HomeMy WebLinkAboutC2021-037 - 2/9/2021 - Approved CITY OF CORPUS CHRISTI c.o,,...•fie„.., ENGINEERING SERVICES Io.l' 1 CHANGE ORDER J ...r CHANGE ORDER NO: 3 CHANGE ORDER DATE: 1/12/2021 PROJECT: Holly Rd.-Rodd Field to Ennis Joslin PROJECT NUMBER: 18021 A CONTRACTOR: Ray,LTD. ORIGINAL CONTRACT TIME: 540 CD's ENGINEER: LNV Engineering Make the following additions,modifications or deletions to the work described in the Contract Documents: ADDITIONS Quantity Unit Unit Price Total Install 30"Waterline+30"Line Stop(Holly Rd.-Woodbend to Toben) Section F-Water Improvements New TCP+Barricades I LS S 4,052.17 S 4,052.17 New SWPPP 1 LS S 962.18 S 962.18 New Exploratory Digging 1 DAY S 4,677.71 S 4,677.71 New Excavation 2 DAY S 2,645.78 S 5,291.56 New Dewatering 30"Waterline 10 HRS S 146.1630 S 1,461.63 New 30"Linestop+Conc Support 1 LS S 85,601.21 S 85,601.21 New New 30"Valve I EA S 18,824.03 S 18,824.03 New FDR Path(I0'x12'&10k10') 220 SY S 82.3219 S 18,110.81 New Cleanup 1 LS S 1,832.44 S 1,832.44 Ncw Contingency Item(30"Fitting may be required pending exploratory findings) 1 AL S 27,990.39 S 27,990.39 Additional Calendar Days due to:added Scope 10 DAY S - S - Additions Total: $ 168,804.13 DELETIONS None I n/a 0 LS S - S - Deletions Total: $ - Additional Calendar Days requested 10 NET TOTAL OF THIS CHANGE ORDER: $ 168,804.13 Why was this Change necessary: During a planned water outage on the!lolly Rd.project,it was discovered that an existing valve was damaged and as a result another valve further upstream had to be closed which caused outages to several residents.As a result,the Utility Department has requested that a new 30"water valve be installed upstream of the damaged valve to provide more control over system and help prevent unnecessary impact to residents in the future.To perform this work the contractor will need to install a 30"line stop which will prevent a widespread outage while allowing the contractor to install the new 30"Valve and while the Utility Department simultaneously repairs the damaged valve. The compensation agreed upon in this Change Order is full,complete andfinal payment for all costs the Contractor may incur as a result of or relating to this change whether said costs are known, unknown,foreseen or unforseen at this time,including without!irritation,any cost for delay,extended overhead,ripple or impact cost,or any other effect an changed or unchanged work as a result of this Change Order. Original Contract Amount $ 8,345,032.20 Maximum Change Order Contingency Amount(25%) $ 2,086,258.05 Remaining Available Contingency Amount(including this CO) S 1,733,606.99 Previously Approved Change Order Amount $ 183,846.93 Proposed Change Order Amount $ 168,804.13 Revised Contract Amount $ 8,697,683.26 Percent of Total Change Orders(including this CO) 4.23% Original Contract Time for Substantial Completion 540 CD's Notice to Proceed Date 10/18/2019 Original Substantial Completion Date 4/10/2021 Previously Approved Change Order Time 14 CD's Additional Time on This Change Order 10 CD's Revised Contract Time for Substantial Completion 564 CD's Revised Substantial Completion Date 5/4/2021 REVIEWED BY: Initial Date REQUESTED BY: Bay,LTD. Eng.Proj.Specialist Karissa O'Neill KLO 12/18/2020 Constr.Supervisor Amie Wojtasczyk ADI4 12/29/2020 O\I t Z Constr.Inspector Geoffrey Mayer G'4 12/30/2020 U\NI\ a-�7 Z. 1202.( Constr.Sr.Project Mgr. Ruben Banera RB 12/30/2020 Matthew Beal Date k Sr.Estimator,Highway Division,Bay LTD. Brett Van Digitally signetek �t� CORPUS CHRISTI Van Hazel —Date:2021.01.12 17:00:35 FUND: 4099-041 n/a Hazel ACCOUNT: 550910 n/a RECOMMENDED BY: -06'00' ACTIVITY: 18021-A-4099-EXP n/a Brett Van Hazel Date AMOUNT: $168,804.13 n/a Construction Eng / Digitally signed by Jeff /Edmonds Date:2021.01.1916:48:40 /� RECOMMENDED BY: -06'00' APPROVED RY: 4/2--N.-------v-- 9-at-ell Jeff H.Edmonds Date Michael Rodriguez Date Director of Engineering Services Chief of Staff Pgitally tlgned by bent Akllya, / DN:m=benl Mcfyu.o.uu. Electronic Approval 1/19/2021 02 01.19 . 13,51 <"m.r."5 RECOMMENDED BY: APPROVED AS TO atemnoLwnsl+easar Eddie Houlihan,Dircc or Date : LNlcilyar anagcmcnl and Br rg t QiIq Assistant City Attorney SCANKED REBECCA HUERTA � �� ��� ` IC i3 r1ITT/,r-"Mr-,A I-1%1