HomeMy WebLinkAbout033088 RES - 06/27/2023Resolution awarding a construction contract to Bay Ltd. of Corpus Christi
for the construction of Rodd Field Road from Yorktown Boulevard to Adler
Drive with new asphalt pavement, multi -use shared path, roadside ditches,
ADA compliant curb ramps, traffic signal improvements, signage,
pavement markings, street lighting and utility improvements in an amount
of $5,199,500.00, located in Council District 5 with FY 2023 funding
available from the Bond 2020 Proposition A, Storm Water, Wastewater,
Water Capital Funds and Gas.
Now, therefore, be it resolved by the City Council of the City of Corpus Christi,
Texas:
SECTION 1. The City Manager or designee is authorized to execute a construction
contract with Bay Ltd of Corpus Christi for construction of Rodd Field Road, from
Yorktown Boulevard to Adler Drive, in the amount of $5,199,500.
PASSED AND APPROVED on the an day of , 2023:
Paulette Guajardo
Roland Barrera
Sylvia Campos
Gil Hernandez
Michael Hunter
Jim Klein
Mike Pusley
Everett Roy
Dan Suckley
ATTEST:
A-yz_
CI OF CORPUS CHRISTI
Rebecca Huerta
City Secretary
033 088
Paulette Guajardo
Mayor
SCANNED
CITY OF CORPUS CHRISTI
CERTIFICATION OF FUNDS
(City Charter Article IV, Sections 7 & 8)
I, the Director of Financial Services of the City of Corpus Christi, Texas (or his/her duly authorized
representative), hereby certify to the City Council and other appropriate officers that the money required
for the current fiscal year's portion of the contract, agreement, obligation or expenditure described
below is in the Treasury to the credit of the Fund specified below, from which it is to be drawn, and has
not been appropriated for any other purpose. Future payments are subject to annual appropriation
by the City Council.
City Council Action Date: June 27, 2023 Legistar Number: 23-0798
Agenda Item:
Resolution awarding a construction contract to Bay Ltd. of Corpus Christi, Texas, for the construction of
Rodd Field Road from Yorktown Boulevard to Adler Drive with new asphalt pavement, multi -use shared
path, roadside ditches, ADA compliant curb ramps, traffic signal improvements, signage, pavement
markings, street lighting and utility improvements in an amount of $5,199,500.00, located in Council
District 5 with FY 2023 funding available from the Bond 2020 Proposition A, Storm Water, Wastewater,
Water Capital Funds and Gas.
Amount Required: $5,199,500.00
Fund Name
Accounting
Unit
Account No.
Activity No.
Amount
ST2021 Bd20 A
3558-33-89
550910
21064 -3558 -EXP
$3,157,172.31
StrmWtr 2023 CIP
4534-47-89
550910
21064 -4534 -EXP
$726,632.62
Water 2023 CIP
4486-45-89
550910
21064 -4486 -EXP
$980,332.10
WW 2023 CIP
4259-46-89
550910
21064 -4259 -EXP
$302,324.40
Gas 2023 CIP
4562-11-89
550910
21064 -4562 -EXP
$33,038.57
Overall Contract Total
$5,199,500.00
Total: $5,199,500.00
irector of Fi�j �r}p I Services
Date: Ki If