes, then an
interested party (those affected by the action) can request
review and reconsideration from the Wage and Hour Administrator
(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the
interested party's position and by any information (wage
payment data,project description, area practice material,
etc.)that the requestor considers relevant to the issue.
3.)If the decision of the Administrator is not favorable, an
interested party may appeal directly to the Administrative
Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
----------------------------------------------------------------
END OF GENERAL DECISION
00 91 01 ADDENDUM NUMBER 3
Morgan Ave. From Staples Street To Ocean Drive
Project: (Bond 2014) Project Number: E13090
Owner: City of Corpus Christi
City _ .-.._. ---------- -- _
Engineer: J.H. Edmonds, P. City of Corpus Christi
Designer: Jeff Coym, PE—Vice President UA Engineering, Inc.
Addendum No. 3 Specification Section: 00 9101 Issue Date: 5/13/2019
Acknowledge receipt of this Addendum in the Bid Acknowledgement Form submitted for this
Project. Failure to acknowledge receipt of this addendum in the Bid Acknowledgement Form may
render the Bid as non-responsive and serve as the basis for rejecting the Bid.
Make the additions, modifications or deletions to the Contract Documents described in this
Addendum,
i Approved by: ff Coym, PE—Vice President
//��''�,/�/, r ,gyp.,,,,.... ,•,.I-� ��
Nora Dat
Addendum Items: f. *r�
Modifications: �... JEFFREY C.COYht , i
c 0001 0OTable of Contents �i� '. 1019€33
Attachments: *;ZONAL'
00 0100 Table of Contents(Attachment 1)
c 027200 Control of Wastewater Flows(Temporary Bypass ,0LLJJAA1E: gi e ing, Inc. F-138/6q
Pumping Systems) (Attachment 2) _ 13
/ /
ARTICLE 1—BIDDING REQUIREMENTS
1.01 ACKNOWLEDGE ADDENDA
A. Acknowledge receipt of this Addendum in the Bid Acknowledgement Form submitted for this
Project. Failure to acknowledge receipt of this addendurn in the Bid Acknowledgement Form
may render the Bid as non-responsive and serve as the basis for rejecting the Bid,
B. SECTION 00 0100 TABLE OF CONTENTS
DELETE: TABLE OF CONTENTS in its entirety.
ADD: TABLE OF CONTENTS in its entirety(Attachment 1).
Addendum No. 3 009101- 1
Project No. E13090, Morgan Ave. From Staples Street To Ocean Drive(Bond 2014) Rev o1-13-2016
ARTICLE 2—MODIFCATIONS TO THE SPECIFICATIONS OR TECHNICAL SPECIFICATIONS.
2.01 ADD, DELETE OR REPLACE SPECIFICATION SECTIONS (OR TECHNICAL SPECIFICATIONS)
A. Add the following Specification Sections (or Technical Specifications):
Added Specification Sections (or Technical Specifications)
SECTION 027200 CONTROL OF WASTEWATER FLOWS(TEMPORARY BYPASS PUMPING
SYSTEMS (Attachment 2)
END OF ADDENDUM NO. 3
Addendum No. 3 00 9101- 2
Project No. E13090, Morgan Ave. From Staples Street To Ocean Drive(Bond 2014) Rev 01-13-2016
ADDENDUM NO. 3
ATTACHMENT 1
Sheet 1 of 3
00 01 00 TABLE OF CONTENTS
Division/
Title
Section
Division 00 Procurement and Contracting Requirements
00 00 00 Cover
00 01 00 Table of Contents(Rev.11-14-2018)
00 21 13 Invitation to Bid and Instructions to Bidders (Rev 10-11-2018)
00 30 00 Bid Acknowledgment Form (Rev 10-11-2018)
00 30 01 Bid Form (Rev 10-11-2018)
00 30 02 Compliance to State Law on Nonresident Bidders_(Rev 10-11-2018)
00 30 05 Disclosure of Interest(Revo1-2016)
00 30 06 Non-Collusion Certification_(Rev 10-11-2018)
00 45 16 Statement of Experience (Rev 10-11-2018)
00 52 23 Agreement(Rev 10-11-2018)
00 61 13 Performance Bond (Rev 10-11-2018)
00 61 16 Payment Bond (Rev 10-11-2018)
00 72 00 General Conditions (Rev 11-13-2018)
00 73 00 Supplementary Conditions(Rev 10-11-2018)
Division 01 General Requirements
01 11 00 Summary of Work(Rev 10-11-2018)
01 23 10 Alternates and Allowances(Rev 10-11-2018)
01 29 01 Measurement and Basis for Payment(Rev 10-11-2018)
01 33 01 Submittal Register(Rev 10-11-2018)
01 35 00 Special Procedures (Rev10-11-2018)
01 50 00 Temporary Facilities and Controls (Rev 10-11-2018)
01 57 00 Temporary Controls_(Rev 10-11-2018)
Part S Standard Specifications
Division 02 Sitework
020100 Survey Monuments (Rev 10-30-14)
021020 Site Clearing and Stripping (Rev 10-30-14)
021040 Site Grading(Rev 10-30-14)
Table of Contents 000100- 1
[Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090] Rev 11/2018
ADDENDUM NO. 3
ATTACHMENT 1
Sheet 2 of 3
Division/
Title
Section
Division 02 Sitework
021080 Removing Old Structures (Rev 10-30-14)
022020 Excavation and Backfill For Utilities (Rev03-25-15)
022021 Control of Ground Water(Rev 10-30-14)
022022 Trench Safety For Excavations (Rev 10-30-14)
022040 Street Excavation (Rev 10-30-14)
022080 Embankment(Rev 10-30-14)
022100 Select Material (Rev 10-30-14)
022420 Silt Fence (Rev 10-30-14)
025205 Pavement Repair, Curb, Gutter, Sidewalk& Driveway Replacement(Rev 10-30-14)
025223 Crushed Limestone Flexible Base (Rev03-25-15)
025404 Asphalts, Oils and Emulsions (Rev 10-30-14)
025412 Prime Coat(Asphaltic Materials Only) (Rev 10-30-14)
025424 Hot Mix Asphaltic Concrete Pavement (Class A)
025608 Inlets(Rev 03-25-15)
025610 Concrete Curb and Gutter(Rev03-25-15)
025612 Concrete Sidewalks and Driveways (Rev03-25-15)
025614 Concrete Curb Ramps(Rev03-25-15)
025802 Temporary Traffic Controls During Construction (Rev 10-30-14)
025805 Work Zone Pavement Markings (Rev 10-30-14)
025807 Pavement Markings (Paint and Thermoplastic) (Rev 10-30-14)
025813 Preformed Thermoplastic, Striping, Words & Emblems(Rev03-25-15)
025816 Raised Pavement Markers (Rev 10-30-14)
025818 Reference Specification—TxDOT DMS-4200 Pavement Markers (Reflectorized)
025828 Reference Specification — TxDOT DMS-6130 Bituminous Adhesive For Pavement
Marker
026201 Waterline Riser Assemblies(Rev 10-30-14)
026202 Hydrostatic Testing of Pressure Systems (Rev 10-30-14)
026206 Ductile Iron Pipe & Fittings(Rev 10-30-14)
026210 PVC Pipe — AWWA C900/C905 Pressure Pipe For Municipal Water Mains and
Wastewater Force Mains(Rev03-25-15)
026214 Grouting Abandoned Utility Lines(Rev 10-30-14)
Table of Contents 000100- 2
[Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090] Rev 11/2018
ADDENDUM NO. 3
ATTACHMENT 1
Sheet 3 of 3
Division/
Title
Section
Division 02 Sitework
026402 Waterlines(Rev03-25-15)
026404 Water Service Lines (Rev 03-25-15)
026409 Tapping Sleeves &Tapping Valves(Rev03-25-15)
026411 Gate Valves For Waterlines(Rev03-25-15)
026416 Fire Hydrants(Rev03-25-15)
027200 Control of Wastewater Flows (Temporary Bypass Pumping Systems)
027202 Manholes (Rev03-25-15)
027203 Vacuum Testing of Wastewater Manholes and Structures(Rev 10-30-14)
027205 Fiberglass Manholes (Rev3-25-15)
027402 Reinforced Concrete Pipe Culverts (Rev03-25-15)
027404 Concrete Box Culverts (Rev 10-30-14)
027606 Wastewater Service Lines(Rev 10-30-14)
028020 Seeding(Rev 03-25-15)
028040 Sodding(Rev 03-25-15)
028200 Mail Box Relocation (Rev 10-30-14)
028300 Fence Relocation (Rev 10-30-14)
028320 Chain Link Fence(Rev 10-30-14)
Division 03 Concrete
030020 Portland Cement Concrete(Rev 10-30-14)
032020 Reinforcing Steel (Rev 10-30-14)
037040 Epoxy Compounds (S-44)
038000 Concrete Structures(Rev03-25-15)
Division 05 Metals
055420 Frames, Grates, Rings & Covers (Rev03-25-15)
Appendix Title
Subsurface Investigation, Laboratory Testing Program and Provision of Pavement
1 Recommendations For The Proposed Morgan Ave. — Ocean Drive To Staples Street
(Bond 2014), Rock Engineering &Testing, April 1, 2014
2 Subsurface Utility Engineering Report Along Morgan Avenue (From Staples Street To
Ocean Drive), RVE, Inc., May—June 2014.
END OF SECTION
Table of Contents 000100-3
[Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090] Rev 11/2018
ADDENDUM NO. 3
ATTACHMENT 2
Sheet 1 of 7
SECTION 027200
CONTROL OF WASTEWATER FLOWS
(TEMPORARY BYPASS PUMPING SYSTEMS
1. GENERAL
1.1 DESCRIPTION
A. This specification shall govern all work necessary for designing, installing,
implementing, operating, and maintaining a temporary bypass pumping and flow control
system, as provided by the Contractor for the purpose of diverting wastewater flow
around the work area for the duration necessary to complete the work (i.e., control of
wastewater flows). The Contractor shall furnish all materials, labor, equipment, power,
maintenance, and incidentals required to maintain continuous and reliable wastewater
service in all lines for the duration of the project.
1.2 SUBMITTALS
A. Bypass Pumping Plan Form: It shall be the Contractor's responsibility to legibly and
thoroughly complete, in its entirety, the attached Bypass Pumping Plan Form and submit
it to the Engineer and/or the appropriate City staff for review and approval, prior to the
installation of any pumping system proposed for use.
Unless the bypass pumping is associated with an emergency work order, the standard
approval protocol is as follows: The Contractor prepares and submits the plan to the
Engineer a minimum of 7 days prior to mobilizing to site. The Engineer reviews the
bypass plan and coordinates approval with Engineering Services and the Operating
Department. Engineer and City will put forth a reasonable level of effort to expedite the
review and approval process. No deviation from the procedure shall be allowed.
B. Bypass Pumping Plan Schematic: In addition to the above referenced form, the
Contractor shall also furnish a sufficiently detailed schematic drawing identifying the
approximate location of all bypass pumping system components. The schematic drawing
shall clearly label parallel/crossing streets, identify landmark structures, and depict the
locations of all pumps and piping.
At a minimum, the bypass pumping plan schematic drawing and associated attachments
should include the following items:
1) Pump curves showing designed operation point for this specific project
2) Approximate location of bypass system pumping components
3) Location of manhole or access point for suction and discharge
4) Configuration,routing,location and depth of the suction and discharge piping
5) General arrangement/type of additional support equipment.
6) Temporary pipe supports, anchoring and thrust restraint blocks,if required
7) Traffic Control Plan and Traffic Department permit if the bypass is within the right-
of-way.
8) Description of the method for removing pressure and all wastewater from existing
force mains being taken out of service,if necessary.
9) All other City-department and Regulatory requirements.
027200
Page 1 of 7
Rev.10-30-2014
ADDENDUM NO. 3
ATTACHMENT 2
Sheet 2 of 7
10) Sewer plugging locations,method, and types of plugs
11) Method of protecting discharge manholes or structures from erosion and damage.
1.3 RESPONSIBILITY/AUTHORITY
A. It is essential to the operation of the existing wastewater system that there is no
interruption in the flow of wastewater throughout the duration of the project. The
Contractor shall be completely responsible for designing, scheduling, providing,
installing, operating, fueling and maintaining the temporary bypass pumping system in a
manner that does not cause or contribute to overflows, releases, or spills of wastewater
from the wastewater or bypass system. The Contractor shall neither anticipate nor expect
any assistance from the City of Corpus Christi departments for any of the bypass
operation.
B. Contractor shall provide a responsible employee to man the bypass system 24 hours per
day, 7 days per week during operation. The monitoring employee shall be properly
trained, experienced, and mechanically qualified such that they can quickly and
effectively address any potential emergency and non-emergency situations associated
with the bypass system which must remain in operation. The wastewater and bypass
systems should be inspected at least once every 2 hours. The Contractor shall be
responsible for ensuring that the wastewater collection system is not compromised during
bypass installation or operation, and contractor shall ensure that the system operates
properly during this period.
C. The Contractor shall consider and be responsible for the impacts on the collection system
area, both upstream and downstream of the bypass and shall maintain the system in a
manner that will protect public and private property from damage and flooding.
Upstream impacts may include, but are not limited to backups and overflows.
Downstream impacts may include,but are not limited to surcharges and overflows.
D. Contractor shall make all effort to minimize spills of raw wastewater during the
improvements and bypassing. All spills and sanitary sewer overflows shall immediately
be reported to the City at 361-826-2489 and the Contractor shall be solely responsible for
wash down, clean-up and disinfection of said spillages or overflows to the satisfaction of
the owner at no additional cost to the City of Corpus Christi.
E. The City is permitted through the Texas Commission on Environmental Quality to
operate the wastewater system. The final authority comes from the City as to the
operation of the wastewater system and as such it reserves the right to halt the bypassing
operation at any time in order to maintain public health and safety.
027200
Page 2 of 7
Rev.10-30-2014
ADDENDUM NO. 3
ATTACHMENT 2
Sheet 3 of 7
2. PRODUCTS
2.1 MATERIALS
A. Bypass Pumps
a. Pumps shall be fully automatic self-priming pumps that do not require the use of
foot-valves or vacuum pumps in the priming system. The pumps may be electric or
diesel powered. Pre-approved manufacturers are Godwin or Rain-for-Rent.
Approved equals may be considered by the Engineer if they meet all requirements in
this specification but Contractor shall provide submittal package for Engineer's
review and approval prior to installation. Pumps shall be equipped with critically
silenced, sound attenuated enclosures with a maximum 65 dB (10-feet from pump), a
diesel day tank with a minimum 24-hour runtime without refuel, and automatic
start/stop controls for each pump.
b. Pumping capacity of the bypass pump shall be capable of handling the flow
conditions at all times and shall provide a minimum of 1.5 times the existing capacity
of whatever line or lift station is being bypassed.
c. The Contractor shall have adequate standby equipment available and ready for
immediate operation and use in the event of an emergency or breakdown. In critical
installations, as determined by the Engineer, one standby pump for each size pump
utilized shall be installed at the mainline flow bypassing locations, ready for use in
the event of primary pump failure.
B. Suction and Discharge Piping: Determined according to pump size, flow calculations,
system operating conditions, manhole depth, and length of suction piping in accordance
with the pump manufacturers specifications and recommendations. In order to prevent the
accidental spillage of flows, all discharge systems shall be temporarily constructed of
heavy-duty pipe with positive restrained joints.
a. High Density Polyethylene (HDPE)
i. Homogeneous throughout, free of visible cracks, discoloration, pitting, varying
wall thickness, holes, foreign material, blisters, or other deleterious faults.
Defective areas shall be cut out and butt-fusion welded as per manufacturer's
recommendations.
ii. Assembled and joined at site using couplings, flanges, or butt-fusion method to
provide leak proof joint, as per manufacturer's recommendations and ASTM D-
2657.
iii. Fusing must be performed by personnel certified as fusion technicians by
manufacturer of HDPE pipe and/or fusing equipment. Fused joints shall be
watertight and have tensile strength equal to that of pipe.
iv. HDPE is required to be used in or adjacent to environmentally sensitive areas.
b. Polyethylene Plastic Pipe (PE)
i. High density solid wall and following ASTM F714 Polyethylene (PE) Plastic
Pipe (SDR-DR)based on outside diameter,ASTM D1248 and ASTM D3550
ii. Homogeneous throughout, free of visible cracks, discoloration, pitting, varying
wall thickness,holes, foreign material,blisters,or other deleterious faults.
c. Quick-Disconnect Steel Galvanized Pipe and Heavy-Duty Flexible Hoses
027200
Page 3 of 7
Rev.10-30-2014
ADDENDUM NO. 3
ATTACHMENT 2
Sheet 4 of 7
i. Must consist of heavy-duty steel with high tensile strength, x-ray welded,
abrasion resistant and suitable for intended service with a maximum pressure
rating of at least 174 PSI
ii. Bauer quick-disconnect fittings/joints shall be restrained and watertight. Joints
shall consist of vacuum sealing O-rings to help pumps prime faster and perform
at their designed flow rates with no leaks,even at high pressure ratings
iii. Joints shall provide 30-degree articulation at every coupling and shall not require
perfect alignment to make each connection.
iv. The galvanized couplings shall not be hindered by sand,mud, and grit.
d. Valves and Fittings
i. Contractor shall provide valves and fittings as necessary and in accordance with
the approved pipe materials shown above.
e. Plugs
i. Selected and installed according to size of line to be plugged, pipe, manhole
configurations, and based on specific application.
ii. Prior to use,Engineer may inspect plugs for defects which may lead to failure.
iii. Contractor shall provide additional plugs in the case of failure
f. Miscellaneous
i. When temporary piping crosses local streets/roadways and private driveways,
Contractor shall provide traffic ramps or covers designed, installed, and
maintained for H-20 loading requirements while in use.
3. EXECUTION
3.1 SCHEDULING& COORDINATION
A. Unless the bypass pumping is associated with an emergency work order, the Contractor
shall provide a minimum of 48 hour notice to the Engineer and Wastewater Department
for the startup of bypass operations once the completed bypass plan has been approved by
the design engineer. Unless needed otherwise for emergency work,no bypassing shall be
initiated on Friday, Saturday or Sunday,or the day immediately preceding a City holiday.
B. Inclement Weather: The Contractor shall not be allowed to commence bypass operation
should inclement weather be forecast for the period of the scheduled improvements.
C. Under special circumstances, as identified by the Engineer,where critical lines with large
service areas are being bypassed, the Contractor is responsible for setting up a meeting
between the Engineer/City/Operating Department to affirm and coordinate the approved
bypass plan and to verify the intended site installation conforms to the approved plan.
Engineer may also require the bypass system to be in service for at least 24-hours prior to
taking existing gravity lines or force mains out of service to demonstrate reliability.
D. Before beginning bypass operations, the Engineer/City Operating Department must be
notified for field verification of pumps, piping, and equipment, etc., to ensure the site
installation conforms to the approved plan.
027200
Page 4 of 7
Rev.10-30-2014
ADDENDUM NO. 3
ATTACHMENT 2
Sheet 5 of 7
E. Before beginning bypass operations, the Contractor shall confirm appropriate emergency
contact information has been provided to the City and Engineer on the Bypass Pumping
Plan Form including emergency cell phone number of bypass operators/monitors
responsibly manning the bypass system 24 hours per day along with the project
superintendent and pump supplier.
F. The Contractor can work extended hours, if approved by the Engineer, to perform the
improvements during the bypass operation. Work during extended hours cannot create a
nuisance for the neighbors.
G. Once a lift station is taken out of service and bypass operations begun, work shall be
continuous on the lift station improvements until all improvements are completed and the
lift station is returned to normal service.
H. The Contractor shall cease bypass pumping operations and return flows to the new and/or
existing wastewater system when directed by the Owner. This may be expected if the
bypass system is not in accordance with this specification or if inclement weather is in
the forecast.
3.2 INSTALLATION& OPERATIONS
A. Installation of Temporary Force Mains
a. Force mains may be placed along shoulder of road, medians, and/or outside of
pavement. Do not place in streets or sidewalks without Engineers approval.
b. When temporary piping crosses local streets/roadways and/or private driveways,
Contractor shall provide traffic ramps or covers designed, installed, and maintained
for H-20 loading requirements while in use.
c. When traffic ramps cannot be used, install temporary piping in trenches and cover
with temporary pavement, as approved by the Engineer.
B. Discharge piping to gravity lines or manholes shall be designed in such a manner as to
prevent discharge from contacting manhole walls or benching with as minimal turbulence
as possible.
C. Plugging or blocking of wastewater flows shall incorporate a primary and secondary
plugging device. When plugging or blocking is no longer needed for performance and
acceptance of work, it is to be removed in a manner that permits the wastewater flow to
slowly return to normal without surge, to prevent surcharging or causing other major
disturbances downstream.
D. The Contractor shall not cut existing force mains or gravity lines until it is determined
that the containment area in place is sufficient for handling any wastewater within the
pipe.
E. Some locations may require multiple bypass systems. If bypass system is provided with
air release valves,then the valve drains shall be piped to a manhole for discharge.
F. Upon completion of the bypass pumping operations, remove piping, restore property to
pre-construction condition and restore pavement.
027200
Page 5 of 7
Rev.10-30-2014
ADDENDUM NO. 3
ATTACHMENT 2
Sheet 6 of 7
4. MEASUREMENT AND PAYMENT
Unless otherwise specified in the Bid Form, Control of Wastewater Flows (Temporary Bypass Pumping
Systems) shall not be measured for pay but will be considered subsidiary to the applicable pay item, to
include all material, labor, equipment and supervision necessary to complete the bypass design, planning,
coordination,installation,operation,maintenance and removal.
027200
Page 6 of 7
Rev.10-30-2014
ADDENDUM NO. 3
ATTACHMENT 2
Sheet 7 of 7
BYPASS PUMPING PLAN FORM
Date:
Project Title: No.:
Engineer: Contractor:
Service Area: Lift Station No.(if applicable):
Start Date &Time: Completion Date &Time:
Sewer Line Size being Bypassed: Estimated Peak Flow:
Line Plugging Method&Locations:
Suction Manhole or Lift Station Number and Depth:
Discharge Manhole or Lift Station Number and Depth:
Maximum Surcharge Depth Allowed:
Bypass Forcemain Size,Material&Length:
Pump Description: (Self-Priming,Critically Silenced,and Automatic Level Controls Required)
Make,Model, Suction/Discharge Size: Diesel or Electric
Total Number of Pumps/Standby Pumps:
Total& Firm Capacity(GPM @ TDH):
Vacuum Trucks (if required,number and capacity):
Contractor Personnel Manning Bypass System (24 hours/day):
Name: Phone:
Name: Phone:
Emergency Contacts:
Name: Phone:
Name: Phone:
Additional Notes:
Required Checklist:
YES NO
❑ ❑ Schematic drawing providing details of proposed bypass pumping system,routing of bypass lines(using
manhole numbers and/or lift station names as applicable),equipment location,and proposed sequencing.
❑ ❑ Has traffic control plan been appropriately modified to facilitate the bypass pumping equipment?
❑ ❑ Pumps: Self-priming&Critically Silenced. Provide pump curve with Bypass plan.(Requirement).
❑ ❑ Contractor shall coordinate with Supplier for appropriate instruction and training on pump operation.
❑ ❑ Have emergency and/or backup provisions been made for quick pump change out in the case of system
failure?
❑ ❑ Contractor has confirmed no rain(less than 1/2-in)in the forecast?
Prepared by: Reviewed by:
Contractor Representative Date Wastewater Representative Date
027200
Page 7 of 7
Rev.10-30-2014
E13090 Morgan Ave.from S.Staples St.to Ocean Drive(Bond 2014) Report Created On:5/17/2019 4:06:42 PM
PROJECT:
E13090 Morgan Ave. from S. Staples St. to Ocean Drive (Bond 2014)
BIDDER:
Bay Ltd.
TOTAL BID:
COMPLETION TIME:
Not Required
BIDDER INFO:
1414 Valero Way
Corpus Christi,TX 78409
P: 361-299-3730
F:
E13090 Morgan Ave.from S.Staples St.to Ocean Drive(Bond 2014) Report Created On:5/17/2019 4:06:42 PM
BID TOTALS
BASE BID-PART 1 (HMAC) Total
PART 1A-GENERAL(ITEMS 1A1 THRU 1A13) $491,785.00
PART 1 B-STREET IMPROVEMENTS (ITEMS 1 B1 THRU 1 B33) $1,182,371.20
PART 1 C- RTA IMPROVEMENTS(ITEMS 1 C1 THRU 1 C2) $47,600.00
PART 1 D-ADA IMPROVEMENTS(1 D1 THRU 1 D6) $266,028.40
PART 1 E- DRAINAGE(1 E1 THRU 1 E30) $2,050,575.00
PART 1 F-WATER IMPROVEMENTS(1 F1 THRU 1 F33) $665,226.20
PART 1G-WASTEWATER IMPROVEMENTS(1 G1 THRU 1G22) $433,588.50
PART 1 IH -GAS IMPROVEMENTS(1 H1 THRU 11-12) $7,000.00
PART 11 - I.T. INFRASTRUCTURE IMPROVEMENTS(111 THRU 113) $43,562.50
Total $5,187,736.80
ADDITIVE ALTERNATE NO. 1 (HMAC) Total
Part 1J - ADDITIVE ALTERNATE NO. 1 STAPLES ST.TRAFFIC SIGNAL REPLACEMENT(1J1) $300,000.00
Total $300,000.00
ADDITIVE ALTERNATE NO.2(HMAC) Total
PART 1 K-ADDITIVE ALTERNATE NO. 2 SANTA FE TRAFFIC SIGNAL REPLACEMENT(1 K1) $300,000.00
Total $300,000.00
ADDITIVE ALTERNATE 3(HMAC) Total
PART 1 L-ADDITIVE ALTERNATE NO. 3 3rd ST.TRAFFIC SIGNAL REPLACEMENT(1 L1) $300,000.00
Total $300,000.00
BASE BID PART 2(CONCRETE) Total
PART 2A-GENERAL(ITEMS 2A1 THRU 2A13) Not Bidding
PART 2B-STREET IMPROVEMENTS (ITEMS 2131 THRU 21332) Not Bidding
PART 2C- RTA IMPROVEMENTS(3 BUS STOPS)(ITEM 2C1) Not Bidding
PART 2D-ADA IMPROVEMENTS(ITEMS 2D1 THRU 2D6) Not Bidding
PART 2E- DRAINAGE IMPROVEMENTS(2E1 THRU 2E30) Not Bidding
E13090 Morgan Ave.from S.Staples St.to Ocean Drive(Bond 2014) Report Created On:5/17/2019 4:06:42 PM
PART 2F-WATER IMPROVEMENTS(2F1 THRU 2F33) Not Bidding
PART 2G-WASTEWATER IMPROVEMENTS(2G1 THRU 2G22) Not Bidding
PART 2H -GAS IMPROVEMENTS(21-11 THRU 21-12) Not Bidding
PART 21 - I.T. INFRASTRUCTURE IMPROVEMENTS(211 THRU 213) Not Bidding
Total Not Bidding
ADDITIVE ALTERNATE NO. 1 (CONCRETE) Total
Part 2J - ADDITIVE ALTERNATE NO. 1 STAPLES ST.TRAFFIC SIGNAL REPLACEMENT(2J1) Not Bidding
Total Not Bidding
ADDITIVE ALTERNATE NO.2(CONCRETE) Total
PART 2K-ADDITIVE ALTERNATE NO. 2 SANTA FE TRAFFIC SIGNAL REPLACEMENT(2K1) Not Bidding
Total Not Bidding
ADDITIVE ALTERNATE NO.3(CONCRETE) Total
PART 2L-ADDITIVE ALTERNATE NO. 3 3rd ST.TRAFFIC SIGNAL REPLACEMENT(21-1) Not Bidding
Total Not Bidding
PART 1A-GENERAL(ITEMS 1A1 THRU 1A13)
No. Description Unit Qty Unit Price Ext Price
1A1 MOBILIZATION(MAX. 5%OF PROJECT LS 1 $230,000.00 $230,000.00
TOTAL)
1A2 BONDS&INSURANCE LS 1 $38,000.00 $38,000.00
1A3 CLEAR RIGHT-OF-WAY AC 3.4 $4,000.00 $13,600.00
1A4 TRAFFIC CONTROL PLAN AND LS 1 $15,600.00 $15,600.00
PREPARATION
1A5 TRAFFIC CONTROL LS 1 $12,800.00 $12,800.00
MOBILIZATION/ADJUSTMENTS
1A6 TRAFFIC CONTROL ITEMS(SIGNS, MO 18 $3,200.00 $57,600.00
BARRICADES,CHANNELIZING DEVICES,
ETC.)
1A7 LOW PROFILE CONCRETE BARRIER LF 2175 $20.00 $43,500.00
E13090 Morgan Ave.from S.Staples St.to Ocean Drive(Bond 2014) Report Created On:5/17/2019 4:06:42 PM
1A8 MOBILE DIGITAL SIGN BOARDS EA 3 $9,900.00 $29,700.00
1A9 BLOCK SODDING SY 865 $21.00 $18,165.00
1A10 STORM WATER POLLUTION LS 1 $8,100.00 $8,100.00
PREVENTION PLAN
1A11 INLET PROTECTION EA 26 $160.00 $4,160.00
1Al2 SILT FENCE LF 2800 $7.20 $20,160.00
1A13 OZONE ACTION DAY DAYS 2 $200.00 $400.00
Sub Total: $491,785.00
PART 1B-STREET IMPROVEMENTS (ITEMS 11131 THRU 111333)
No. Description Unit Qty Unit Price Ext Price
1131 REMOVE CURB AND GUTTER LF 4484 $6.20 $27,800.80
1132 REMOVE CONCRETE DRIVEWAY SF 3349 $2.90 $9,712.10
1133 REMOVE ASPHALT DRIVEWAY SF 135 $17.50 $2,362.50
1 B4 REMOVE EXISTING SIGN EA 29 $75.00 $2,175.00
1135 SAWCUT EXISTING ASPHALT AND LF 910 $7.80 $7,098.00
CONCRETE
1136 STREET EXCAVATION(1' B.O.C. -2' SY 12850 $12.00 $154,200.00
APPROX.AVG. DEPTH)
1137 12"SUBGRADE PREPARATION(1' B.O.C.) SY 12850 $2.00 $25,700.00
1138 TX-5 GEOGRID(1' B.O.C.) SY 12850 $3.80 $48,830.00
1139 11"CRUSHED LIMESTONE BASE(TYPE A, SY 12850 $25.00 $321,250.00
GRADE 1-2)
11310 PRIME COAT(MC-30)(0.15 GALLON/SY) GAL 1928 $5.90 $11,375.20
11311 3"TYPE'B' HMAC BASE COURSE SY 11386 $20.00 $227,720.00
11312 2"TYPE'D' HMAC FINAL COURSE SY 11386 $12.75 $145,171.50
11313 2" MILLING OF EXISTING HMAC(SANTA SY 1021 $9.30 $9,495.30
FE STREET)
11314 2"TYPE'D' HMAC OVERLAY(SANTA FE SY 1021 $18.25 $18,633.25
STREET)
11315 PRIME COAT(MC-30)(0.15 GALLON/SY) GAL 153 $7.20 $1,101.60
11316 FULL DEPTH PAVEMENT REPAIR SY 464 $84.00 $38,976.00
11317 CONCRETE DRIVEWAY SF 3987 $14.25 $56,814.75
E13090 Morgan Ave.from S.Staples St.to Ocean Drive(Bond 2014) Report Created On:5/17/2019 4:06:42 PM
11318 REFLECTIVE PAVEMENT MARKINGS TY. 1 LF 351 $15.00 $5,265.00
(W)(24"X9')(SLD)(100 MIL)-
CROSSWALK
11319 REFLECTIVE PAVEMENT MARKINGS TY. 1 LF 267 $17.50 $4,672.50
(W)(24")(SLD)(100 MIL)-STOP BAR
1 B20 REFLECTIVE PAVEMENT MARKINGS TY.1 LF 38 $25.00 $950.00
(W)(8")(SLD)(100 MIL)
1 B21 REFLECTIVE PAVEMENT MARKINGS TY. 1 LF 3485 $1.10 $3,833.50
(Y)(4")(SLD)(100 MIL)
1 B22 REFLECTIVE PAVEMENT MARKINGS TY. 1 LF 914 $1.10 $1,005.40
(W)(4")(BKN)(100 MIL)
1 B23 RAISED REFLECTIVE PAVEMENT EA 52 $6.20 $322.40
MARKINGS(TYII-A-A)YELLOW
1 B24 RAISED REFLECTIVE PAVEMENT EA 16 $6.20 $99.20
MARKINGS(TYII-B-B) BLUE
1 B25 RAISED REFLECTIVE PAVEMENT EA 56 $6.20 $347.20
MARKINGS(TYII-C-R)WHITE/RED
1 B26 PREFABRICATED PAVEMENT MARKINGS EA 2 $680.00 $1,360.00
TY.1 (W)(WORD)"ONLY"(100 MIL)
1 B27 COMBO STOP SIGN(R1-1) EA 7 $1,100.00 $7,700.00
(30"X30")/STREET NAME SIGN(INCL.
METAL POLE AND FOUNDATION)
1 B28 SPEED LIMIT SIGN(R2-1)(24"X30")(INCL. EA 2 $680.00 $1,360.00
METAL POLE AND FOUNDATION)
1 B29 COMBO NO PARKING SIGN(R8-3) EA 28 $690.00 $19,320.00
(24"X30")/R7-202TP(RED)(INCL. METAL
POLE AND FOUNDATION)
1 B30 NO TRUCKS SIGN(R5-2)(INCLUDING EA 2 $680.00 $1,360.00
METAL POLE AND FOUNDATION)
1 B31 "T" INTERSECTION SIGN(W2-4) EA 1 $680.00 $680.00
(INCLUDING METAL POLE AND
FOUNDATION)
1 B32 "ON OCEAN DRIVE" PLAQUE EA 1 $680.00 $680.00
1 B33 ALLOWANCE FOR UNANTICIPATED LS 1 $25,000.00 $25,000.00
STREET IMPROVEMENTS
Sub Total: $1,182,371.20
PART 1C-RTA IMPROVEMENTS(ITEMS 1C1 THRU 1C2)
E13090 Morgan Ave.from S.Staples St.to Ocean Drive(Bond 2014) Report Created On:5/17/2019 4:06:42 PM
No. Description Unit Qty Unit Price Ext Price
1C1 CONCRETE BUS PADS SY 220 $140.00 $30,800.00
1C2 CONCRETE SHELTER PAD SF 600 $28.00 $16,800.00
Sub Total: $47,600.00
PART 1D-ADA IMPROVEMENTS(1D1 THRU 1D6)
No. Description Unit Qty Unit Price Ext Price
1D1 REMOVE EXISTING CONCRETE SF 16416 $2.60 $42,681.60
SIDEWALK
1D2 5'CONCRETE PEDESTRIAN SIDEWALK SF 14333 $9.60 $137,596.80
1D3 CONCRETE CURB RAMP SF 4240 $15.25 $64,660.00
1 D4 SIDEWALK RETAINING CURB LF 195 $62.00 $12,090.00
1D5 SIDEWALK DRAIN EA 1 $4,000.00 $4,000.00
1D6 ALLOWANCE FOR UNANTICIPATED ADA LS 1 $5,000.00 $5,000.00
IMPROVEMENTS
Sub Total: $266,028.40
PART 1E-DRAINAGE(1E1 THRU 1E30)
No. Description Unit Qty Unit Price Ext Price
1E1 REMOVE EXISTING STORM WATER EA 10 $1,800.00 $18,000.00
MANHOLE
1 E2 REMOVE EXISTING STORM WATER INLET EA 22 $1,600.00 $35,200.00
1 E3 REMOVE EXISTING 12" RCP LF 737 $110.00 $81,070.00
1 E4 REMOVE EXISTING 15" RCP LF 335 $72.00 $24,120.00
1 E5 REMOVE EXISTING 18" RCP LF 160 $90.00 $14,400.00
1 E6 REMOVE EXISTING 36" RCP LF 1200 $81.00 $97,200.00
1 E7 REMOVE EXISTING 54" RCP LF 975 $21.00 $20,475.00
1 E8 REMOVE EXISTING 54"TO 6'X 6' EA 1 $7,500.00 $7,500.00
TRANSITION
1 E9 REMOVE EXISTING 6'X 4' RCB TO 36" EA 1 $7,500.00 $7,500.00
RCP TRANSITION
1E10 15"CLASS III RCP LF 66 $180.00 $11,880.00
1E11 18"CLASS III RCP LF 546 $170.00 $92,820.00
E13090 Morgan Ave.from S.Staples St.to Ocean Drive(Bond 2014) Report Created On:5/17/2019 4:06:42 PM
1E12 30"CLASS III RCP LF 279 $230.00 $64,170.00
1E13 6'X 4' PRECAST CONCRETE BOX LF 1903 $540.00 $1,027,620.00
1E14 6'X 6' PRECAST CONCRETE BOX LF 268 $520.00 $139,360.00
1E15 PIPE TRENCH SAFETY LF 3062 $6.00 $18,372.00
1E16 4' DIAMETER TY'A' MANHOLE EA 7 $4,600.00 $32,200.00
1E17 3'X3' MANHOLE RISER EA 8 $5,400.00 $43,200.00
1E18 5'X 8'-2"JUNCTION BOX/MANHOLE EA 5 $13,700.00 $68,500.00
1E19 5'CURB INLET EA 21 $3,900.00 $81,900.00
1 E20 5'CURB INLET(TYPE 3) EA 1 $4,400.00 $4,400.00
1 E21 MANHOLE/JUNCTION BOX/CURB INLET EA 42 $180.00 $7,560.00
TRENCH SAFETY
1 E22 TIE EXISTING 12" RCP INTO PROPOSED EA 2 $920.00 $1,840.00
4' DIAMETER MANHOLE
1 E23 TIE EXISTING 15" RCP INTO PROPOSED EA 2 $920.00 $1,840.00
15" RCP
1 E24 TIE EXISTING 18" RCP INTO PROPOSED EA 3 $1,400.00 $4,200.00
4' DIAMETER MANHOLE
1 E25 TIE EXISTING 30" RCP INTO PROPOSED EA 1 $1,900.00 $1,900.00
JUNCTION BOX
1 E26 TIE PROPOSED 18" RCP INTO EXISTING EA 2 $1,400.00 $2,800.00
CURB INLET
1 E27 TIE PROPOSED 6'X 4' RCB INTO EA 1 $4,700.00 $4,700.00
EXISTING JUNCTION BOX
1 E28 TIE PROPOSED 6'X 6' RCB INTO EA 1 $4,600.00 $4,600.00
EXISTING JUNCTION BOX
1 E29 STD. 6"CURB AND GUTTER LF 4427 $24.00 $106,248.00
1 E30 ALLOWANCE FOR UNANTICIPATED LS 1 $25,000.00 $25,000.00
DRAINAGE IMPROVEMENTS
Sub Total: $2,050,575.00
PART 1F-WATER IMPROVEMENTS(1F1 THRU 1F33)
No. Description Unit Qty Unit Price Ext Price
1F1 REMOVE AND SALVAGE EXISTING FIRE EA 4 $460.00 $1,840.00
HYDRANT
1F2 REMOVE WATER METER EA 4 $350.00 $1,400.00
E13090 Morgan Ave.from S.Staples St.to Ocean Drive(Bond 2014) Report Created On:5/17/2019 4:06:42 PM
1 F3 REMOVE EXISTING 3/4"COPPER LF 139 $10.00 $1,390.00
WATERLINE
1 F4 REMOVE EXISTING 6"ACP WATERLINE LF 109 $82.00 $8,938.00
1 F5 REMOVE EXISTING 8"ACP WATERLINE LF 578 $82.00 $47,396.00
1 F6 REMOVE EXISTING 10"ACP WATERLINE LF 2140 $71.00 $151,940.00
1 F7 REMOVE EXISTING 12"ACP WATERLINE LF 114 $80.00 $9,120.00
1 F8 3/4" PE WATER SERVICE(INCL. SERVICE LF 164 $57.00 $9,348.00
SADDLE,CORP.STOP, PE,AND
RECONNECTION)
1F9 WATER METER ASSEMBLY EA 4 $1,300.00 $5,200.00
1 F10 6"C900 PVC WATERLINE LF 462 $68.00 $31,416.00
1 F11 8"C900 PVC WATERLINE LF 634 $71.00 $45,014.00
1 F12 12"C900 PVC WATERLINE LF 2193 $65.00 $142,545.00
1 F13 PIPE TRENCH SAFETY LF 3289 $2.80 $9,209.20
1 F14 8" DI 450 BEND EA 16 $330.00 $5,280.00
1 F15 8" DI 22.50 BEND EA 1 $300.00 $300.00
1 F16 8" DI 11.250 BEND EA 3 $300.00 $900.00
1 F17 8"GATE VALVE&BOX EA 10 $2,100.00 $21,000.00
1 F18 12" DI 450 DI BEND EA 5 $580.00 $2,900.00
1 F19 12" DI 22.50 DI BEND EA 1 $580.00 $580.00
1 F20 12" DI 11.250 DI BEND EA 2 $580.00 $1,160.00
1 F21 12"GATE VALVE&BOX EA 6 $3,200.00 $19,200.00
1 F22 12"X 16" DI CROSS EA 1 $2,000.00 $2,000.00
1 F23 12"X10" REDUCER EA 1 $450.00 $450.00
1 F24 12"X 8" DI CROSS EA 4 $1,200.00 $4,800.00
1 F25 12"X 8" DI TEE EA 2 $330.00 $660.00
1 F26 12"X 6' DI CROSS EA 8 $180.00 $1,440.00
1 F27 ADJUST 12"WATERLINE(INCL. DIP EA 1 $11,100.00 $11,100.00
WATERLINE&ALL REQ'D FITTINGS)
1F28 FIRE HYDRANT ASSEMBLY(TYPE 1) EA 16 $4,400.00 $70,400.00
1 F29 CONNECTTO EXIST. 16" PVC WATERLINE EA 2 $2,800.00 $5,600.00
(INCL.ALL REQ'D FITTINGS)
E13090 Morgan Ave.from S.Staples St.to Ocean Drive(Bond 2014) Report Created On:5/17/2019 4:06:42 PM
1 F30 CONNECTTO EXISTING 12" PVC EA 2 $2,800.00 $5,600.00
WATERLINE(INCL.ALL REQ'D FITTINGS)
1 F31 CONNECT TO EXISTING 10"ACP EA 1 $2,100.00 $2,100.00
WATERLINE(INCL.ALL REQ'D FITTINGS)
WITH OMNI COUPLING SYSTEM
1 F32 CONNECT TO EXISTING 8"ACP EA 10 $2,500.00 $25,000.00
WATERLINE(INCL.ALL REQ'D FITTINGS)
WITH OMNI COUPLING SYSTEM
1 F33 ALLOWANCE FOR UNANTICIPATED LS 1 $20,000.00 $20,000.00
WATER IMPROVEMENTS
Sub Total: $665,226.20
PART 1G-WASTEWATER IMPROVEMENTS(1G1 THRU 1G22)
No. Description Unit Qty Unit Price Ext Price
1G1 REMOVE EXISTING 6"VCP WASTEWATER LF 772 $40.00 $30,880.00
LINE
1G2 REMOVE EXISTING 8"VCP WASTEWATER LF 54 $45.00 $2,430.00
LINE
1G3 REMOVE EXISTING 21"VCP LF 54 $120.00 $6,480.00
WASTEWATER LINE
1G4 REMOVE EXISTING 24"VCP LF 56 $120.00 $6,720.00
WASTEWATER LINE
1G5 REMOVE EXISTING WASTEWATER EA 7 $2,100.00 $14,700.00
MANHOLE
1G6 6" PVC(SDR 26)WASTEWATER LINE(0'-6' LF 581 $110.00 $63,910.00
DEPTH)
1G7 6" PVC(SDR 26)WASTEWATER LINE(6'-8' LF 95 $93.00 $8,835.00
DEPTH)
1G8 6" PVC(SDR 26)WASTEWATER LINE(8'- LF 96 $110.00 $10,560.00
10' DEPTH)
1G9 8" PVC(SDR 26)WASTEWATER LINE(0'-6' LF 54 $120.00 $6,480.00
DEPTH)
1G10 24" PVC(SDR 26)WASTEWATER LINE LF 54 $210.00 $11,340.00
(18'-20' DEPTH)
1G11 PIPE TRENCH SAFETY LF 880 $3.30 $2,904.00
1G12 4' DIAMETER MANHOLE EA 13 $8,800.00 $114,400.00
1G13 5' DIAMETER MANHOLE EA 2 $9,100.00 $18,200.00
E13090 Morgan Ave.from S.Staples St.to Ocean Drive(Bond 2014) Report Created On:5/17/2019 4:06:42 PM
1G14 TRENCH SAFETY FOR WASTEWATER EA 15 $3.30 $49.50
MANHOLES
1G15 4' DIAMETER MANHOLE EXTRA DEPTH(> VF 8 $500.00 $4,000.00
6')
1G16 5' DIAMETER MANHOLE EXTRA DEPTH(> VF 28 $500.00 $14,000.00
6')
1G17 CONNECT EXISTING 6"WASTEWATER EA 8 $4,700.00 $37,600.00
LINE TO PROPOSED WASTEWATER
MANHOLE
1G18 CONNECT EXISTING 8"WASTEWATER EA 2 $5,300.00 $10,600.00
LINE TO PROPOSED WASTEWATER
MANHOLE
1G19 CONNECT EXISTING 21"WASTEWATER EA 1 $7,000.00 $7,000.00
LINE TO PROPOSED WASTEWATER
MANHOLE
1G20 CONNECT EXISTING 24"WASTEWATER EA 1 $7,000.00 $7,000.00
LINE TO PROPOSED WASTEWATER
MANHOLE
1 G21 WASTEWATER BYPASS OPERATIONS LS 1 $45,500.00 $45,500.00
1G22 ALLOWANCE FOR UNANTICIPATED LS 1 $10,000.00 $10,000.00
WASTEWATER IMPROVEMENTS
Sub Total: $433,588.50
PART 11H-GAS IMPROVEMENTS(1 H1 THRU 111-112)
No. Description Unit Qty Unit Price Ext Price
11-11 ADJUST EXISTING GAS VALVE BOXES TO EA 4 $500.00 $2,000.00
MATCH PROPOSED PAVEMENT
11-12 ALLOWANCE FOR UNANTICIPATED GAS LS 1 $5,000.00 $5,000.00
IMPROVEMENTS
Sub Total: $7,000.00
PART 11- I.T. INFRASTRUCTURE IMPROVEMENTS(111 THRU 113)
No. Description Unit Qty Unit Price Ext Price
111 PULL BOX FOR 2" I.T. EA 3 $3,600.00 $10,800.00
112 2" BLANK I.T. CONDUIT LF 2221 $12.50 $27,762.50
113 ALLOWANCE FOR UNANTICIPATED I.T. LS 1 $5,000.00 $5,000.00
INFRASTRUCTURE IMPROVEMENTS
E13090 Morgan Ave.from S.Staples St.to Ocean Drive(Bond 2014) Report Created On:5/17/2019 4:06:42 PM
Sub Total: $43,562.50
Part 1J - ADDITIVE ALTERNATE NO. 1 STAPLES ST.TRAFFIC SIGNAL REPLACEMENT(1J1)
No. Description Unit Qty Unit Price Ext Price
1J1 ALLOWANCE FOR STAPLES ST.TRAFFIC LS 1 $300,000.00 $300,000.00
SIGNAL REPLACEMENT
Sub Total: $300,000.00
PART 1 K-ADDITIVE ALTERNATE NO.2 SANTA FE TRAFFIC SIGNAL REPLACEMENT(1 K1)
No. Description Unit Qty Unit Price Ext Price
1K1 ALLOWANCE FOR SANTA FE TRAFFIC LS 1 $300,000.00 $300,000.00
SIGNAL REPLACEMENT
Sub Total: $300,000.00
PART 1 L-ADDITIVE ALTERNATE NO.3 3rd ST.TRAFFIC SIGNAL REPLACEMENT(1111-11)
No. Description Unit Qty Unit Price Ext Price
11-1 ALLOWANCE FOR 3RD ST.TRAFFIC LS 1 $300,000.00 $300,000.00
SIGNAL REPLACEMENT
Sub Total: $300,000.00
E13090 Morgan Ave.from S.Staples St.to Ocean Drive(Bond 2014) Report Created On:5/17/2019 4:06:42 PM
ACKNOWLEDGE ADDENDA
NAME ACKNOWLEDGEMENT DATE
E13090 Addendum No. 1 05/17/2019 8:34:51 AM
Addendum No. 2 05/17/2019 8:34:52 AM
Addendum No. 3 05/17/2019 8:34:53 AM
E13090 Morgan Ave.from S.Staples St.to Ocean Drive(Bond 2014) Report Created On:5/17/2019 4:06:42 PM
REQUIRED DOWNLOADS
TYPE NAME DOWNLOAD DATE
Bid Docs E13090 Specifications 5/17/2019 8:35:36 AM
Plans E13090 Plans 5/17/2019 8:35:43 AM
Addenda E13090 Addendum No. 1 5/6/2019 8:32:22 AM
Addenda Addendum No. 2 5/13/2019 10:36:26 AM
Addenda Addendum No. 3 5/16/2019 6:53:54 AM
Bidders Pre Bid Attendance Roster 5/17/2019 8:35:50 AM
ADDENDUM NO. 2
ATTACHMENT 2
Sheet 1 of 6
00 30 00 BID ACKNOWLEDGEMENT FORM
ARTICLE 1—BID RECIPIENT
1.01 In accordance with the Drawings, Specifications, and Contract Documents, this Bid Proposal is
submitted by Berry Contracting, LP dba Bay Ltd. (type or print name of
company) on: 10:00 A.M. on Friday, May 17, 2019 for Project#E13090 and Morgan Ave. From
Staples Street To Ocean Drive(Bond 2014).
1.02 Submit Bids, Bid Security and all attachments to the Bid (See Section 7.01 below) to the City's
electronic bidding website at www.CivCastUSA.com.
To submit the original bid security or if submitting hard copy bids, please send to:
The City of Corpus Christi,Texas
City Secretary's Office
1201 Leopard Street
Corpus Christi,Texas 78401
Attention: City Secretary
Bid- Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No.E13090.
All envelopes and packages(including FEDEX envelopes)must clearly identify, on the OUTSIDE
of the package,the project name and number and that bid documents are enclosed.
ARTICLE 2—BIDDERS'S ACKNOWLEDGMENTS
2.01 Bidder proposes and agrees,if this Bid is accepted,to enter into an Agreement with Owner on the
form included in the Contract Documents,to perform all Work specified or indicated in Contract
Documents for the Contract Price indicated in this Bid or as modified by Contract Amendment.
Bidder agrees to complete the Work within the Contract Times established in the Agreement or
as modified by Contract Amendment and comply with the all other terms and conditions of the
Contract Documents.
2.02 Bidder accepts all of the terms and conditions of SECTION 00 21 13 INVITATION TO BID AND
INSTRUCTIONS TO BIDDERS, including those dealing with required Bonds. The Bid will remain
subject to acceptance for 90 days after the opening of Bids.
2.03 Bidder acknowledges that Owner, at its discretion,will correct mathematical errors contained in
the Bid and will conform bid items in accordance with SECTION 01 29 01 MEASUREMENT AND
BASIS FOR PAYMENT.
2.04 Bidder accepts the provisions of the Agreement as to liquidated damages in the event of its failure
to complete Work in accordance with the schedule set forth in the Agreement.
2.05 Bidder acknowledges receipt of the following Addenda:
Bid Acknowledgement Form 003000-1
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
ADDENDUM NO. 2
ATTACHMENT 2
Sheet 2 of 6
Addendum No. Addendum Dat Signature Acknowledging Receipt
1 4/25/2019
2 5/13/2019
3 5/13/2019
ARTICLE 3—BIDDER'S REPRESENTATIONS
3.01 The Bidder has examined and carefully studied the Contract Documents and the other related
data identified in the Bidding Documents.
3.02 The Bidder has visited the Site and become familiar with and is satisfied as to the general, local,
and Site conditions that may affect cost, progress,and performance of the Work.
3.03 The Bidder is familiar with Laws and Regulations that may affect cost, progress,and performance
of the Work.
3.04 The Bidder has carefully studied the following Site-related reports and drawings as identified in
the Supplementary Conditions:
A. Geotechnical Data Reports regarding subsurface conditions at or adjacent to the Site;
B. Drawings of physical conditions relating to existing surface or subsurface structures at the
Site;
C. Underground Facilities referenced in reports and drawings;
D. Reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent
to the Site; and
E. Technical Data related to each of these reports and drawings.
3.05 The Bidder has considered the:
A. Information known to Bidder;
B. Information commonly known to contractors doing business in the locality of the Site;
C. Information and observations obtained from visits to the Site; and
D. The Contract Documents.
3.06 The Bidder has considered the items identified in Paragraphs 3.04 and 3.05 with respect to the
effect of such information,observations,and documents on:
A. The cost, progress, and performance of the Work;
B. The means, methods, techniques, sequences, and procedures of construction to be
employed by Bidder; and
C. Bidder's safety precautions and programs.
3.07 Based on the information and observations referred to in the preceding paragraphs, Bidder agrees
that no further examinations,investigations,explorations,tests,studies,or data are necessary for
Bid Acknowledgement Form 003000-2
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014),Project No. E13090 Rev 10/2018
ADDENDUM NO. 2
ATTACHMENT 2
Sheet 3 of 6
the performance of the Work at the Contract Price,within the Contract Times,and in accordance
with the other terms and conditions of the Contract Documents.
3.08 The Bidder is aware of the general nature of Work to be performed by Owner and others at the
Site that relates to the Work as indicated in the Contract Documents.
3.09 The Bidder has correlated the information known to the Bidder, information and observations
obtained from visits to the Site, reports and drawings identified in the Contract Documents, and
all additional examinations,investigations,explorations,tests,studies,and data with the Contract
Documents.
3.10 The Bidder has given the OAR written notice of all conflicts,errors, ambiguities,or discrepancies
that the Bidder has discovered in the Contract Documents, and the written resolution provided
by the OAR is acceptable to the Bidder.
3.11 The Contract Documents are generally sufficient to indicate and convey understanding of all terms
and conditions for performance and furnishing of the Work.
3.12 Bidder's entry into this Contract constitutes an incontrovertible representation by Bidder that
without exception all prices in the Agreement are premised upon performing and furnishing the
Work required by the Contract Documents.
3.13 As required by Chapter 2270, Texas Government Code, Bidder hereby verifies that it does not
boycott Israel and will not boycott Israel through the term of this Contract. For purposes of this
verification, "boycott Israel" means refusing to deal with,terminating business activities with,or
otherwise taking any action that is intended to penalize, inflict economic harm on, or limit
commercial relations specifically with Israel,or with a person or entity doing business in Israel or
in an Israeli-controlled territory, but does not include an action made for ordinary business
purposes.
ARTICLE 4—BASIS OF BID
4.01 Bidder will complete the Work in accordance with the Contract Documents for:
Base Bid $ 5, �g 17714. '60
Add Alternate 1 $ 100 Poo . 0 0
Add Alternate 2 $ .10
0 0 0 p . 0 0
Add Alternate 3 $ 1001000 , 00
A. The Bidder selected for award of the Contract will be the Lowest Responsible Bidder that
submits a responsive Bid. Owner will, at its discretion, award the contract to the lowest
responsible Bidder for the Base Bid, plus any combination of Add or Deduct Alternates.
Bidder acknowledges that the estimated quantities are not guaranteed, and final payment
for all Unit Price items will be based on actual quantities provided, measured as provided in
the Contract Documents.
Bid Acknowledgement Form 003000-3
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014),Project No.E13090 Rev 10/2018
ADDENDUM NO. 2
ATTACHMENT 2
Sheet 4 of 6
ARTICLE 5—EVALUATION OF BIDDERS
5.01 The Owner will consider the amount bid, the Bidder's responsibility, the Bidder's safety record,
the Bidder's indebtedness to Owner and whether the Bidder has met the minimum specific
project experience requirements to determine the lowest responsive, responsible Bidder. The
Owner reserves the right to waive any and all irregularities in determining the Bidders'
responsibility or value,and whether the Bidder has met the minimum specific project experience
requirements, and reserves the right to require the submission of additional information.
5.02 The Owner has the right to accept a Bid, reject any and all Bids,to waive any and all irregularities
in the Bids, correct mathematical errors or to reject non-conforming, non-responsive or
conditional Bids. In addition,the Owner reserves the right to reject any Bid where circumstances
and developments have,in the opinion of the Owner,changed the responsibility of the Bidder.
5.03 Material misstatements in the documentation submitted to determine the Bidder's responsibility,
including information submitted per SECTION 00 45 16 STATEMENT OF EXPERIENCE, may be
grounds for rejection of the Bidder's Bid on this Project. Any such misstatement, if discovered
after award of the Contract to such Bidder, may be grounds for immediate termination of the
Contract. Additionally,the Bidder will be liable to the Owner for any additional costs or damages
to the Owner resulting from such misstatements, including costs and attorney's fees for collecting
such costs and damages.
ARTICLE 6—TIME OF COMPLETION
6.01 Bidder will complete the Work required to be substantially completed within 550 days after the
date when the Contract Times commence to run as provided in Paragraph 4.01 of the General
Conditions. Bidder will complete the Work required for final payment in accordance with
Paragraph 17.16 of the General Conditions within 580 days after the date when the Contract
Times commence to run.
6.02 Bidder agrees that the.Work will be substantially complete and will be completed and ready for
final payment in accordance with Paragraph 17.16 of the General Conditions within the number
of days indicated in Section 00 30 01 BID FORM.
ARTICLE 7—ATTACHMENTS TO THIS BID
In compliance with the Bid Requirements in SECTION 00 2113 INVITATION TO BID AND INSTRUCTIONS TO
BIDDERS,the following are made a condition of this Bid:
A. Bid Security.
B. SECTION 00 30 00 BID ACKNOWLEDGEMENT FORM and documentation of signatory
authority.
C. SECTION 00 30 01 BID FORM.
D. SECTION 00 30 02 COMPLIANCE TO STATE LAW ON NONRESIDENT BIDDERS.
E. SECTION 00 30 05 DISCLOSURE OF INTEREST.
F. SECTION 00 30 06 NON-COLLUSION CERTIFICATION.
G. SECTION 00 45 16 STATEMENT OF EXPERIENCE
Bid Acknowledgement Form 003000-4
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014),Project No.E13090 Rev 10/2018
ADDENDUM NO. 2
ATTACHMENT 2
Sheet 5 of 6
ARTICLE 8—DEFINED TERMS
8.01 The terms used in this Bid have the meanings indicated in the General Conditions and the
Supplementary Conditions. The significance of terms with initial capital letters is described in the
General Conditions.
ARTICLE 9—VENUE
9.01 Bidder agrees that venue shall lie exclusively in Nueces County,Texas for any legal action.
ARTICLE 10—ETHICAL BEHAVIOR
10.01 Bidder certifies that Bidder's officers,employees and agents will not attempt to lobby or influence
a vote or recommendation related to this Bid, directly or indirectly,through any contact with City
Council members or other City officials from the date the Bid is submitted to the City until a
Contract is executed by the City Manager or designee, except that comments are allowed to be
made at a public meeting held under the Texas Open Meetings Act.
ARTICLE 11—SIGNATORY REQUIREMENTS FOR BIDDERS
11.01 Bidders must include their correct legal name, state of residency, and federal tax identification
number in the Bid Form.
11.02 The Bidder, or the Bidder's authorized representative, shall sign and date the Bid Form to
accompany all materials included in the submitted Bid. Bids which are not signed and dated in
this manner, or which do not contain the required documentation of signatory authority may be
rejected as non-responsive. The individual(s)signing the Bid must have the authority to bind the
Bidder to a contract,and if required,shall attach documentation of signatory authority to the Bid
Form.
11.03 Bidders who are individuals ("natural persons" as defined by the Texas Business Organizations
Code §1.002), but who will not be signing the Bid Form personally, shall include in their bid a
notarized power of attorney authorizing the individual designated as their authorized
representative to submit the Bid and to sign on behalf of the Bidder.
11.04 Bidders that are entities who are not individuals shall identify in their Bid their charter or
Certificate of Authority number issued by the Texas Secretary of State and shall submit with their
Bid a copy of a resolution or other documentation approved by the Bidder's governing body
authorizing the submission of the Bid and designating the individual(s) authorized to execute
documents on behalf of the Bidder. Bidders using an assumed name (an "alias") shall submit a
copy of the Certificate of Assumed Name or similar document.
11.05 Bidders that are not residents of the State of Texas must document their legal authority to
conduct business in Texas. Nonresident Bidders that have previously registered with the Texas
Secretary of State may submit a copy of their Certificate of Authority. Nonresident Bidders that
have not previously registered with the Texas Secretary of State shall submit a copy of the Bidder's
enabling documents as filed with the state of residency,or as otherwise existing.
Bid Acknowledgement Form 003000-5
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014),Project No. E13090 Rev 10/2018
ADDENDUM NO. 2
ATTACHMENT 2
Sheet 6 of 6
ARTICLE 12—BID SUBMITTAL
12.01 This Bid is submitted by:
Bidder: Berry Contracting,LP dba Bay Ltd.
(typed or printed full legal name of Bidder)
By: V, cr n NA { .
(in ' 'dual'ssignature)
Name: Jon Lentz
(typed or printed)
Title: Estimating Manager
(typed or printed)
Attest:
(individual's signature)
State of Residency: Texas
Federal Tax Id. No. 74-2982901
Address for giving notices: Bay Ltd.
1414 Valero Way
Corpus Christi, TX 78409
Phone: (361)693-2100(main#) Email: lentzj@bayltd.com
(Attach evidence of authority to sign if the authorized individual is not the Bidder, but an
individual signing on behalf of another individual Bidder, or if the authorized individual is a
representative of a corporation, partnership,or joint venture.)
END OF SECTION
Bid Acknowledgement Form 003000-6
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
SPECIAL MEETING OF MANAGERS
BERRY OPERATING COMPANY,LLC
February 1,2017
Berry Operating Company,LLC, general partner of Berry Contracting,LP,dba
Bay Ltd.held a special meeting this lst day of February 2017. Edward A.Martin,
President,presided as Chairman of the meeting and DonEtta Beaty served as Secretary.
All managers were present and waived notice of call and purpose of meeting. Mr.
Martin said the purpose of the meeting was to name the individuals authorized to act for
and on behalf of Bay Ltd.,Highway Division in connection with matters relating to the
Texas Department of Transportation and other state,municipal,federal,quasi-
governmental entities and private bodies.
RESOLVED that the following named individuals be empowered to act �
for and on behalf of Bay Ltd. as to the making and signing of contracts,
bonds,bids, offers or other arrangements and revisions,changes or
modification of same as the needs of the company may require.
K. J. Luhan President
D. W.Berry Vice President
M. G.Bevy Vice President
A. L, Berry Vice President
Edward A. Martin Vice President
Robert C. Blair Vice President
Diane DeCou Vice President and CFO
Kevin Stone Vice President
FURTHER RESOLVED that Mr.Jon Lentz is empowered to sign
contracts,bonds, bids, offers, or arrangements and revisions, changes or
modification of same as the needs of the Highway Division of Bay Ltd.
may require,hereby ratifying and affirming all such acts.
l
FURTHER RESOLVED that Kevin Stone,Vice President and Jon Lentz,
Estimating Manager are specifically empowered to act for and on behalf of
Bay Ltd.to sign"Proposal to the Texas Department of Transportation".
FURTHER RESOLVED that the Secretary be and is herein authorized and
directed to furnish a certified copy hereof to any interested parties with the
knowledge that such parties will rely upon same until actual receipt of
written notice of change,deletion,modification, or revocation of such
authority.
i
i
Berry Operating Company LLC
Special Meeting,February 1, 2017
Page 2
Approysad Correct:
I
5dward A. Ma ,President
i
Attest: I
i
i
i
DonEtta Beaty, Secretar j
Certification
t
1,DonEtta Beaty, Secretary of Berry Operating Company,LLC certify that the above are
minutes of a special meeting of the Managers of Berry Operating Company, LLC
general partner of Berry Contracting LP,dba Bay Ltd.,held on the date shown above
and that such resolution was validly adopted at the Managers meeting at which a quorum
was present and such resolution is a continuing resolution and is presently valid and in
full force and effect this 1St day of February 2017,to which witness my hand.
DonEtta Beaty, Secretar
{
I�
i
f�
i
i
BID BOND
KNOW ALL MEN BY THESE PRESENTS,that we BERRY CONTRACTING, LP DBA BAY LTD.
as Principal, hereinafter called the Principal,and CONTINENTAL CASUALTY COMPANY
a corporation duly organized under the laws of the State of ILLINOIS as Surety, hereinafter
called the Surety, are held and firmly bound unto CITY OF CORPUS CHRISTI
as Obligee, hereinafter called the Obligee, in the sum of
FIVE PERCENT OF THE GREATEST AMOUNT BID Dollars( 5% G.A.B. )
for the payment of which sum well and truly to be made, the said Principal and the said Surety, bind ourselves,our heirs,executors,
administrators, successors and assigns,jointly and severally, firmly by these presents.
WHEREAS, the Principal has submitteda bid for MORGAN AVE. FROM STAPLES STREET TO OCEAN DRIVE(BOND 2014)
PROJECT NO. E13090
NOW,THEREFORE,if the Obligee shall accept the bid of the Principal and the Principal shall enter into a Contract with the Obligee in
accordance with the terms of such bid, and give such bond or bonds as may be specified in the bidding or Contract Documentswith
good and sufficient surety for the faithful performance of such Contract and for the prompt payment of labor and material furnished in
the prosecution thereof, or in the event of the failure of the Principal to enter such Contract and give such bond or bonds, if the
Principal shall pay to the Obligee the difference not to exceed the penalty hereof between the amount specified in said bid and such
larger amount for which the Obligee may in good faith contract with another party to perform the Work covered by said bid, then this
obligation shall be null and void, otherwise to remain in full force and effect.
Signed and sealed this 1ST day of MAY 2019
BERRY CONTRACTING, LP DBA BAY LTD.
(Principal) (Seal)
(Witnes By.
-31(Title)
CONTINENTAL CASUALTY COMPANY
11L ac, //Z (Surety)�� (Seal)
( ess)
(Title)
MARY EN MOORE, ATTY IN FACT
Printed in cooperation withthe American Institute of Architects(AIA)by the CNA Insurance Companies.
The language in this document conforms exactly to the language used in AIA Document A310-Bid Bond-February 1970 Edition.
G-108041-A
POWER OF ATTORNEY APPOINTING INDIVIDUAL ATTORNEY-IN-FACT
Know All Men By These Presents,That Continental Casualty Company,an Illinois insurance company,National Fire Insurance Company of
Hartford,an Illinois insurance company,and American Casualty Company of Reading,Pennsylvania,a Pennsylvania insurance company(herein called
"the CNA Companies"),are duly organized and existing insurance companies having their principal offices in the City of Chicago,and State of Illinois,
and that they do by virtue of the signatures and seals herein affixed hereby make,constitute and appoint
Mary Ellen Moore,Steve Addkison,Cathleen Hayles,Aaron J Endris,Tricia Balolong,Individually
i
of Corpus Christi,TX,their true and lawful Attorney(s)-in-Fact with full power and authority hereby conferred to sign,seal and execute for and on their
behalf bonds,undertakings and other obligatory instruments of similar nature
-In Unlimited Amounts-
and to bind them thereby as fully and to the same extent as if such instruments were signed by a duly authorized officer of their insurance companies and
all the acts of said Attorney,pursuant to the authority hereby given is hereby ratified and confirmed.
This Power of Attorney is made and executed pursuant to and by authority of the By-Law and Resolutions,printed on the reverse hereof,duly
adopted,as indicated,by the Boards of Directors of the insurance companies.
In Witness Whereof,the CNA Companies have caused these presents to be signed by their Vice President and their corporate seals to be hereto
affixed on this 26th day of October,2016.
GAS Uq(r %%SURgt, °MPANVO'C Continental Casualty Company
c� ^yc �90 National Fire Insurance Company of Hartford
CORP.RArj� Q� p `N�pRPORgrFo American Cas lty Company of Reading,Pennsylvania
D $; JULY 71,
GV SEAL t$- e 190E
a
1a97 HARD b • ' r
Paul T.Bruflat Vice President
State of South Dakota,County of Minnehaha,ss:
On this 26th day of October,2016,before me personally came Paul T.Bruflat to me known,who,being by me duly sworn,did depose and say: that
he resides in the City of Sioux Falls,State of South Dakota;that he is a Vice President of Continental Casualty Company,an Illinois insurance company,
National Fire Insurance Company of Hartford,an Illinois insurance company,and American Casualty Company of Reading,Pennsylvania,a
Pennsylvania insurance company described in and which executed the above instrument;that he knows the seals of said insurance companies;that the
seals affixed to the said instrument are such corporate seals;that they were so affixed pursuant to authority given by the Boards of Directors of said
insurance companies and that he signed his name thereto pursuant to like authority,and acknowledges same to be the act and deed of said insurance
companies.
J.MOHR
NOTARY PUBLIC
SOUTH DAKOTA S U
My Commission Expires June 23,2021 J.Mohr Notary Public
CERTIFICATE
I,D.Bult,Assistant Secretary of Continental Casualty Company,an Illinois insurance company,National Fire Insurance Company of Hartford,an
Illinois insurance company,and American Casualty Company of Reading,Pennsylvania,a Pennsylvania insurance company do hereby certify that the
Power of Attorney herein above set forth is still in force,and further certify that the By-Law and Resolution of the Board of Directors of the insurance
companies printed on the reverse hereof is still in force. In testimony whereof I have hereunto subscribed my name and affixed the seal of the said
insurance companies this 1 ST day of MAY 2019
G UA(r %4SU1?4MPANYOo Continental Casualty Company
(ooRPOAAre
N ° �" National Fire Insurance Company of Hartford
00NCORPpRA?., American Casualty Company of Reading,Pennsylvania
JULYSEAL `T T'� No a�
1897 HAP
D.Bult Assistant Secretary
Form F6853-4/2012
Authorizing By-Laws and Resolutions
ADOPTED BY THE BOARD OF DIRECTORS OF CONTINENTAL CASUALTY COMPANY:
This Power of Attorney is made and executed pursuant to and by authority of the following resolution duly adopted by the Board of Directorsof the
Company at a meeting held on May 12,1995:
"RESOLVED: That any Senior or Group Vice President may authorize an officer to sign specific documents,agreements and instruments on behalf of
the Company provided that the name of such authorized officer and a description of the documents,agreements or instruments that such officer may sign
will be provided in writing by the Senior or Group Vice President to the Secretary of the Company prior to such execution becoming effective."
This Power of Attorney is signed by Paul T.Bruflat,Vice President,who has been authorized pursuant to the above resolution to execute power of
attorneys on behalf of Continental Casualty Company.
This Power of Attorney is signed and sealed by facsimile under and by the authority of the following Resolution adopted by the Board of Directors of the
Company by unanimous written consent dated the 25th day of April,2012:
"Whereas,the bylaws of the Company or specific resolution of the Board of Directors has authorized various officers(the"Authorized Officers") to
execute various policies,bonds,undertakings and other obligatory instruments of bice nature;and
Whereas,from time to time,the signature of the Authorized Officers,in addition to being provided in original,hard copy format,may be provided via
facsimile or otherwise in an electronic format(collectively,`Electronic Signatures");Now therefore be it resolved: that the Electronic Signature of any
Authorized Officer shall be valid and binding on the Company."
ADOPTED BY THE BOARD OF DIRECTORS OF NATIONAL FIRE INSURANCE COMPANY OF HARTFORD:
This Power of Attorney is made and executed pursuant to and by authority of the following resolution duly adopted by the Board of Directors of the
Company by unanimous written consent dated May 10,1995:
"RESOLVED: That any Senior or Group Vice President may authorize an officer to sign specific documents,agreements and instruments on behalf of
the Company provided that the name of such authorized officer and a description of the documents,agreements or instruments that such officer may sign
will be provided in writing by the Senior or Group Vice President to the Secretary of the Company prior to such execution becoming effective."
This Power of Attorney is signed by Paul T. Bruflat,Vice President,who has been authorized pursuant to the above resolution to execute power of
attorneys on behalf of National fire Insurance Company of Hartford.
This Power of Attorney is signed and sealed by facsimile under and by the authority of the following Resolution adopted by the Board of Directors of the
Company by unanimous written consent dated the 25th day of April,2012:
"Whereas,the bylaws of the Company or specific resolution of the Board of Directors has authorized various officers(the"Authorized Officers")to
execute various policies,bonds,undertakings and other obligatory instruments of bice nature;and
Whereas,from time to time,the signature of the Authorized Officers,in addition to being provided in original,hard copy format,may be provided via
facsimile or otherwise in an electronic format(collectively,`Electronic Signatures';Now therefore be it resolved: that the Electronic Signature of any
Authorized Officer shall be valid and binding on the Company."
ADOPTED BY THE BOARD OF DIRECTORS OF AMERICAN CASUALTY COMPANY OF READING,PENNSYLVANIA:
This Power of Attorney is made and executed pursuant to and by authority of the following resolution duly adopted by the Board of Directors of the
Company by unanimous written consent dated May 10, 1995:
"RESOLVED: That any Senior or Group Vice President may authorize an officer to sign specific documents,agreements-and instruments on behalf of
the Company provided that the name of such authorized officer and a description of the documents,agreements or instruments that such officer may sign
will be provided in writing by the Senior or Group Vice President to the Secretary of the Company prior to such execution becoming effective."
This Power of Attorney is signed by Paul T.Bruflat,Vice President,who has been authorized pursuant to the above resolution to execute power of
attorneys on behalf of American Casualty Company of Reading,Pennsylvania.
This Power of Attorney is signed and sealed by facsimile under and by the authority of the following Resolution adopted by the Board of Directors of the
Company by unanimous written consent dated the 25th day of April,2012:
"Whereas,the bylaws of the Company or specific resolution of the Board of Directors has authorized various officers(the"Authorized Officers") to
execute various policies,bonds,undertakings and other obligatory instruments of Ike nature;and
Whereas,from time to time,the signature of the Authorized Officers,in addition to being provided in original,hard copy format,may be provided via
facsimile or otherwise in an electronic format(collectively,"Electronic Signatures");Now therefore be it resolved: that the Electronic Signature of any
Authorized Officer shall be valid and binding on the Company."
00 30 02 COMPLIANCE TO STATE LAW ON NONRESIDENT BIDDERS
Chapter 2252 of the Texas Government Code applies to the award of government contract to
nonresident bidders. This law provides that:
"a government entity may not award a governmental contract to a nonresident bidder unless the
nonresident underbids the lower bid submitted by a responsible resident bidder by an amount that
is not less than the amount by which a resident bidder would be required to underbid the
nonresident bidder to obtain a comparable contract in the state in which the nonresident's
principal place of business is located."
"Nonresident bidder" refers to a person who is not a resident of Texas.
"Resident bidder" refers to a person whose principal place of business is in this state, including a
contractor whose ultimate parent company or majority owner has its principal place of business in
this state.
Check the statement that is correct for Bidder.
❑ Bidder qualifies as a nonresident bidder whose principal place of business or residency is in
the State of
® Bidder(includes parent company or majority owner)qualifies as a resident bidder whose
principal place of business is in the State of Texas.
The Owner will use the information provided in the State of Texas Comptroller's annual publication of
other states' laws on contracts to evaluate the Bids of nonresident Bidders.
Bidder:
Company Name: Berry Contracting, LP dba Bay Ltd.
(typed or printed)
By. LS � .
( ' nature--attach evidence of a ority to n)
Name: Jon Lentz
(typed or printed)
Title: Estimating Manager
Business address: Bay Ltd.
1414 Valero Way
Corpus Christi,TX 78409
Phone: (361)693-2100 (main#) Email: lentzj@bayltd.com
END OF SECTION
Compliance to State Law on Nonresident Bidders 003002-1
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 10/2018
SPECIAL MEETING OF MANAGERS
BERRY OPERATING COMPANY,LLC
February 1,2017
Berry Operating Company,LLC, general partner of Berry Contracting,LP, dba
Bay Ltd.held a special meeting this 0 day of February 2017. Edward A.Martin,
President,presided as Chairman of the meeting and DonEtta Beaty served as Secretary.
All managers were present and waived notice of call and purpose of meeting. Mr.
Martin said the purpose of the meeting was to name the individuals authorized to act for
and on behalf of Bay Ltd.,Highway Division in connection with matters relating to the
Texas Department of Transportation and other state,municipal,federal, quasi-
governmental entities and private bodies. f
RESOLVED that the following named individuals be empowered to act {
for and on behalf of Bay Ltd.as to the making and signing of contracts,
bonds,bids, offers or other arrangements and revisions,changes or
modification of same as the needs of the company may require,
K. J.Luhan President
D. W.Berry Vice President
M. G.Berry Vice President
A.L.Berry Vice President
Edward A.Martin Vice President
Robert C.Blair Vice President
Diane DeCou Vice President and CFO '
Kevin Stone Vice President
FURTHER RESOLVED that Mr. Jon Lentz is empowered to sign
contracts,bonds,bids, offers, or arrangements and revisions, changes or
modification of same as the needs of the highway Division of Bay Ltd.
may require,hereby ratifying and affirming all such acts.
FURTHER RESOLVED that Kevin Stone,Vice President and Jon Lentz,
Estimating Manager are specifically empowered to act for and on behalf of i
Bay Ltd.to sign"Proposal to the Texas Department of Transportation". 1i
FURTHER RESOLVED that the Secretary be and is herein authorized and 1
directed to furnish a certified copy hereof to any interested parties with the
knowledge that such parties will rely upon same until actual receipt of
written notice of change,deletion,modification, or revocation of such
authority.
I
Berry Operating Company LLC
Special Meeting,February 1,2017
Page 2
l
Ar d Correct:
dward A. Ma i ,President
i
i
i
Attest:
i
i
DonEtta Beaty, Secretar
i
I
Certification
i
1,DonEtta Beaty, Secretary of Berry Operating Company,LLC certify that the above are
minutes of a special meeting of the Managers of Berry Operating Company,LLC
general partner of Berry Contracting LP, dba Bay Ltd.,held on the date shown above
and that such resolution was validly adopted at the Managers meeting at which a quorum
was present and such resolution is a continuing resolution and is presently valid and in
full force and effect this 111 day of February 2017,to which witness my hand.
DonEtta Beaty, Secretar
f
I
li
3
I
JJI
1
i
i
00 30 05 City of Corpus Christi Disclosure of Interest
CITY OF CORPUS CHRISTI
DISCLOSURE OF INTEREST
City of Corpus Christi Ordinance 17112, as amended, requires allpersons or firms seeking to do business with the
City to provide the following information. Every question must be answered. If the question is not applicable,
answer with"NA". See reverse side for Filing Requirements, Certifications and definitions.
COMPANY NAME: Berry Contracting,LP dba Bay Ltd.
STREET
P. 0.BOX: 9908 (78469-9908) ADDRESS 1414 Valero Way(78409)
CITY: Corpus Christi STATE: Texas ZIP: 78409 -
FIRM IS: 1. Corporation ❑ 2. Partnership ® 3. Sole Owner E]4. Association 5. Other
DISCLOSURE QUESTIONS
If additional space is necessary,please use the reverse side of this page or attach separate sheet.
1. State the names of each "employee" of the City of Corpus Christi having an `ownership interest" constituting
3%or more of the ownership in the above named"firm.'
Name N/A Job Title and City Department(if known)
2. State the names of each"official" of the City of Corpus Christi having an"ownership interest" constituting 3%
or more of the ownership in the above named"firm."
Name N/A Title
3. State the names of each "board member" of the City of Corpus Christi having an "ownership interest"
constituting 3%or more of the ownership in the above named"firm."
Name N/A Board,Commission or Committee
4. State the names of each employee or officer of a"consultant"for the City of Corpus Christi who worked on any
matter related to the subject of this contract and has an "ownership interest" constituting 3% or more of the
ownership in the above named"firm."
Name Consultant
N/A
City of Corpus Christi 003005-1
Morgan Ave_From Staples Street To Ocean Drive(Bond 2014),Project No.E13090Rev 01/2016
FILING REQUIREMENTS
If a person who requests official action on a matter knows that the requested action will confer an economic benefit
on any City official or employee that is distinguishable from the effect that the action will have on members of the
public in general or a substantial segment thereof,you shall disclose that fact in a signed writing to the City official,
employee or body that has been requested to act in the matter,unless the interest of the City official or employee m
the matter is apparent. The disclosure shall also be made in a signed writing filed with the City Secretary. [Ethics
Ordinance Section 2-349(d)]
CERTIFICATION
I certify that all information provided is true and correct as of the date of this statement, that I have not
knowingly withheld disclosure of any information requested; and that supplemental statements will be promptly
submitted to the City of Corpus Christi,Texas as changes occur.
Certifying Person: Jon Lentz Title: Estimating Manager
(Type or Print)
Signature of Certifying Person: Date: 1 r
DEFINITIONS
a. "Board member." A member of any board, commission, or committee appointed by the City Council of the
City of Corpus Christi,Texas.
b. "Economic benefit". An action that is likely to affect an economic interest if it is likely to have an effect on that
interest that is distinguishable from its effect on members of the public in general or a substantial segment
thereof.
c. "Employee." Any person employed by the City of Corpus Christi, Texas either on a full or part-time basis,
but not as an independent contractor.
d. "Firm." Any entity operated for economic gain, whether professional, industrial or commercial, and whether
established to produce or deal with a product or service, including but not limited to, entities operated in the
form of sole proprietorship, as self-employed person, partnership, corporation, joint stock company, joint
venture,receivership or trust,and entities which for purposes of taxation are treated as non-profit organizations.
e. "Official." The Mayor, members of the City Council, City Manager, Deputy City Manager, Assistant City
Managers,Department and Division Heads,and Municipal Court Judges of the City of Corpus Christi,Texas.
£ "Ownership Interest." Legal or equitable interest, whether actually or constructively held, in a firm,
including when such interest is held through an agent, trust, estate, or holding entity. "Constructively held"
refers to holdings or control established through voting trusts, proxies, or special terms of venture or
partnership agreements."
g. "Consultant."Any person or firm, such as engineers and architects, hired by the City of Corpus Christi for the
purpose of professional consultation and recommendation.
City of Corpus Christi 003005-1
Morgan Ave.From Staples Street To Ocean Drive(Bond 2014),Project No.E13090Rev 01/2016
00 30 06 NON-COLLUSION CERTIFICATION
STATE OF TEXAS
COUNTY OF NUECES
OWNER: City of Corpus Christi,Texas
1201 Leopard Street
Corpus Christi,Texas 78401
CONTRACT: Morgan Ave. From Staples Street To Ocean Drive (Bond 2014)
Project No. E13090
Bidder certifies that it has not been a party to any collusion among Bidders in the restraint of freedom of
competition by agreement to submit a Bid at a fixed price or to refrain from bidding; or with any official
or employee of the Owner as to quantity, quality,or price in the prospective contract, or any other terms
of said prospective contract; or in any discussion between Bidders and any official of the Owner
concerning exchange of money or other thing of value for special consideration in the letting of a contract.
Company Name: Berry Contracting, LP dba Bay Ltd.
(typed or printed)
BY S M r.
(signature--attach evidence of crdthority to ign)
Name: Jon Lentz
(typed or printed)
Title: Estimating Manager
Business address: Bay Ltd.
1414 Valero Way
Corpus Christi,TX 78409
Phone: (361)693-2100 (main#) Email: lentzj@bayltd.com
END OF SECTION
Non-Collusion Certification 003006-1
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 10/2018
SPECIAL MEETING OF MANAGERS
BERRY OPERATING COMPANY,LLC
February 1,2017
Berry Operating Company, LLC,general partner of Berry Contracting,LP,dba
Bay Ltd.held a special meeting this 11t day of February 2017. Edward A,Martin,
President,presided as Chairman of the meeting and DonEtta Beaty served as Secretary.
All managers were present and waived notice of call and purpose of meeting. Mr.
Martin said the purpose of the meeting was to name the individuals authorized to act for
and on behalf of Bay Ltd.,Highway Division in connection with matters relating to the
Texas Department of Transportation and other state,municipal,federal,quasi-
governmental entities and private bodies.
RESOLVED that the following named individuals be empowered to act
for and on behalf of Bay Ltd. as to the making and signing of contracts,
bonds,bids, offers or other arrangements and revisions,changes or
modification of same as the needs of the company may require.
K. J. Luhan President
D. W.Berry Vice President
M. G.Berry Vice President
A. L. Berry Vice President
Edward A.Martin Vice President
Robert C. Blair Vice President
Diane DeCou Vice President and CFO
Kevin Stone Vice President
FURTHER RESOLVED that Mr.Jon Lentz is empowered to sign
contracts,bonds,bids, offers, or arrangements and revisions, changes or
modification of same as the needs of the Highway Division of Bay Ltd.
may require,hereby ratifying and affirming all such acts.
I
FURTHER RESOLVED that Kevin Stone,Vice President and Jon Lentz,
Estimating Manager are specifically empowered to act for and on behalf of
Bay Ltd.to sign"Proposal to the Texas Department of Transportation". i
FURTHER RESOLVED that the Secretary be and is herein authorized and
directed to furnish a certified copy hereof to any interested parties with the I
knowledge that such parties will rely upon same until actual receipt of f
written notice of change,deletion,modification, or revocation of such
authority.
Berry Operating Company LLC
Special Meeting,February 1, 2017
Page 2
4 -
A r d Correct:
i
5dward A. Ma i ,President
Attest:
I
I
DonEtta Beaty, Secretar
Certification
i
1,DonEtta Beaty, Secretary of Berry Operating Company,LLC certify that the above are
minutes of a special meeting of the Managers of Berry Operating Company,LLC
general partner of Berry Contracting LP,dba Bay Ltd.,held on the date shown above
and that such resolution was validly adopted at the Managers meeting at which a quorum
was present and such resolution is a continuing resolution and is presently valid and in
}_ full force and effect this 1St day of February 2017,to which witness my hand.
3
DonEtta Beaty, Secretar
I
}
r
I
i
i
i
l
l
r
i
i
i
i
00 45 16 STATEMENT OF EXPERIENCE
ARTICLE 1—REQUIREMENT TO PROVIDE A STATEMENT OF EXPERIENCE
1.01 To be considered a responsive Bidder, the three lowest Bidders must complete and submit the Statement of
Experience within 5 days after the date Bids are due, or earlier if required by the Bid Documents, to demonstrate
the Bidders'responsibility and ability to meet the minimum requirements to complete the Work. Failure to submit
the required information in the Statement of Experience may result in the Owner considering the Bid non-
responsive and result in rejection of the Bid by the Owner. The Bid Security of the Bidder will be forfeited if Bidder
fails to deliver the Statement of Experience in an attempt to be released from its Bid. Bidders may be required to
provide supplemental information if requested by the Owner to clarify, enhance or supplement the information
provided in the Statement of Experience.
1.02 Bidders must provide the information requested in this Statement of Experience using the forms attached to this
Section. A copy of these forms can be provided in Microsoft Word to assist with the preparation of the Statement
of Experience. Information in these forms must be provided completely and in detail. Information that cannot
be totally incorporated in the form may be included in an attachment to the form. This attachment must be clearly
referenced by attachment number in the form, and the attached material must include the attachment number
on every sheet of the attachment. The attachment must include only the information that responds to the
question or item number to which the attachment information applies.
1.03 The Bidder may also be required to supply a financial statement, prepared no later than 90 days prior to the City
Engineer's request, signed and dated by the Bidder's owner, president or other authorized party, specifying all
current assets and liabilities.
ARTICLE 2—EXPERIENCE REQUIREMENTS
2.01 The Bidder agrees that, in addition to determining the apparent low Bid, the Owner will consider the
responsiveness of the Bids and the responsibility of the Bidders in awarding a Contract for this Project.
Information that indicates the Bidder or a Subcontractor is not responsible or that might negatively impact a
Bidder's ability to complete the Work within the Contract Time and for the Contract Price may result in the Owner
rejecting the Bid.
2.02 If none of the three apparent low Bidders are deemed responsible, the Owner may notify the next apparent low
Bidders in order, who will then be required to submit the Statement of Experience for review, until a Contract is
awarded or all Bids have been rejected.
2.03 The Bidder is responsible for the accuracy and completeness of all of the information provided by the Bidder or
a proposed Subcontractor in response to this Statement of Experience.
2.04 Provide general information about the organization as required in Table 1. Describe the organizational structure
of the Bidder's organization as it relates to this Project in Table 2.
2.05 Provide resumes for the key personnel that will be actively working on this Project.
A. Key personnel include the Project Manager, Project Superintendent, Safety Manager and Quality Control
Manager. If key personnel are to fulfill more than one of the roles listed above, provide a written narrative
describing how much time will be devoted to each function, their qualifications to fulfill each role, and the
percentage of their time that will be devoted to each role. If the individual is not to be devoted solely to this
Project, indicate how that individual's time is to be divided between this Project and other assignments.
B. The Bidder may provide resumes for an alternate individual if the Bidder is not able to commit to one
individual for the Project at the time the Bid is submitted. Qualifications of these individuals will be
considered in determining whether the experience of the Bidder meets the minimum requirements. The
Statement of Experience 004516-1
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
Bidder must provide the services of the proposed key personnel for the life of the Project as a condition of
qualification. Failure to provide the proposed Key Personnel may result in the disqualification of the Bidder
and may void the award of the Contract.
C. Provide information for each primary and alternate candidate that includes: technical experience,
managerial experience,education and formal training and a work history which describes project experience,
including the roles and responsibilities for each assignment. Additional information demonstrating
experience that meets the minimum requirements should also be included.
D. The Project Manager and Project Superintendent must have at least 5 years of recent experience in the
management and oversight of projects of a similar size and complexity to this Project. This experience must
include scheduling of manpower and materials, safety, coordination of Subcontractors, experience with the
submittal process, Federal and State wage rate requirements and contract close-out procedures. The Project
Superintendent is to be present at the Site at all times that Work is being performed. Foremen must have at
least 5 years of recent experience in similar work and be subordinate to the Project Superintendent. Foremen
cannot act as a superintendent without prior written approval from the Owner.
2.06 Provide information on the project experience and past performance of the organization.
A. Provide information on projects that have been awarded to the Organization in the last 5 years in Table 3.
Attach additional pages if necessary. Experience must include the satisfactory completion of at least five
similar projects within the last 5 years for the Bidder's organization that are equal to or greater in size and
magnitude than the current Project.
B. In determining the responsibility of the Bidder, the Owner will consider the Bidder's past projects and any
substandard quality of workmanship on completed projects. The Owner will consider whether the Bidder's
past project experience shows substandard quality of workmanship, issues related to a substandard
appearance of the completed work, the amount of warranty or rework required, problems with durability
and maintainability of the completed project, and problems with the lack of quality of documentation
provided. In addition to the work produced, the Owner may consider issues related to the quality of
construction practices, responsiveness to the owner's needs during construction, an inability to work in the
spirit of partnering and any non-responsiveness of the Bidder to make warranty corrections. Information to
make this determination will come from Owner's interviews with references provided for this project. By
listing reference contact information in this Statement of Experience, Bidder indicates its approval for OPTto
contact the individuals listed as a reference.
ARTICLE 3—SAFETY EXPERIENCE REQUIREMENTS
3.01 The Bidder agrees that pursuant to Section 252.0435 of the Local Government Code,the Owner will consider the
safety record of the Bidder prior to awarding contracts. The Owner has adopted the following written definitions
and criteria for determining the Bidder's safety record.
3.02 The Bidder's safety record will be used to determine if the Bidder can be deemed responsible.
3.03 Provide general information about the safety record of the organization as required in Table 4.
A. For purposes of providing this information,the following terms shall have the following meanings:
1. "Bidder" includes the firm, corporation, partnership, or other legal entity represented by the Bidder or
anyone acting for such firm, corporation, partnership, or other legal entity submitting the bid.
2. "Citations" include notices of violation, notices of enforcement, suspension/revocation of state or
federal licenses or registrations, fines assessed pending criminal complaints, indictments, convictions,
administrative orders, draft orders, final orders, and judicial final judgments. Notice of Violations and
Notice of Enforcement received from the TCEQ shall include those classified as major violations and
Statement of Experience 004516-2
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
moderate violations under the TCEQ's regulations for documentation of Compliance History, 30 Texas
Administrative Code, Chapter 60.2 (c) (1) and (2).
3. "Environmental Protection Agency' includes, but is not limited to the Texas Commission on
Environmental Quality (the "TCEQ"), the United States Environmental Protection Agency (the "EPA"),
the U.S. Fish and Wildlife Service, the U.S. Army Corps of Engineers, the Texas Department of State
Health Services, the Texas Parks and Wildlife Department,the Structural Pest Control Service, agencies
of local governments responsible for enforcing environmental protection laws or regulations,and similar
regulatory agencies of other states of the United States.
B. In determining the responsibility of the Bidder,the Owner will consider the following in regards to Table 4:
1. Whether the Bidder's response in reveals more than two (2) cases in which final orders have been
entered by the Occupational Safety and Health Review Commission (the "OSHRC") against the Bidder
for serious violations of Occupational Safety and Health Administration ("OSHA") regulations within the
past five (5)years.
2. Whether the Bidder's response reveals more than one (1) case in which Bidder has received a citation
or for which final orders have been entered from an environmental protection agency for violations
within the past five (5)years.
3. Whether the Bidder's response reveals that the Bidder has been convicted of a criminal offense or has
been subject to a judgment for a negligent act or omission, which resulted in serious bodily injury or
death, within the past ten (10)years.
C. The Owner may consider the responses to each question in Table 4 separately when determining the
responsibility of the Bidder. The Owner may also consider the cumulative impact of the information
generated by the Bidder's responses.
ARTICLE 4—PROVIDE INFORMATION TO DEMONSTRATE THE ABILITY OF THE BIDDER TO PROVIDE SUBCONTRACTING
OPPORTUNITIES THAT WILL MEET THE OWNER'S ESTABLISHED GOALS FOR MINORITY, MBE,AND DBE PARTICIPATION
IN THE PROJECT. LIST ALL WORK TO BE PERFORMED BY QUALIFIED MINORITY, MBE AND DBE-PROPOSED
SUBCONTRACTORS OR SUPPLIERS IN TABLE 5. INCLUDE PERCENTAGES OF WORK SUBCONTRACTED TO EACH TO
DEMONSTRATE COMPLIANCE WITH OWNER'S STATED GOALS.
Statement of Experience 004516-3
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
TABLE 1—ORGANIZATION INFORMATION
Organization doing business as: I BAY LTD.
1414 VALERO WAY
Business Address of Principal Office CORPUS CHRISTI,TX 78409
Telephone No. 1 (361)693-2100 Website I https://bayltd.com
Form of Business (check one) ❑ Corporation 1K Partnership ❑ Individual
If a Corporation
State of Incorporation TEXAS Date of Incorporation
Chief Executive Officer's Name E.A. MARTIN President's Name K.J.LUHAN
K.STONE
DJ SMITH
R. BLAIR
Vice President's Name(s) D. CARLIN
C. VANAMAN
R. HAWS
Secretary's Name Don Etta BEATY Treasurer's Name DIANE DeCou
If a Partnership
Date of Organization 11/29/1990 Form of Partnership: ❑ General 12� Limited
If an Individual
Name
Ownership of Organization
List of companies,firms, or organizations that own any part of the organization.
Names of Companies, Firms, or Organizations Percent Ownership
BERRY OPERATING COMPANY, LLC 1%
BERRY HOLDINGS, LP
Organization History
List of names that this organization currently, has, or anticipates operating under including the names of related
companies presently doing business.
Names of Organizations From Date To Date
BERRY CONTRACTING, INC. 1950 2000
BAY LTD. 1980 2000
BERRY CONTRACTING, L.P. dba BAY LTD. 2000 PRESENT
Indicators of Organization Size
Average number of current full-time employees 2,500
Average estimate of revenue for the current year $500 MILLION
Statement of Experience
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 004516-4
Rev 10/2018
Table 1—Organization Information
Organization doing business as: I BAY LTD.
Previous History with City of Corpus Christi
List the 5 most recent projects that have been completed with the City of Corpus Christi.
Project Name Year
1 STAPLES STREET-WILLIAMS TO SARATOGA 2013
2 WALDRON RD. 2016
3 ALAMEDA ST. 2017
4 STATPLES ST. - IH 37 TO MORGAN 2017
5 INTERNATIONAL DRIVE 2017
Construction Site Safety Experience
Provide Bidders Experience Modification Ratio (EMR) History for the last 3 years. Provide documentation of the
EMR.
Year 1 2016 1 EMR .63 Year I 2015 I EMR 1 .58 Year 12014 1 EMR I 53
Previous Bidding and Construction Experience—Answer all question Yes or No.
Has Bidder or a predecessor organization been debarred within the last 10 years? List debarring entities below and
provide full details in a separate attachment if yes. NO X YES
Has Bidder or a predecessor organization been disqualified as a bidder within the last 10 years? List Projects below
and provide full details in a separate attachment if yes. NO X YES
Has Bidder or a predecessor organization been released from a bid or proposal in the past 10 years? List Projects
below and provide full details in a separate attachment if yes. NO X YES
Has Bidder or a predecessor organization ever defaulted on a project or failed to complete any work awarded to it?
List Projects below and provide full details in a separate attachment if yes. NO X YES
Has Bidder or a predecessor organization been involved in claims or litigation involving project owners within the
last 10 years? List Projects below and provide full details in a separate attachment if yes. NO X YES
Have liens or claims for outstanding unpaid invoices been filed against the Bidder for services or materials on any
projects begun within the preceding 3 years? Specify the name and address of the party holding the lien or making
the claim, the amount and basis for the lien or claim, and an explanation of why the lien has not been released or
that the claim has not been paid if yes. NO X YES
Statement of Experience
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 004516-5
Rev 10/2018
Table 2—Project Information
Organization doing business as: I BAY LTD.
Proposed Project Organization
Provide a brief description of the organizational structure proposed for this project indicating the names and
functional roles of proposed key personnel and alternates. Provide resumes for Project Manager, Superintendent,
Safety Manager and Quality Control Manager.
Position Primary Alternate
Project Manager JAMES CHAPMAN JESUS WONG
Superintendent
Safety Manager RICK SHADLE DAVID CARLIN
Quality Control
RAN DAL MOFF
Manager
Division of work between Bidder and Proposed Subcontractor and Suppliers
Provide a list of Work to be self-performed by the Bidder and the Work contracted to Subcontractors and Suppliers
for more than 10 percent of the Work(based on estimated subcontract or purchase order amounts and the Contract
Price).
Name of Entity Performing the Estimated Percentage
Description of Work Work of Contract Price
DIRT WORK,STORM WATER,WATERLINE AND PAVING BAY LTD. 98.67%
Subcontractor Construction Site Safety Experience
Provide Experience Modification Ratio (EMR) History for the last 3 years for Subcontractors that will provide Work
valued at 25%or more of the Contract Price. Provide documentation of the EMR.
Subcontractor
Year IEMR Year EMR Year EMR
Subcontractor
Year IEMRI Year EMR Year EMR
Statement of Experience
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014),Project No. E13090 004516-6
Rev 10/2018
Table 3—Projects Awarded during the Last 5 Years
Organization doing business as: BAY LTD.
Proiect Information
Project STAPLES STREET-WILLIAMS TO COMPLETE REMOVAL OF AN EXISTING ROADWAY AND
Description
N �SARATOGA RECONSTRUCTION 5-LANE ROADWAY
ame
Reference Contact Information
Project Owner CITY OF CORPUS CHRISTI
Name/Title KEN KAPER, P.E./PROJECT MANAGER
Telephone (361)826-3522 Email KENTP@CCTEXAS.COM
Project Designer FREESE & NICHOLS
Project Budget and Performance
Original $16,435,907.81 Final Contract #Contract # Days
Contract Price $15,081,495.80 Price Days 540 CD Late
Issues/Claims/
Litigation:
Project Information
Project CCIA Description DISPLACEMENT/EXTENSION RUNWAY
Name
Reference Contact Information
Project Owner CITY OF CORPUS CHRISTI
Name/Title ELLIOT NEPH, P.E.
Telephone (972) 542-2995 Email ENEPH@KSAENG.COM
Project Designer KSA ENGINEERS, INC.
Project Budget and Performance
Original Final Contract #Contract #Days
$12,841,419.06 $15,631,021.36 365 CD
Contract Price Price Days Late
Issues/Claims/
Litigation:
Proiect Information
Project ALAMEDA ST.-LIPAN TO KINNEY FULL-DEPTH RECONSTRUCTION OF EXISTING TWO-LANE
Name (BOND 2014) Description MIRROR COLLECTOR ROADWAY
Reference Contact Information
Project Owner CITY OF CORPUS CHRISTI
Name/Title ANDY R.VISTOL, E.I.T.
Telephone (361)882-2257 Email ARVIGSTOL@IAN-INOM
Project Designer LOCKWOOD,ANDREWS&NEWMAN, INC.
Project Budget and Performance
Original $1,942,131.94 180 CD Final Contract #Contract # Days
Contract Price $1,862,252.50 Price Days Late
Issues/Claims/
Litigation:
Statement of Experience
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 004516-7
Rev 10/2018
Table 3—Projects Awarded during the Last 5 Years—Not including City of Corpus Christi Projects
Organization doing business as: BAY LTD.
Proiect Information
Project INTERNATIONAL DR. IMPROVEMENTS REHAB.OF INTERNATIONAL DR.AT THE CCIA LEVEL-UP OVERLAY
Name (BOND 2012) Description WITH FULL DEPTH PAVEMENT REPAIR,ETC.
Reference Contact Information
Project Owner CITY OF CORPUS CHRISTI
Name/Title SCOTT JON ES, P.E.
Telephone (361) 887-8851 Email SJONES@UAENGEINEERING.COM
Project Designer UA ENGINEERING, INC.
Project Budget and Performance
Original Final Contract #Contract # Days
Contract Price $1,683,694.35 $1,798,541.35 180 CD price Days Late
Issues/Claims/
Litigation:
Proiect Information
Project SOUTH STAPLES ST. FROM MORGAN—[------ RECONSTRUCTION OF TWO(2)SECTIONS OF STAPLES ST.
Name AVE.TO IH 37 Description (HAVING DIFFERENT EXISTING CONDITIONS AND PAVEMENT REQUIREMENTS)
Reference Contact Information
Project Owner CITY OF CORPUS CHRISTI
Name/Title THOMAS EVERETT, E.I.T.
Telephone (361) 814-9900 Email THOMAS EVERETT-TEVERETT@HANSON-INC.COM
Project Designer NAISMITH/HANSON ENGINEERING
Project Budget and Performance
Original Final Contract #Contract # Days
Contract Price $13,448,289.10 Price $13,873,704.00 Days 730 CD Late
Issues/Claims/
Litigation:
Proiect Information
Project WALDRON RD. FROM CARIBBEAN DR. Description CEMENT STABILIZED PAVING,ALONG WITH RELATED
Name TO GLENOAK DR. (BOND 2014) SIDEWALK,WATER,STORMWATER&WASTEWATER UTILITIES
Reference Contact Information
Project Owner CITY OF CORPUS CHRISTI
Name/Title MURRAY HUDSON, P.E.
Telephone (361)854-3101 Email MURRAY HUDSON MURFH@URBANENG.COM
Project Designer URBAN ENGINEERING
Project Budget and Performance
Original Final Contract #Contract #Days
Contract Price $2,580,631.90 Price $2,607,399.97 Days 180 CD Late
Statement of Experience
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014),Project No. E13090 0045 16-8
Rev 10/2018
Table 3—Projects Awarded during the Last 5 Years—Not including City of Corpus Christi Projects
Organization doing business as: BAY LTD.
Project Information
Projec
Name t NUECES COUNTY-FM 43 Description CONSTRUCT ADDITIONAL TRAVEL LANES
Reference Contact Information
Project Owner TEXAS DEPARTMENT OF TRANSPORTATION
Name/Title MARTIN HORST, P.E./AREA ENGINEER
Telephone (361) 808-2300 Email MARTIN.HORST@TXDOT.GOV
Project Designer TxDOT
Project Budget and Performance
Original Final Contract #Contract #Days
Contract Price $9,863,126.39 Price $10,143,972.29 Days 317 WD Late
Issues/Claims/
Litigation:
Project Information
Project NUECES COUNTY-IH0037 Description MILL,SEAL AND OVERLAY
Name
Reference Contact Information
Project Owner TEXAS DEPARTMENT OF TRANSPORTATION
Name/Title MARTIN HORST, P.E./AREA ENGINEER
Telephone (361)808-2300 Email MARTIN.HORST@TXDOT.GOV
Project Designer TxDOT
Project Budget and Performance
Original Final Contract #Contract #Days
Contract Price $1,085,298.60 Price $2,224,602.57 Days 365 CD Late
Issues/Claims/
Litigation:
Project Information
Project SAN PATRICIO COUNTY-SH 188 UPGRADING ROAD, NEW BASE, NEW STRUCTURES AND HOT
Name Description MIX
Reference Contact Information
Project Owner TEXAS DEPARTMENT OF TRANSPORTATION
Name/Title CHARLES BENAVIDEZ, P.E.
Telephone (361)364-6402 Email CHARLES.BENAVIDEZ@TXDOT.GOV
Project Designer TxDOT
Project Budget and Performance
Original Final Contract #Contract #Days
Contract Price $9233,815.50 Price $9,627,216.92 Days 345 WD Late
Issues/Claims/
Litigation:
Statement of Experience
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No.E13090 004516-9
Rev 10/2018
Table 4—Safety Record Questionnaire and Statement of Bidder's Safety Experience
Organization doing business as: I BAY LTD.
Bidder's Safety Record and Experience
Has the Bidder received any Citations for violations of OSHA within the past five(5)years? List Citations below(date
and location of Citation)and provide full details in a separate attachment if yes.The full details must include the type
of violation or offense,the final disposition of the violation or offense, if any, and the penalty assessed.
NO X YES
Has the Bidder received any Citations for violations of environmental protection laws or regulations within the past
five(5)years? List Citations below(date and location of Citation) and provide full details in a separate attachment if
yes.The full details must include the type of violation or offense, the final disposition of the violation or offense, if
any, and the penalty assessed. NO X YES
Has the Bidder, within the past ten (10) years, been convicted of a criminal offense or been subject to a judgment
for a negligent act or omission,which resulted in serious bodily injury or death? List convictions orjudgments below
and provide full details in a separate attachment if yes. NO X YES
The Owner will consider the following information as additional support to make a determination as to the
responsibility of the Bidder.The Bidder must answer the following questions and provide evidence that it meets
minimum OSHA construction safety standards and has a lost time injury rate that does not exceed the limits
established below:
1 Does the Bidder have a written construction safety program? N Yes ❑ No
2 Does the Bidder conduct regular construction site safety inspections? d1 Yes ❑ No
3 Does the Bidder have an active construction safety training program? N Yes ❑ No
4 Does the Bidder, or affected subcontractor, have competent persons in the following areas (as applicable to
the scope of the current Project):
A. Scaffolding iX Yes ❑ No ❑ N/A
B. Excavation N Yes ❑ No ❑ N/A
C. Cranes& Hoists N Yes ❑ No ❑ N/A
D. Electrical X Yes ❑ No ❑ N/A
Statement of Experience
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 004516-10
Rev 10/2018
Table 4—Safety Record Questionnaire and Statement of Bidder's Safety Experience
Organization doing business as: I BAY LTD.
E. Fall Protection K Yes ❑ No ❑ N/A
F. Confined Spaces [X Yes ❑ No ❑ N/A
G. Material Handling EX Yes ❑ No ❑ N/A
H. Demolition x Yes ❑ No ❑ N/A
I. Steel Erection [A Yes ❑ No ❑ N/A
J. Underground Construction X Yes ❑ No ❑ N/A
Does the Bidder have a lost time injury rate and a total recordable injury rate of less than
or equal to the national average for North American Industrial Classification System ix
5 Yes ❑ No
("NAICS") Category 23 for each of the past five (5)years? Provide the Bidder's OSHA 300
and 300A logs for the past five (5)years in a separate attachment.
Does the Bidder have an experience modifier rate of 1.0 or less? Provide the Bidder's
6 NCCI workers' compensation experience rating sheets for the past five (5) years in a 1XYes ❑ No
separate attachment.
Has the Bidder had any OSHA inspections within the past six (6) months? Provide
7 documentation showing the nature of the inspection,the findings, and the magnitude of X Yes ❑ No
the issues in a separate attachment if yes.
Statement of Experience 004516-11
Morgan Ave.From Staples Street To Ocean Drive(Bond 2014), Project No.E13090 Rev 10/2018
Table 5-Demonstrated Minority,MBE, DBE Participation
Organization doing business as I BAY LTD.
Project Subcontractors and Suppliers
Provide a list of anticipated Minority, MBE,DBE Subcontractors or Suppliers contracts that will be used to demonstrate
compliance with the Owner's Minority/MBE/DBE Participation Policy
Name Work to be Provided Estimated%of
Contract Price
HIGHWAY BARRICADES BARRICADES, SIGNS AND STRIPING 1.12%
SOIL-TECH, INC. SODDING/LANDSCAPING, ETC. 0.21%
OTHERS TO BE DETERMINED
Statement of Experience 004516-12
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014),Project No. E13090 Rev 10/2018
ARTICLE 5—CERTIFICATION
5.01 By submitting this Statement of Experience and related information, Bidder certifies that it has read
this Statement of Experience and that Bidder's responses are true and correct and contain no
material misrepresentations and that the individual signing below is authorized to make this
certification on behalf of the Bidder's organization. The individual signing this certification shall
attach evidence of individual's authority to bind the organization to an agreement.
Bidder: BERRY CONTRACTING, L.P.dba BAY LTD
(typed or printed)
By:
(individual's signature)
Name: JON LENTZ
(typed or printed)
Title: ESTIMATING MANAGER
(typed or printed)
Designated Representative:
Name: JON LENTZ
Title: ESTIMATING MANAGER
Address: BAY LTD.
1414 VALERO WAY
CORPUS CHRISTI,TX 78409
Telephone No.: (361) 693-2100(main#) Email: lentzj@bayltd.com
END OF SECTION
Statement of Experience 004516-13
Morgan Ave. From Staples Street To Ocean Drive (Bond 2014), Project No. E13090 Rev 10/2018
i
SPECIAL MEETING OF MANAGERS
BERRY OPERATING COMPANY,LLC
February 1,2017
Berry Operating Company,LLC, general partner of Berry Contracting,LP,dba
Bay Ltd.held a special meeting this 11t day of February 2017, Edward A,Martin,
President,presided as Chairman of the meeting and DonEtta Beaty served as Secretary.
All managers were present and waived notice of call and purpose of meeting. Mr,
Martin said the purpose of the meeting was to name the individuals authorized to act for
and on behalf of Bay Ltd.,Highway Division in connection with matters relating to the
Texas Department of Transportation and other state,municipal,federal,quasi-
governmental entities and private bodies. 17
RESOLVED that the following named individuals be empowered to act !
,
for and on behalf of Ba Ltd. as to the making and signing of contracts
a a y t g gn g
bonds,bids, offers or other arrangements and revisions,changes or
modification of same as the needs of the company may require,
K. J. Luhan President
D.W.Berry Vice President
M, G.Bevy Vice President
A.L.Berry Vice President
Edward A.Martin Vice President
Robert C.Blair Vice President
Diane DeCou Vice President and CFO ;
Kevin Stone Vice President
FURTHER RESOLVED that Mr.Jon Lentz is empowered to sign
contracts,bonds, bids, offers, or arrangements and revisions, changes or
modification of same as the needs of the;Highway Division of Bay Ltd.
may require,hereby ratifying and affirming all such acts. '
FURTHER RESOLVED that Kevin Stone,Vice President and Jon Lentz,
Estimating Manager are specifically empowered to act for and on behalf of i
Bay Ltd.to sign"Proposal to the Texas Department of Transportation".
FURTHER RESOLVED that the Secretary be and is herein authorized and t
directed to furnish a certified copy hereof to any interested parties with the t;
knowledge that such parties will rely upon same until actual receipt of
written notice of change,deletion,modification, or revocation of such
authority.
i
i
1
Berry Operating Company LLC
Special Meeting,February 1, 2017
Page 2
4
A r d Correct:
I
3
dward A.Ma i ,President
i
i
Attest:
i
I
DonEtta Beaty, Secretar
Certification
1,DonEtta Beaty, Secretary of Berry Operating Company,LLC certify that the above are
minutes of a special meeting of the Managers of Berry Operating Company,LLC
general partner of Berry Contracting LP,dba Bay Ltd.,held on the date shown above
and that such resolution was validly adopted at the Managers meeting at which a quorum
was present and such resolution is a continuing resolution and is presently valid and in 3
full force and effect this 1St day of February 2017,to which witness my hand.
DonEtta Beaty, Secretar
i
i
3
I7
i
1
1
1
i
3:
i
00 52 23 AGREEMENT
This Agreement, for the Project awarded on July 16, 2019, is between the City of Corpus Christi (Owner)
and
Berry Contracting LP dba Bay, Ltd (Contractor).
Owner and Contractor agree as follows:
ARTICLE 1—WORK
1.01 Contractor shall complete all Work as specified or indicated in the Contract Documents. The Work
is generally described as:
Morgan Ave. From Staples Street To Ocean Drive (Bond 2014)
Proiect No. E13090
ARTICLE 2—DESIGNER AND OWNER'S AUTHORIZED REPRESENTATIVE
2.01 The Project has been designed by:
UA Engineering, Inc.
Jeff Coym, PE
5353 South Staples Street, Suite 425
Corpus Christi,Texas 78411
UASouthccC@lia.com
The Owner's Authorized Representative for this Project is:
Kent Power, P.E.—Acting Construction Management Engineer
City of Corpus Christi—Engineering Services
4917 Holly Rd, Bldg#5
Corpus Christi,TX 78411
ARTICLE 3—CONTRACT TIMES
3.01 Contract Times
A. The Work is required to be substantially completed within 550 days after the date when the
Contract Times commence to run as provided in the Notice to Proceed and is to be completed
and ready for final payment in accordance with Paragraph 17.16 of the General Conditions
within 580 days after the date when the Contract Times commence to run.
B. Milestones,and the dates for completion of each,are as defined in SECTION 0135 00 SPECIAL
PROCEDURES.
3.02 Liquidated Damages
A. Owner and Contractor recognize that time limits for specified Milestones, Substantial
Completion, and completion and readiness for Final Payment as stated in the Contract
Documents are of the essence of the Contract. Owner and Contractor recognize that the
Agreement 005223- 1
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
Owner will suffer financial loss if the Work is not completed within the times specified in
Paragraph 3.01 and as adjusted in accordance with Paragraph 11.05 of the General
Conditions. Owner and Contractor also recognize the delays, expense, and difficulties
involved in proving in a legal or arbitration proceeding the actual loss suffered by Owner if
the Work is not completed on time. Accordingly, instead of requiring any such proof, Owner
and Contractor agree that as liquidated damages for delay (but not as a penalty):
1. Substantial Completion: Contractor shall pay Owner $1,750 for each day that expires
after the time specified in Paragraph 3.01 for Substantial Completion until the Work is
substantially complete.
2. Completion of the Remaining Work: Contractor agrees to pay Owner$400 for each day
that expires after the time specified in Paragraph 3.01 for completion and readiness for
final payment until the Work is completed and ready for final payment in accordance
with Paragraph 17.16 of the General Conditions.
3. Liquidated damages for failing to timely attain Substantial Completion and Final
Completion are not additive and will not be imposed concurrently.
4. Milestones: Contractor agrees to pay Owner liquidated damages as stipulated in
SECTION 0135 00 SPECIAL PROCEDURES for failure to meet Milestone completions.
5. The Owner will determine whether the Work has been completed within the Contract
Times.
B. Owner is not required to only assess liquidated damages, and Owner may elect to pursue its
actual damages resulting from the failure of Contractor to complete the Work in accordance
with the requirements of the Contract Documents.
ARTICLE 4—CONTRACT PRICE
4.01 Owner will pay Contractor for completion of the Work in accordance with the Contract
Documents at the unit prices shown in the attached BID FORM. Unit prices have been computed
in accordance with Paragraph 15.03 of the General Conditions. Contractor acknowledges that
estimated quantities are not guaranteed, and were solely for the purpose of comparing Bids, and
final payment for all unit price items will be based on actual quantities, determined as provided
in the Contract Documents.
Total Base Bid Price $ 5,187,733.85
ARTICLE 5—PAYMENT PROCEDURES
5.01 Submit Applications for Payment in accordance with Article 17 of the General Conditions.
Applications for Payment will be processed by the OAR as provided in the General Conditions.
5.02 Progress Payments; Retainage:
A. The Owner will make progress payments on or about the 25th day of each month during
performance of the Work. Payment is based on Work completed in accordance with the
Schedule of Values established as provided in the General Conditions.
Agreement 005223- 2
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
B. Progress payments equal to the full amount of the total earned value to date for completed
Work minus the retainage listed below and properly stored materials will be made prior to
Substantial Completion.
1. The standard retainage is 5 percent.
C. Payment will be made for the amount determined per Paragraph 5.02.13, less the total of
payments previously made and less set-offs determined in accordance with Paragraph 17.01
of the General Conditions.
D. At the Owner's option, retainage may be increased to a higher percentage rate, not to exceed
ten percent, if progress on the Project is considered to be unsatisfactory. If retainage in
excess of the amount described above is held prior to Substantial Completion,the Owner will
place the additional amount in an interest bearing account. Interest will be paid in
accordance with Paragraph 6.01.
E. At the Owner's option, Owner may pay Contractor 100 percent of the Work completed, less
amounts withheld in accordance with Paragraph 17.01 of the General Conditions and less
200 percent of OAR's estimate of the value of Work to be completed or corrected to reach
Substantial Completion. Owner may, at its sole discretion, elect to hold retainage in the
amounts set forth above for progress payments prior to Substantial Completion if Owner has
concerns with the ability of the Contractor to complete the remaining Work in accordance
with the Contract Documents or within the time frame established by this Agreement.
Release or reduction in retainage is contingent upon and consent of surety to the reduction
in retainage.
5.03 Owner will pay the remainder of the Contract Price as recommended by OAR in accordance with
Paragraph 17.16 of the General Conditions upon Final Completion and acceptance of the Work.
ARTICLE 6—INTEREST ON OVERDUE PAYMENTS AND RETAINAGE
6.01 The Owner is not obligated to pay interest on overdue payments except as required by Texas
Government Code Chapter 2251.
6.02 Except as specified in Article 5, the Owner is not obligated to pay interest on moneys not paid
except as provided in Texas Government Code Chapter 2252.
ARTICLE 7—CONTRACTOR'S REPRESENTATIONS
7.01 The Contractor makes the following representations:
A. The Contractor has examined and carefully studied the Contract Documents and the other
related data identified in the Bidding Documents.
B. The Contractor has visited the Site and become familiar with and is satisfied as to the general,
local, and Site conditions that may affect cost, progress, and performance of the Work.
C. The Contractor is familiar with Laws and Regulations that may affect cost, progress, and
performance of the Work.
Agreement 005223-3
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
D. The Contractor has carefully studied the following Site-related reports and drawings as
identified in the Supplementary Conditions:
1. Geotechnical Data Reports regarding subsurface conditions at or adjacent to the Site;
2. Drawings of physical conditions relating to existing surface or subsurface structures at
the Site;
3. Underground Facilities referenced in reports and drawings;
4. Reports and drawings relating to Hazardous Environmental Conditions, if any, at or
adjacent to the Site; and
5. Technical Data related to each of these reports and drawings.
E. The Contractor has considered the:
1. Information known to Contractor;
2. Information commonly known to contractors doing business in the locality of the Site;
3. Information and observations obtained from visits to the Site; and
4. The Contract Documents.
F. The Contractor has considered the items identified in Paragraphs 7.01.D and 7.01.E with
respect to the effect of such information, observations, and documents on:
1. The cost, progress, and performance of the Work;
2. The means, methods, techniques, sequences, and procedures of construction to be
employed by Contractor; and
3. Contractor's safety precautions and programs.
G. Based on the information and observations referred to in the preceding paragraphs,
Contractor agrees that no further examinations, investigations, explorations, tests, studies,
or data are necessary for the performance of the Work at the Contract Price, within the
Contract Times, and in accordance with the other terms and conditions of the Contract
Documents.
H. The Contractor is aware of the general nature of Work to be performed by Owner and others
at the Site that relates to the Work as indicated in the Contract Documents.
I. The Contractor has correlated the information known to the Contractor, information and
observations obtained from visits to the Site, reports and drawings identified in the Contract
Documents, and all additional examinations, investigations, explorations, tests, studies, and
data with the Contract Documents.
J. The Contractor has given the OAR written notice of all conflicts, errors, ambiguities, or
discrepancies that the Contractor has discovered in the Contract Documents,and the written
resolution provided by the OAR is acceptable to the Contractor.
K. The Contract Documents are generally sufficient to indicate and convey understanding of all
terms and conditions for performance and furnishing of the Work.
L. Contractor's entry into this Contract constitutes an incontrovertible representation by
Contractor that without exception all prices in the Agreement are premised upon performing
and furnishing the Work required by the Contract Documents.
Agreement 005223-4
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
M. CONTRACTOR SHALL INDEMNIFY, DEFEND AND HOLD HARMLESS THE OWNER'S
INDEMNITEES IN ACCORDANCE WITH PARAGRAPH 7.14 OF THE GENERAL CONDITIONS
AND THE SUPPLEMENTARY CONDITIONS.
ARTICLE 8—ACCOUNTING RECORDS
8.01 Accounting Record Availability: The Contractor shall keep such full and detailed accounts of
materials incorporated and labor and equipment utilized for the Work consistent with the
requirements of Paragraph 15.01 of the General Conditions and as may be necessary for proper
financial management under this Agreement. Subject to prior written notice,the Owner shall be
afforded reasonable access during normal business hours to all of the Contractor's records, books,
correspondence, instructions,drawings, receipts,vouchers, memoranda,and similar data relating
to the Cost of the Work and the Contractor's fee. The Contractor shall preserve all such
documents for a period of 3 years after the final payment by the Owner.
ARTICLE 9—CONTRACT DOCUMENTS
9.01 Contents:
A. The Contract Documents consist of the following:
1. Specifications, forms, and documents listed in SECTION 00 0100 TABLE OF CONTENTS.
2. Drawings listed in the Sheet Index.
3. Addenda.
4. Exhibits to this Agreement:
a. Contractor's Bid Form.
5. Documentation required by the Contract Documents and submitted by Contractor prior
to Notice of Award.
B. There are no Contract Documents other than those listed above in this Article.
C. The Contract Documents may only be amended, modified, or supplemented as provided in
Article 11 of the General Conditions.
ARTICLE 10—CONTRACT DOCUMENT SIGNATURES
One original of the signed Agreement will be required. The sequence of signatures will be
completed in the following order:
A. CONTRACTOR— Contract Documents must be signed by a person authorized to bind the
firm or company. If Contractor is a Corporation, documents must be Attested;
B. ASSISTANT CITY ATTORNEY for the City;
C. DIRECTOR OF ENGINEERING SERVICES;
D. CITY SECRETARY for the City.
Agreement 005223-5
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
[SIGNATURE PAGE TO FOLLOW]
Agreement 005223-6
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
ATTEST CITY OF CORPUS CHRISTI
Dgit lly-g dby Rebe H rta DIg dy Ig—by—Etl ds
RebeccaH uerta seg i ry ,_eee° bay as°�nm�°Us,,e�-�� Dtis �et,Edme�de E g1eer11g emat le reye�ee�.a=�em.
Date.2019 08 05 09 43 53 05'00Dat 2019.0]3014'52 27 0500'
Rebecca Huerta J.H. Edmonds, P.E.
City Secretary Director of Engineering Services
M2019-101 AUTHORIZED
APPROVED AS TO LEGAL FORM: BY COUNCIL 07/16/2019
Digitally signed by Kent Mcllyar
DN cn KentMcllyar n nD Digitally signed by RH/AB
email trent—gi,ctexascnm c US RH/AB
Date.2019.07.3014.03.20 0a00a _ Date:2019.08.01 11:16:04-05'00'
Assistant City Attorney
ATTEST(IF CORPORATION) CONTRACTOR
Berry Contracting LP dba Bay Ltd
signedJon Lenz
(Seal Below) By: Jon Lentz Date:Digitally
019.0729Y10:16:54105'00'
Note: Attach copy of authorization to sign if Title: Estimating Manager
person signing for CONTRACTOR is not President,
Vice President, Chief Executive Officer, or Chief 1414 Valero Way
Financial Officer Address
Corpus Christi, Texas 78409
City State Zip
361/693-2100 361 -289-2304
Phone Fax
lentzj@bayltd.com
EMail
END OF SECTION
Agreement 005223-7
Morgan Ave. From Staples Street To Ocean Drive(Bond 2014), Project No. E13090 Rev 10/2018
00 6113
PERFORMANCE BOND
BOND NO. 30046791
Contractor as Principal
Name: Berry Contracting LP dba Bay Ltd
Mailing address (principal place of business):
1414 Valero Way
Corpus Christi, TX 78409
Owner
Name: City of Corpus Christi, Texas
Mailing address (principal place of business):
Engineering Services
1201 Leopard Street
Corpus Christi, Texas 78469
Contract
Project name and number:
Project No. E13090
Morgan Ave from Staples Street to Ocean Drive
(Bond 2014)
Award Date of the Contract: July 16, 2019
Contract Price: $5,187,733.85
Bond
Date of Bond: JULY 19, 2019
(Date of Bond cannot be earlier than Award Date
of the Contract)
Surety
Name: CONTINENTAL CASUALTY COMPANY
Mailing address (principal place of business):
5151 SAN FELIPE, SUITE 1200
HOUSTON, TEXAS 77056
Physical address (principal place of business):
SAME
Surety is a corporation organized and existing
under the laws of the state of: ILLINOIS
By submitting this Bond, Surety affirms its
authority to do business in the State of Texas and
its license to execute bonds in the State of Texas.
Telephone (main number): 713-513-6301
Telephone (for notice of claim):
SEE ATTACHED
Local Agent for Surety
Name: HIGGINBOTHAM INSURANCE AGENCY
Address:
500 N. SHORELINE BLVD., SUITE 1200
CORPUS CHRISTI, TEXAS 78401
Telephone: 361-883-1711
Email Address: memoore@higginbotham.net
The address of the surety company to which any
notice of claim should be sent may be obtained
from the Texas Dept. of Insurance by calling the
following toll-free number: 1-800-252-3439
Performance Bond
E13090 Morgan Ave — Staples to Ocean Dr (Bond 2014)
006113-1
7-8-2014
Surety and Contractor, intending to be legally bound and obligated to Owner do each cause this
Performance Bond to be duly executed on its behalf by its authorized officer, agent or representative.
The Principal and Surety bind themselves, and their heirs, administrators, executors, successors and
assigns, jointly and severally to this bond. The condition of this obligation is such that if the Contractor as
Principal faithfully performs the Work required by the Contract then this obligation shall be null and
void; otherwise the obligation is to remain in full force and effect. Provisions of the bond shall be
pursuant to the terms and provisions of Chapter 2253 and Chapter 2269 of the Texas Government Code
as amended and all liabilities on this bond shall be determined in accordance with the provisions of said
Chapter to the same extent as if it were copied at length herein. Venue shall lie exclusively in Nueces
County, Texas for any legal action.
Contract as Principal
Signature: T-
o. "'
Surety `��
Signature: ‘..,.e..:‘, ��,., ///G'Mt.,-
Name: .... L en k- Z
Name: MA LEN MOORE
Title: Es -V, „r, �-�M r
5
Title: ATTORNEY IN FACT
5
Email Address: L to -2„J @0 11.0../ L'Ir Co -d•
Email Address: memoore@hiRRinbotham.net
(Attach Power of Attorney and place surety seal below)
END OF SECTION
Performance Bond
E13090 Morgan Ave — Staples to Ocean Dr (Bond 2014)
006113-2
7-8-2014
POWER OF ATTORNEY APPOINTING INDIVIDUAL ATTORNEY-IN-FACT
Know All Men By These Presents, That Continental Casualty Company, an Illinois insurance company, National Fire Insurance Company of
Hartford, an Illinois insurance company, and American Casualty Company of Reading, Pennsylvania, a Pennsylvania insurance company (herein called
"the CNA Companies"), are duly organized and existing insurance companies having their principal offices in the City of Chicago, and State of Illinois,
and that they do by virtue of the signatures and seals herein affixed hereby make, constitute and appoint
Mary Ellen Moore, Steve Addkison, Cathleen Hayles, Aaron J Endris, Tricia Balolong, Individually
of Corpus Christi, TX, their true and lawful Attorneys) -in -Fact with full power and authority hereby conferred to sign, seal and execute for and on their
behalf bonds, undertakings and other obligatory instruments of similar nature
- In Unlimited Amounts -
and to bind them thereby as fully and to the same extent as if such instruments were signed by a duly authorized officer of their insurance companies and
all the acts of said Attorney, pursuant to the authority hereby given is hereby ratified and confirmed.
This Power of Attorney is made and executed pursuant to and by authority of the By -Law and Resolutions, printed on the reverse hereof, duly
adopted, as indicated, by the Boards of Directors of the insurance companies.
In Witness Whereof, the CNA Companies have caused these presents to be signed by their Vice President and their corporate seals to be hereto
affixed on this 26th day of October, 2016.
Continental Casualty Company
National Fire Insurance Company of Hartford
American Cass lty Company of Reading, Pennsylvania
Paul T. Bruflat # Vice President
State of South Dakota, County of Minnehaha, ss:
On this 26th day of October, 2016, before me personally came Paul T. Bruflat to me known, who, being by me duly sworn, did depose and say: that
he resides in the City of Sioux Falls, State of South Dakota; that he is a Vice President of Continental Casualty Company, an Illinois insurance company,
National Fire Insurance Company of Hartford, an Illinois insurance company, and American Casualty Company of Reading, Pennsylvania, a
Pennsylvania insurance company described in and which executed the above instrument; that he knows the seals of said insurance companies; that the
seals affixed to the said instrument are such corporate seals; that they were so affixed pursuant to authority given by the Boards of Directors of said
insurance companies and that he signed his name thereto pursuant to like authority, and acknowledges same to be the act and deed of said insurance
companies.
My Commission Expires June 23, 2021
CERTIFICATE
I, D. Bult, Assistant Secretary of Continental Casualty Company, an Illinois insurance company, National Fire Insurance Company of Hartford, an
Illinois insurance company, and American Casualty Company of Reading, Pennsylvania, a Pennsylvania insurance company do hereby certify that the
Power of Attorney herein above set forth is still in force, and further certify that the By -Law and Resolution of the Board of Directors of the insurance
companies printed on the reverse hereof is still in force. In testimony whereof I have hereunto subscribed my name and affixed the seal of the said
insurance companies this 19TH day of JTZT.y
Form F6853-4/2012
,9016 .
Continental Casualty Company
National k'ire.Insurance Company of Hartford
C)A,inuericamQasualty Company of Reading, Pennsylvania
D. Bult
•
Assistant Secretary
Authorizing By -Laws and Resolutions
ADOPTED BY THE BOARD OF DIRECTORS OF CONTINENTAL CASUALTY COMPANY:
This Power of Attorney is made and executed pursuant to and by authority of the following resolution duly adopted by the Board of Directors of the
Company at a meeting held on May 12, 1995:
"RESOLVED: That any Senior or Group Vice President may authorize an officer to sign specific documents, agreements and instruments on behalf of
the Company provided that the name of such authorized officer and a description of the documents, agreements or instruments that such officer may sign
will be provided in writing by the Senior or Group Vice President to the Secretary of the Company prior to such execution becoming effective."
This Power of Attorney is signed by Paul T. Bruflat, Vice President, who has been authorized pursuant to the above resolution to execute power of
attorneys on behalf of Continental Casualty Company.
This Power of Attorney is signed and sealed by facsimile under and by the authority of the following Resolution adopted by the Board of Directors of the
Company by unanimous written consent dated the 25th day of April, 2012:
"Whereas, the bylaws of the Company or specific resolution of the Board of Directors has authorized various officers (the "Authorized Officers") to
execute various policies, bonds, undertakings and other obligatory instruments of like nature; and
Whereas, from time to time, the signature of the Authorized Officers, in addition to being provided in original, hard copy format, may be provided via
facsimile or otherwise in an electronic format (collectively, "Electronic Signatures"); Now therefore be it resolved: that the Electronic Signature of any
Authorized Officer shall be valid and binding on the Company."
ADOPTED BY THE BOARD OF DIRECTORS OF NATIONAL FIRE INSURANCE COMPANY OF HARTFORD:
This Power of Attorney is made and executed pursuant to and by authority of the following resolution duly adopted by the Board of Directors of the
Company by unanimous written consent dated May 10, 1995:
"RESOLVED: That any Senior or Group Vice President may authorize an officer to sign specific documents, agreements and instruments on behalf of
the Company provided that the name of such authorized officer and a description of the documents, agreements or instruments that such officer may sign
will be provided in writing by the Senior or Group Vice President to the Secretary of the Company prior to such execution becoming effective."
This Power of Attorney is signed by Paul T. Bruflat, Vice President, who has been authorized pursuant to the above resolution to execute power of
attorneys on behalf of National fire Insurance Company of Hartford.
This Power of Attorney is signed and sealed by facsimile under and by the authority of the following Resolution adopted by the Board of Directors of the
Company by unanimous written consent dated the 25th day of April, 2012:
"Whereas, the bylaws of the Company or specific resolution of the Board of Directors has authorized various officers (the "Authorized Officers") to
execute various policies, bonds, undertakings and other obligatory instruments of like nature; and
Whereas, from time to time, the signature of the Authorized Officers, in addition to being provided in original, hard copy format, may be provided via
facsimile or otherwise in an electronic format (collectively, "Electronic Signatures"); Now therefore be it resolved: that the Electronic Signature of any
Authorized Officer shall be valid and binding on the Company."
ADOPTED BY THE BOARD OF DIRECTORS OF AMERICAN CASUALTY COMPANY OF READING, PENNSYLVANIA:
This Power of Attorney is made and executed pursuant to and by authority of the following resolution duly adopted by the Board of Directors of the
Company by unanimous written consent dated May 10, 1995:
"RESOLVED: That any Senior or Group Vice President may authorize an officer to sign specific documents, agreements and instruments on behalf of
the Company provided that the name of such authorized officer and a description of the documents, agreements or instruments that such officer may sign
will be provided in writing by the Senior or Group Vice President to the Secretary of the Company prior to such execution becoming effective."
This Power of Attorney is signed by Paul T. Bruflat, Vice President, who has been authorized pursuant to the above resolution to execute power of
attorneys on behalf of American Casualty Company of Reading, Pennsylvania.
This Power of Attorney is signed and sealed by facsimile under and by the authority of the following Resolution adopted by the Board of Directors of the
Company by unanimous written consent dated the 25th day of April, 2012:
"Whereas, the bylaws of the Company or specific resolution of the Board of Directors has authorized various officers (the "Authorized Officers") to
execute various policies, bonds, undertakings and other obligatory instruments of Ince nature; and
Whereas, from time to time, the signature of the Authorized Officers, in addition to being provided in original, hard copy format, may be provided via
facsimile or otherwise in an electronic format (collectively, "Electronic Signatures"); Now therefore be it resolved: that the Electronic Signature of any
Authorized Officer shall be valid and binding on the Company."
Figure: 28 TAC §1.601(a)(3)
1 IMPORTANT NOTICE
To obtain information or make a complaint:
2 You may contact Continental Casualty Company,
National Fire Insurance Company of Hartford,
American Casualty Company of Reading, PA and
Continental Insurance Company at 312-822-5000.
3 You may call Continental Casualty. Company,
National Fire Insurance Company of Hartford,
American Casualty Company of Reading, PA and
Continental Insurance Company's toll-free telephone
number for information or to make a complaint at:
1-877-672-6115
4 You may also write to Continental Casualty
Company, National Fire Insurance Company of
Hartford, American Casualty Company of Reading,
PA and Continental Insurance Company at:
CNA Surety, Surety Claims
151 North Franklin, 17th Floor
Chicago, IL 606
5 You may contact the Texas Department of
Insurance to obtain information on companies,
coverages, rights or complaints at:
1-800-252-3439
6 You may write the Texas Department of
Insurance:
P.O. Box 149104
Austin, TX 78714-9104
Fax: (512) 490-1007
Web: www.tdi.texas.gov
E -Mail: ConsumerProtection@tdi.texas.gov
7 PREMIUM OR CLAIM DISPUTES:
Should you have a dispute conceming your
premium or about a claim you should contact
Continental Casualty Company, National Fire
Insurance Company of Hartford, American Casualty
Company of Reading, PA and Continental Insurance
Company first. If the dispute is not resolved, you
may contact the Texas Department of Insurance.
8 ATTACH THIS NOTICE TO YOUR POLICY:
This notice is for information only and does not
become a part or condition of the attached
document.
Form F8277-6-2018
AVISO IMPORTANTE
Para obtener informacion o para someter una queja:
Puede comunicarse con Continental Casualty
Company, National Fire Insurance Company de
Hartford, American Casualty Company de Reading, PA
y Continental Insurance Company al 312-822-5000.
Usted puede Ilamar al numero de telefono gratis de
Continental Casualty Company, National Fire
Insurance Company de Hartford, American Casualty
Company de Reading, PA y Continental Insurance
Company's para informacion o para someter una
queja al:
1-877-672-6115
Usted tambien puede escribir a Continental Casualty
Company, National Fire Insurance Company de
Hartford, American Casualty Company de Reading,
PA y Continental Insurance Company:
CNA Surety, Surety Claims
151 North Franklin, 17th Floor
Chicago, IL 606
Puede comunicarse con el Departamento de Seguros
de Texas para obtener informacion acerca de
companias, coberturas, derechos o quejas al:
1-800-252-3439
Puede escribir al Departamento de Seguros de
Texas:
P.O. Box 149104
Austin, TX 78714-9104
Fax: (512) 490-1007
Web: www.tdi.texas.gov
E -Mail: ConsumerProtection@tdi.texas.gov
DISPUTAS SOBRE PRIMAS 0 RECLAMOS:
Si tiene una disputa concemiente a su prima o a
un reclamo, debe comunicarse con el Continental
Casualty Company, National Fire Insurance
Company de Hartford, American Casualty Company
de Reading, PA y Continental Insurance Company
primero. Si no se resuelve la disputa, puede
entonces comunicarse con el departamento (TDI).
UNA ESTE AVISO A SU POLIZA: Este aviso es
solo para proposito de informacion y no se
convierte en parte o condicion del documento
adjunto.
00 6116 PAYMENT BOND
BOND NO. 30046791
Contractor as Principal
Name: Berry Contracting LP dba Bav Ltd
Mailing address (principal place of business):
1414 Valero Wav
Corpus Christi, TX 78409
Owner
Name: City of Corpus Christi, Texas
Mailing address (principal place of business):
Engineering Services
1201 Leopard Street
Corpus Christi, Texas 78469
Contract
Project name and number:
Project No. E13090
Morgan Ave from Staples Street to Ocean Drive
(Bond 2014)
Award Date of the Contract: July 16, 2019
Contract Price: $5,187,733.85
Bond
Date of Bond: JULY 19, 2019
(Date of Bond cannot be earlier than Award Date
of Contract)
Surety
Name: CONTINENTAL CASUALTY COMPANY
Mailing address (principal place of business):
5151 SAN FELIPE, SUITE 1200
HOUSTON, TEXAS 77056
Physical address (principa! place of business):
SAME
Surety is a corporation organized and existing
under the laws of the state of: ILLINOIS
By submitting this Bond, Surety affirms its
authority to do business in the State of Texas and
its license to execute bonds in the State of Texas.
Telephone (main number): 713-513-6301
Telephone (for notice of claim):
SEE ATTACHED
Local Agent for Surety
Name: HIGGINBOTHAM INSURANCE AGENCY
Address:
500 N. SHORELINE BLVD., SUITE 1200
CORPUS CHRISTI, TEXAS 78401
Telephone: 361-883-1711
Email Address: memooreCwhieeinbotham.net
The address of the surety company to which any
notice of claim should be sent may be obtained
from the Texas Dept. of Insurance by calling the
following toll-free number: 1-800-252-3439
Payment Bond Form
E13090 Morgan Ave — Staples to Ocean Dr (Bond 2014)
006116-1
7-8-2014
Surety and Contractor, intending to be legally bound and obligated to Owner do each cause this Payment
Bond to be duly executed on its behalf by its authorized officer, agent or representative. The Principal
and Surety bind themselves, and their heirs, administrators, executors, successors and assigns, jointly
and severally to this bond. The condition of this obligation is such that if the Contractor as Principal pays
all claimants providing labor or materials to him or to a Subcontractor in the prosecution of the Work
required by the Contract then this obligation shall be null and void; otherwise the obligation is to remain
in full force and effect. Provisions of the bond shall be pursuant to the terms and provisions of Chapter
2253 and Chapter 2269 of the Texas Government Code as amended and all liabilities on this bond shall
be determined in accordance with the provisions of said Chapter to the same extent as if it were copied
at length herein. Venue shall lie exclusively in Nueces County, Texas for any legal action.
Contracto s Principal
Signature:
Surety
Signature: &z:::_. ID?)en-4—
�rD?)en-4—
q
Name:
Name: ''Q^ Lt'r -
����
Name: MARY Et(kN MOORE
Title: l S4r; 1-•,•A-' n9 M r.
Title: ATTORNEY IN FACT
b
Email Address: Lam„ It. 2.- (�,4,�L 1, Corn
Email Address: memoorePhigginbotham.net
(Attach Power of Attorney and place surety seal below)
END OF SECTION
Payment Bond Form
E13090 Morgan Ave – Staples to Ocean Dr (Bond 2014)
006116-2
7-8-2014
POWER OF ATTORNEY APPOINTING INDIVIDUAL ATTORNEY-IN-FACT
Know All Men By These Presents, That Continental Casualty Company, an Illinois insurance company, National Fire Insurance Company of
Hartford, an Illinois insurance company, and American Casualty Company of Reading, Pennsylvania, a Pennsylvania insurance company (herein called
"the CNA Companies"), are duly organized and existing insurance companies having their principal offices in the City of Chicago, and State of Illinois,
and that they do by virtue of the signatures and seals herein affixed hereby make, constitute and appoint
Mary Ellen Moore, Steve Addkison, Cathleen Bayles, Aaron J Endris, Tricia Balolong, Individually
of Corpus Christi, TX, their true and lawful Attorney(s)-in-Fact with full power and authority hereby conferred to sign, seal and execute for and on their
behalf bonds, undertakings and other obligatory instruments of similar nature
- In Unlimited Amounts -
and to bind them thereby as fully and to the same extent as if such instruments were signed by a duly authorized officer of their insurance companies and
all the acts of said Attorney, pursuant to the authority hereby given is hereby ratified and confirmed.
This Power of Attorney is made and executed pursuant to and by authority of the By -Law and Resolutions, printed on the reverse hereof, duly
adopted, as indicated, by the Boards of Directors of the insurance companies.
In Witness Whereof, the CNA Companies have caused these presents to be signed by their Vice President and their corporate seals to be hereto
affixed on this 26th day of October, 2016.
Continental Casualty Company
National Fire Insurance Company of Hartford
American Catty Company of Reading, Pennsylvania
Paul T. Bruflat # Vice President
State of South Dakota, County of Minnehaha, ss:
On this 26th day of October, 2016, before me personally came Paul T. Bruflat to me known, who, being by me duly sworn, did depose and say: that
he resides in the City of Sioux Falls, State of South Dakota; that he is a Vice President of Continental Casualty Company, an Illinois insurance company,
National Fire Insurance Company of Hartford, an Illinois insurance company, and American Casualty Company of Reading, Pennsylvania, a
Pennsylvania insurance company described in and which executed the above instrument; that he knows the seals of said insurance companies; that the
seals affixed to the said instrument are such corporate seals; that they were so affixed pursuant to authority given by the Boards of Directors of said
insurance companies and that he signed his name thereto pursuant to like authority, and acknowledges same to be the act and deed of said insurance
companies.
My Commission Expires June 23, 2021
CERTIFICATE
I, D. Bult, Assistant Secretary of Continental Casualty Company, an Illinois insurance company, National Fire Insurance Company of Hartford, an
Illinois insurance company, and American Casualty Company of Reading, Pennsylvania, a Pennsylvania insurance company do hereby certify that the
Power of Attorney herein above set forth is still in force, and further certify that the By -Law and Resolution of the Board of Directors of the insurance
companies printed on the reverse hereof is still in force. In testimony whereof I have hereunto subscribed my name and affixed the seal of the said
insurance companies this 19TH day °f JULY , 9019 •
Continental Casualty Company
Natiogal l~ ire.Insurance Company of Hartford
t.'ineridari•(Oasualty Company of Reading, Pennsylvania
Form F6853-4/2012
t'1
D. Bult
Assistant Secretary
Authorizing By -Laws and Resolutions
ADOPTED BY THE BOARD OF DIRECTORS OF CONTINENTAL CASUALTY COMPANY:
This Power of Attorney is made and executed pursuant to and by authority of the following resolution duly adopted by the Board of Directors of the
Company at a meeting held on May 12, 1995:
"RESOLVED: That any Senior or Group Vice President may authorize an officer to sign specific documents, agreements and instruments on behalf of
the Company provided that the name of such authorized officer and a description of the documents, agreements or instruments that such officer may sign
will be provided in writing by the Senior or Group Vice President to the Secretary of the Company prior to such execution becoming effective."
This Power of Attorney is signed by Paul T. Bruflat, Vice President, who has been authorized pursuant to the above resolution to execute power of
attorneys on behalf of Continental Casualty Company.
This Power of Attorney is signed and sealed by facsimile under and by the authority of the following Resolution adopted by the Board of Directors of the
Company by unanimous written consent dated the 25th day of April, 2012:
"Whereas, the bylaws of the Company or specific resolution of the Board of Directors has authorized various officers (the "Authorized Officers") to
execute various policies, bonds, undertakings and other obligatory instruments of like nature; and
Whereas, from time to time, the signature of the Authorized Officers, in addition to being provided in original, hard copy format, may be provided via
facsimile or otherwise in an electronic format (collectively, "Electronic Signatures"); Now therefore be it resolved: that the Electronic Signature of any
Authorized Officer shall be valid and binding on the Company."
ADOPTED BY THE BOARD OF DIRECTORS OF NATIONAL FIRE INSURANCE COMPANY OF HARTFORD:
This Power of Attorney is made and executed pursuant to and by authority of the following resolution duly adopted by the Board of Directors of the
Company by unanimous written consent dated May 10, 1995:
"RESOLVED: That any Senior or Group Vice President may authorize an officer to sign specific documents, agreements and instruments on behalf of
the Company provided that the name of such authorized officer and a description of the documents, agreements or instruments that such officer may sign
will be provided in writing by the Senior or Group Vice President to the Secretary of the Company prior to such execution becoming effective."
This Power of Attorney is signed by Paul T. Bruflat, Vice President, who has been authorized pursuant to the above resolution to execute power of
attorneys on behalf of National fire Insurance Company of Hartford.
This Power of Attorney is signed and sealed by facsimile under and by the authority of the following Resolution adopted by the Board of Directors of the
Company by unanimous written consent dated the 25th day of April, 2012:
"Whereas, the bylaws of the Company or specific resolution of the Board of Directors has authorized various officers (the "Authorized Officers") to
execute various policies, bonds, undertakings and other obligatory instruments of like nature; and
Whereas, from time to time, the signature of the Authorized Officers, in addition to being provided in original, hard copy format, may be provided via
facsimile or otherwise in an electronic format (collectively, "Electronic Signatures"); Now therefore be it resolved: that the Electronic Signature of any
Authorized Officer shall be valid and binding on the Company."
ADOPTED BY THE BOARD OF DIRECTORS OF AMERICAN CASUALTY COMPANY OF READING, PENNSYLVANIA:
This Power of Attorney is made and executed pursuant to and by authority of the following resolution dub' adopted by the Board of Directors of the
Company by unanimous written consent dated May 10, 1995:
"RESOLVED: That any Senior or Group Vice President may authorize an officer to sign specific documents, agreements and instruments on behalf of
the Company provided that the name of such authorized officer and a description of the documents, agreements or instruments that such officer may sign
will be provided in writing by the Senior or Group Vice President to the Secretary of the Company prior to such execution becoming effective."
This Power of Attorney is signed by Paul T. Bruflat, Vice President, who has been authorized pursuant to the above resolution to execute power of
attorneys on behalf of American Casualty Company of Reading, Pennsylvania.
This Power of Attorney is signed and sealed by facsimile under and by the authority of the following Resolution adopted by the Board of Directors of the
Company by unanimous written consent dated the 25th day of April, 2012:
"Whereas, the bylaws of the Company or specific resolution of the Board of Directors has authorized various officers (the "Authorized Officers") to
execute various policies, bonds, undertakings and other obligatory instruments of like nature; and
Whereas, from time to time, the signature of the Authorized Officers, in addition to being provided in original, hard copy format, may be provided via
facsimile or otherwise in an electronic format (collectively, "Electronic Signatures"); Now therefore be it resolved: that the Electronic Signature of any
Authorized Officer shall be valid and binding on the Company."
Figure: 28 TAC §1.601(a)(3)
1 IMPORTANT NOTICE
To obtain information or make a complaint:
2 You may contact Continental Casualty Company,
National Fire Insurance Company of Hartford,
American Casualty Company of Reading, PA and
Continental Insurance Company at 312-822-5000.
3 You may call Continental Casualty. Company,
National Fire Insurance Company of Hartford,
American Casualty Company of Reading, PA and
Continental Insurance Company's toll-free telephone
number for information or to make a complaint at:
1-877-672-6115
4 You may also write to Continental Casualty
Company, National Fire Insurance Company of
Hartford, American Casualty Company of Reading,
PA and Continental Insurance Company at:
CNA Surety, Surety Claims
151 North Franklin, 17th Floor
Chicago, IL 606
5 You may contact the Texas Department of
Insurance to obtain information on companies,
coverages, rights or complaints at:
1-800-252-3439
6 You may write the Texas Department of
Insurance:
P.O. Box 149104
Austin, TX 78714-9104
Fax: (512) 490-1007
Web: www.tdi.texas.gov
E -Mail: ConsumerProtection@tdi.texas.gov
7 PREMIUM OR CLAIM DISPUTES:
Should you have a dispute concerning your
premium or about a claim you should contact
Continental Casualty Company, National Fire
Insurance Company of Hartford, American Casualty
Company of Reading, PA and Continental Insurance
Company first. If the dispute is not resolved, you
may contact the Texas Department of Insurance.
8 ATTACH THIS NOTICE TO YOUR POLICY:
This notice is for information only and does not
become a part or condition of the attached
document.
Form F8277-6-2018
AVISO IMPORTANTE
Para obtener informacion o para someter una queja:
Puede comunicarse con Continental Casualty
Company, National Fire Insurance Company de
Hartford, American Casualty Company de Reading, PA
y Continental Insurance Company al 312-822-5000.
Usted puede Ilamar al numero de telefono gratis de
Continental Casualty Company, National Fire
Insurance Company de Hartford, American Casualty
Company de Reading, PA y Continental Insurance
Company's para informacion o para someter una
queja al:
1-877-672-6115
Usted tambien puede escribir a Continental Casualty
Company, National Fire Insurance Company de
Hartford, American Casualty Company de Reading,
PA y Continental Insurance Company:
CNA Surety, Surety Claims
151 North Franklin, 17th Floor
Chicago, IL 606
Puede comunicarse con el Departamento de Seguros
de Texas para obtener informacion acerca de
companias, coberturas, derechos o quejas al:
1-800-252-3439
Puede escribir al Departamento de Seguros de
Texas:
P.O. Box 149104
Austin, TX 78714-9104
Fax: (512) 490-1007
Web: www.tdi.texas.gov
E -Mail: ConsumerProtection@tdi.texas.gov
DISPUTAS SOBRE PRIMAS 0 RECLAMOS:
Si tiene una disputa concemiente a su prima o a
un reclamo, debe comunicarse con el Continental
Casualty Company, National Fire Insurance
Company de Hartford, American Casualty Company
de Reading, PA y Continental Insurance Company
primero. Si no se resuelve la disputa, puede
entonces comunicarse con el departamento (TDI).
UNA ESTE AVISO A SU POLIZA: Este aviso es
solo para proposito de informacion y no se
convierte en parte o condicion del documento
adjunto.