HomeMy WebLinkAbout032145 ORD - 06/23/2020 Ordinance authorizing Developer Participation Agreement with MPM
Development, LP, to reimburse developer up to $874,000 for oversizing
required for a master planned water grid main; authorizing Water Grid Main,
Water Distribution Main, Wastewater Trunk Main, and Wastewater
Collection Line Extension Construction Reimbursement Agreements with
MPM Development, LP to install grid mains, water distribution mains,
wastewater trunk main, and wastewater collection lines for a planned
residential subdivision with completion within 18 months; appropriating
$154,126.23 from the Water Arterial Transmission & Grid Main Trust Fund,
$16,673.25 from the Water Distribution Main Trust Fund, $75,706.88 from the
Sanitary Sewer Trunk System Main Trust Fund, and $45,607.42 from the
Sanitary Sewer Collection Line Trust Fund to reimburse the developer per
the agreements.
WHEREAS, City Ordinance 032063 amended the City's Water Distribution System Master
Water Plan for South of Oso Creek to provide a new alignment of the 16" Grid Main located on
County Road 33 requiring oversizing for Kings Landing subdivision;
WHEREAS, it is in the best interests of the City to have the water distribution system
infrastructure installed by the Developer in conjunction with the Owner's final Plat;
WHEREAS, Section 212.071 of the Texas Local Government Code authorizes a
municipality to make a contract with a developer of a subdivision or land in the municipality to
construct public improvements related to the subdivision or land;
WHEREAS, under the UDC, the Developer is eligible for reimbursement of the Developer's
costs for the construction of the sanitary sewer trunk main line, water arterial and grid main line,
wastewater collection line and water distribution line;
WHEREAS,the Developer has submitted an application for reimbursement of the costs for
installing the Trunk Main Line, Collection Line, Water Grid Main; and Distribution Line; and
WHEREAS, it is to the best interest of the City that the wastewater trunk main line, water
arterial and grid main line, wastewater collection line and water distribution line be constructed to
its ultimate capacity under the City's applicable Master Plan;
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF CORPUS CHRISTI,
TEXAS:
SECTION 1. The City Manager or designee is authorized to execute a developer participation
agreement("Agreement")with MPM Development, LP, ("Developer"), for the City's participation
of the cost to construct the 16-inch Master Planned Water Arterial Transmission and Grid Main
Line in order to complete the Grid Main Loop, between CR-33 and FM-43, in accordance with
the adopted Water Master Plan South of Oso Creek, Corpus Christi, Nueces County, Texas.
SECTION 2. Funding in the amount of $874,000.00 is appropriated from the No.4010-
21805 Water Fund; Q
SECTION 3 . The City Manager or designee is authorized to execute a Water Arterial z
Transmission and Grid Main Construction and Reimbursement Agreement, Distribution Main
Line Construction and Reimbursement Agreement, Wastewater Trunk Main Line
Construction Reimbursement Agreement, and Wastewater Collection Line Extension Q
Construction and Reimbursement Agreement attached hereto, with MPM Development, LP
for the construction and installation of a 16-inch and a 12-inch water transmission and grid
main line, a 8-inch water distribution main line, a 18-inch wastewater trunk main line, and a
032145
12-inch wastewater collection line, for the development of the platted property known as
Kings Landing, Corpus Christi, Texas.
SECTION 4. Funding in the amount of $154,126.23 is appropriated from the No.4030-
21805 Water Arterial Transmission and Grid Main Trust, and $16,673.25 is appropriated
from the No. 4030-21806 Water Distribution Main Trust Fund, $75,706.88 is appropriated from
the No.4220-21800 Sanitary Sewer System Trunk Main Trust Fund and $45,607.42 is
appropriated from the No. 4220-21801 Sanitary Sewer Collection Line Trust Fund, to reimburse
the Developer for the construction of a 16-inch and a 12-inch water transmission and grid main
line, a 8-inch water distribution main line, a 18-inch wastewater trunk main line, and a 12-inch
wastewater collection line, and construction improvements in accordance with the Agreements.
That the foregoing ordinance was read for the first time and passed to its second reading on this
the Lr day of 750,( , 2020, by the following vote:
Joe McComb AQ Michael Hunter
Roland Barrera p �-,/v Ben Molina A_`1,Q
Rudy Garza A"4Everett Roy P� `` (1
Paulette M. Guajardo ' ‘,r( Greg Smith 1'Y
ix.
Gil Hernandez _______4___
That the foregoing ordinance was read for the second time and passed finally on this the or,--,ra
day of `,'y.f s, )._ 2020, by the following vote:
Joe McComb Q..._ Michael Hunter
Roland Barrera
Pc-F—
Ben Molina AL--)K
Rudy Garza I Everett Roy ,
Paulette M. Guajardo Greg Smith
Gil Hernandez
A41-1(--
PASSED AND APPROVED on this the )-----1[6'
- day of -3unQ, , 2020.
ATTEST:
42'L 'C'i t-4-4;1-1AA-e----
Rebecca Huerta Jo cComb
El City Secretary May r
I
I
3
O321 /M
CITY OF CORPUS CHRISTI
CERTIFICATION OF FUNDS
(City Charter Article IV, Sections 7 & 8)
I, the Director of Financial Services of the City of Corpus Christi, Texas (or his/her duly authorized
representative), hereby certify to the City Council and other appropriate officers that the money required
for the current fiscal year's portion of the contract, agreement, obligation or expenditure described
below is in the Treasury to the credit of the Fund specified below, from which it is to be drawn, and has
not been appropriated for any other purpose. Future payments are subject to annual appropriation
by the City Council.
City Council Action Date: June 16, 2020 Legistar Number: 20-0504
Agenda Item:
Ordinance authorizing Developer Participation Agreement with MPM Development, LP, to reimburse
developer up to $874,000 for oversizing required for a master planned water grid main; authorizing
Water Grid Main, Water Distribution Main, Wastewater Trunk Main, and Wastewater Collection
Line Extension Construction Reimbursement Agreements with MPM Development, LP to install grid
mains, water distribution mains, wastewater trunk main, and wastewater collection lines for a planned
residential subdivision with completion within 18 months; appropriating $154,126.23 from the Water
Arterial Transmission & Grid Main Trust Fund, $16,673.25 from the Water Distribution Main Trust Fund,
$75,706.88 from the Sanitary Sewer Trunk System Main Trust Fund, and $45,607.42 from the Sanitary
Sewer Collection Line Trust Fund to reimburse the developer per the agreements. (District 3)
Amount Required: (Amount to be Certified) $ $1,166,113,78
Fund Name Accounting Unit Account No. Activity No. Amount
Water Arterial
Transmission & Grid Main 4030 209010 $154,126.23
Trust
Water Distribution Main 4030 209020
Trust $16,673.25
Sanitary Sewer Trunk 4220 250410
Main Trust $75,706.88
Sanitary Sewer Collection
Line Trust 4220 250420 $45,607.42
Water Operating Fund 4010-30000-041 540450
$874,000.00
Total
$ 1,166,113.78
❑ Certification Not Required
Director of Financial Services
Date: 'line l( ( )( c)0
1