HomeMy WebLinkAboutM1989-0230 - 08/15/1989Motions - 8/15/89 14. Motion approving the following actions relative to the Raw Water Reservoir and Sludge Lagoon project: a. Approving Change Order No. 1 in the amount of $98,638.82 for various items necessary to complete the project and authorizing a 38-day time extension for substantial completion and a 45-day extension for final completion, b. Suspending the charging of time on this project until water demand decreases and remaining items can be completed, c. Assessing liquidated damages in the amount of $20,500 for 41 days overrun to substantial completion and $3,500 for 14 days overrun to full completion, and d. Author~zing reduction of retainage from ten percent to five percent. M89-0230 ,vitCi{OFILMED