HomeMy WebLinkAbout033272 ORD - 01/30/2024 Ordinance authorizing execution of all documents with American
Electric Power, Texas (AEP), associated with the construction of the
Inner Harbor Seawater Desalination Treatment Plant Interconnection
Project in the amount of $3,062,880.00 and conveyance of property
rights and/or modifications of existing contracts for the purchase of
real property to transfer interest(s) in property as required by AEP or
its authorized related entities for the construction of said project,
located in Council District 1.
WHEREAS, there is a statutory exception for this procurement in Local
Government Code, Section 252.022 (2) (7) (C), items that are available from only one
source, including gas, water and other utility services.
Now, therefore, be it ordained by the City Council of the City of Corpus Christi,
Texas:
SECTION 1. The City Council specifically finds that the foregoing statements included in
the preamble of this ordinance are true and correct and adopts such findings for all intents
and purposes related to the authorization of this procurement.
SECTION 2. The City Manager or designee is authorized to execute all documents with
American Electric Power, Texas (AEP), associated with the construction of the Inner
Harbor Seawater Desalination Treatment Plant Interconnection Project in the amount of
$3,062,880.00.
SECTION 3. The City Manager or designee is authorized to convey property rights and/or
modify existing contracts for the purchase of real property to transfer interest(s) in
property as required by AEP or its authorized related entities for the construction of said
project.
Introduced and voted on the rf day of 0-11Lko , 2024.
PASSED and APPROVED on the day of .30.." , 2024.
ATTEST:
Paulet e Guajardo,''your , Re ecca Huerta, City Secretary
033272 SCANNED
CITY OF CORPUS CHRISTI
CERTIFICATION OF FUNDS
(City Charter Article IV, Sections 7 & 8)
I, the Director of Financial Services of the City of Corpus Christi, Texas (or his/her duly authorized
representative), hereby certify to the City Council and other appropriate officers that the money required
for the current fiscal year's portion of the contract, agreement, obligation or expenditure described
below is in the Treasury to the credit of the Fund specified below, from which it is to be drawn, and has
not been appropriated for any other purpose. Future payments are subject to annual appropriation
by the City Council.
City Council Action Date: January 23, 2024 Legistar Number: 24-0072
Agenda Item:
L3ra"1`AL`Z, authorize the execution of all documents with American Electric Power, Texas, associated
with construction of the interconnection to the of the Inner Harbor Seawater Desalination Treatment Plant
to the Electric Council of Texas (ERCOT) electric transmission grid in the amount of$3,062,880.00, and
for the conveyance of property rights and/or modifications of existing contracts for the purchase of real
property to transfer interest(s) in property as required by American Electric Power, Texas or its authorized
related entities for the construction of said project, located in Council District 1 with FY 2024 funding
available from the State Water Implementation Revenue Fund Texas Loan-2020.
Amount Required: $3,062,880.00
Fund Name Fund Department Org Account Activity No. Amount
2020C SWIRFT Bd 4483 45 89 550950 E15117-01-4483-EXP $3,062,880.00
Total $3,062,880.00
Gott, -
'rector of Financial Services
Date: 1� '3)0 1 k—e--